Entry  Monday, January 29, 2018, 06:51, David Wang, Conditioning Station, Maintenance, TM1, , TCS and TM1 vacuum pumps switched off 

TCS and Tm1 vacuum pumps are switched off this morning. TM1 TP1and TP2 work fine during this test period. Tm1 will be moved back to silo this morning.

TM1 IG1 stopped work during the test period. It could be broken. We will only replace this gauge if TM1 is used in ITW again.

Entry  Wednesday, January 24, 2018, 13:30, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 has been moved to TCS this morning 

Tm1 has been moved to TCS this morning. All turbo-pumps are started successfully at TCS and TM1.

Entry  Monday, January 22, 2018, 07:47, David Wang, Conditioning Station, Standard Operation, TM3, , Restarted TM3 vacuum sysytem after site power bump 

All TCS and TM3  vacuum pumps are started successfully.

Entry  Wednesday, January 17, 2018, 13:54, David Wang, Conditioning Station, Standard Operation, TM3, , Start TM3 turbo pumps at TCS.  

TM3 turbo-pumps are started at TCS. We will keep pumps running until next Wednesday.

Entry  Wednesday, January 17, 2018, 10:38, Anders Mjos, Spent Target Vault, Standard Operation, TM1, , Old TM1 Source Tray moved to Cyclotron basement 

The old TM1 Source Tray from 2011 has been moved to Cyclotron basement this morning. Source tray was stored in location 10. The box was moved from the vault to the ante-room yesterday. No contamination was found on the box. Photos

Entry  Wednesday, January 17, 2018, 06:51, David Wang, Conditioning Station, Standard Operation, , , Stop TCS vacuum pumps  

I stopped TCS vacuum pumps for coming TM3 move.

Entry  Tuesday, January 16, 2018, 10:36, Anders Mjos, Spent Target Vault, Standard Operation, TM2, , Old TM2 Source Tray moved to Cyclotron basement 

The old TM2 Source Tray from 2009 has been moved to Cyclotron basement this morning. Source tray was stored in location 9. The box was moved from the vault to the ante-room yesterday. No contamination was found on the box.

Entry  Tuesday, January 16, 2018, 06:50, David Wang, ITE/ITW Cooling, Standard Operation, , , Field measurement on old resin tank in silo 

The old resin tank has been stored in silo since last year March.  Without crane the tank up, We use the pole monitor measured the field around the bottom of the tank in silo. The average contact field on the bottom is about 4.0msv/hr. @0.5meter , the field is about  900usv/hr. It is still too hot to remove it.

Entry  Thursday, January 04, 2018, 13:28, Anders Mjos, Conditioning Station, Maintenance, , , Troubleshooting IG1S 

TCS:IG1S is reporting vacuum levels that seem to be too low (1E-10 to 1E-8 Torr). The gauge was connected to the controller for IG1, which showed the same value. A degas was performed for ~5 min.

Entry  Tuesday, January 02, 2018, 15:17, Anders Mjos, Conditioning Station, Maintenance, , , Tested chiller 

Tested all 3 compressors and MP2

Entry  Tuesday, January 02, 2018, 14:47, Anders Mjos, Conditioning Station, Standard Operation, , , Pumping on secondary vacuum 

Tuesday, January 02, 2018, 14:45: TP1S started

Entry  Tuesday, January 02, 2018, 11:28, David Wang, ITE, Standard Operation, TM4, , ITE annual water interlock check. 

Eric and I finished ITE annual water interlock check. Everything works properly.

Entry  Tuesday, January 02, 2018, 10:46, David Wang, ITE/ITW Cooling, Standard Operation, , , Start High active water system. 

High active water system  was  checked before restart. A small water leak on resin can supply valve was found. It is fixed. MP1 and MP2 were started and checked separately. System pressure and flow rate are normal.MP1 is in operation now. 

Entry  Friday, December 22, 2017, 11:09, Anders Mjos, ITW, Standard Operation, TM2, , Shut down High Active Cooling water 

Stopped MP1 today in preparation for the power outage over the holidays. both P-25 and P-26 breakers have been switched off to prevent inadvertent start of system

Entry  Thursday, December 21, 2017, 15:11, Anders Mjos, Conditioning Station, Maintenance, , , Powered down devices 

Powered down mechanical pumps in ISAC-I Experimental hall, vacuum gauge and turbo pump controllers in ISAC-I B2 North Hot Cell service area

Entry  Tuesday, December 19, 2017, 10:41, Anders Mjos, Crane, Maintenance, , , Crane powered down 

The target hall crane has been powered down by Don today in preparation for the power shutdown over the Holidays.

Entry  Tuesday, December 19, 2017, 10:40, Don Jackson, Crane, Maintenance, , , Crane Power during winter break 

 The power to the crane and controls were turned off using the power switch in the Crane Control room.  The main disconnect switch in the target hall was not touched.

All site power will be off for a period of time during the Christmas break and this removes the crane from any issues when power is restored.

Entry  Wednesday, December 13, 2017, 15:32, Anders Mjos, Assembly/Bench Test, Maintenance, TM2, , Source Tray inspection 

The Source tray was inspected in the RH shop today by Anders, Friedhelm and Jens. The routing of the lines are satisfactory, however a design proposal to remove the ground electrode line will be made. This design will have to ensure a proper connection from the electrode to ground (using the window cooling lines). All other lines are OK at this point. Some fine adjustments are expected after brazing and soldering to maintain high voltage separation. Photos are available on DocuShare Collection-21401

Entry  Wednesday, December 06, 2017, 09:33, Anders Mjos, Conditioning Station, Maintenance, , , Running chiller for maintenance tech 

 Dakine is on site to do maintenance on the chiller. The tech requested the chiller to operate.

Entry  Friday, December 01, 2017, 16:42, Isaac Earle, North Hot-Cell, Repair, , , NHC manipulator service visit 1512175169704.jpg1512175181553.jpg

Pete Dudley, manipulator service technician from CRL, was on site from Nov 27-30 to service the NHC Model N manipulators (See E-log entry #1578 for background).

He began by evaluating the motion selection and electric drive of the manipulator installed on the blue service cart.  This manipulator had chip A0166R01, same as the right side manipulator which had the failure described in E-Log 1578.  Pete noted that the arm was very slow to switch between the different drive directions, and had a significant lag between when the switch for motion was released, and when the motor actually stopped driving.  This was the case with all directions.  Because of this, he suspected that the right arm Z tape broke because when the manipulator reached the switch at the end of travel, the motor did not stop quickly enough causing over tension and snapping the tape.  A newer chip, A0166R04, was removed from the spare master arm (received Spring 2017), and installed into the master arm on the blue cart.  The test was repeated, and this time the motion selection and drive worked as expected.  The situation which previously caused failure was evaluated:  slave end fully extended in Z, master end fully collapsed in Z.  In this configuration the arm was moved back and forth in the Y direction.  No tape failure occurred, and the Z motion tape tension seemed normal.  Y motion drive was attempted, and was not possible, as expected.  This test was repeated in the opposite configuration (slave end fully collapsed, master end fully extended) with the same results.  Full drive speed was used for all tests.

The right side slave arm (with broken Z tape) was then removed and transported to the HCSA.  Using the bench mounted locking plate, the broken Z tape was replaced, and a full inspection and cable/tape tensioning was performed.  Pete accidentally broke the Z tape on the right side master arm while investigating the failure, which was also replaced.

The other two slave arms were also both inspected, tensioned, and tested in the same way.  Then all three were each in turn installed to the master arm #9348 on the blue manipulator transport cart where all mechanical motions and drives were tested (except X, because mounted on cart), the failure situation described above was also tested for all three slave arms.

The left side manipulator was then installed into the wall.  It was necessary to remove the lead sheilding on the thru-tube and machine it down approximtaely 0.070" in order for the arm to fit into the wall tube.  After installation, the manipulator motions and drives were tested again including the X motion, and the failure scenario situation was also re-tested.  Chad used the left side manipulator to remove and re-install the pre-filter mounted on the west side partition wall.  He also confirmed that he could reach the east wall electrical outlets and the outlets, gas fittings in front of the window.

The right side slave arm was adjusted so that the Y position was moved 1/2 turn of the shaft drive towards the window (this is the maximum adjustment possible before it hits a hard stop).  This was done so that the operator can more easily reach the outlets and air/gas connections inside the cell in front of the window.  Because both the master and slave ends protrude further out from the wall compared to the E-HD manipulators for the SHC, this modification makes the NHC manipulators feel a bit more like the SHC manipualtors for the operator.  After the adjustment, the right side slave arm was installed.  The left side slave arm was removed, adjusted the same as the right side, then reinstalled.  The spare slave arm was also adjusted in the same way.

The right side manipulator was evaluated through all mechanical motions.  We attempted to remove the A0166R04 chip from the left side, and install in the right in order to try the motion drives, however the pins had been damaged from the previous removal/install, and eventually one pin broke so this was abandoned.  CRL will ship us at least three new A0166R04 chips which should arrive in 2-3 weeks.

Upon completion of the work the location of the different arms is as follows:  Right side master #9351, Left side master #9348, Spare master #9763, Right side slave #9349, Left side slave #9764, Spare slave #9352

1512175169704.jpg

 

1512175181553.jpg