ID Date Author Category Type Module Target/Numberdown Subject
  1340   Thursday, August 25, 2016, 14:25 Travis CaveSpent Target VaultStandard Operation SiC#33Spent Target move

SiC#33 was placed into pail #141 which in turn was placed into slot 2B of the vault. I was 295mS/hr upon removal from the south hot cell.

  1105   Monday, October 19, 2015, 11:53 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 installed on TM2

SiC#32 has been installed on TM2. High current fasteners torqued to 130 in lbs.

  1106   Monday, October 19, 2015, 15:52 Anders MjosSouth Hot-CellStandard OperationTM2SiC#32Electrical and leak check

 An electrical check was completed by Travis C and Anders M. Note ~250 kOhm between Target and 60 kV common. Leak check was done by Dan M and Chad F on HS and Window circuits. No leaks found

  1107   Tuesday, October 20, 2015, 10:18 Travis CaveITWStandard OperationTM2SiC#32Module moved

TM#2 with SiC#32 has been moved from the south hot cell to the west target station.

  1108   Tuesday, October 20, 2015, 12:49 Dan McDonaldITWStandard Operation SiC#32Tm2 hook up In ITW

Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and TP2

  1166   Wednesday, March 16, 2016, 09:20 Travis CaveITEStandard OperationTM2SiC#32module moved

TM#2 with SiC#32 has been moved from the west station to the south hot cell.

  1167   Wednesday, March 16, 2016, 14:23 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 removal Target Module Inspection

SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the left target heater A.

As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector.

  1173   Friday, March 18, 2016, 13:13 Travis CaveConditioning StationStandard OperationTM2SiC#32Electrical Check

Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs.

  1177   Tuesday, March 22, 2016, 10:27 Travis CaveSpent Target VaultStandard Operation SiC#32Spent Target move

SiC#32 has been moved from the south hot cell to the spent target storage. See attached PDF for details.

  1910   Monday, April 29, 2019, 09:32 Travis CaveSpent Target VaultStandard Operation SiC#31,32 and UC#19,20,21Spent targets moved to mini vault.

 The following targets have been moved from the spent target vault to the mini vault:

#127 - SiC#31 (front)

#132 - SiC#32 

#145 - UC#19

#150 - UC#20

#159 - UC#21 (back) 

  2008   Thursday, October 17, 2019, 11:49 Travis CaveSpent Target VaultStandard Operation SiC#31,32 and UC#19,20,21Loading F-308

 The targets in the mini storage have been loaded into the F-308.

  1023   Tuesday, July 28, 2015, 14:40 chad fisherSouth Hot-CellStandard OperationTM4SiC#31 UCx#13SiC#31 removed UCx#13 installed

SiC#31 has been removed from TM4 and UCx#13 installed. UCx#13 connection to the 9 pin connector was VERY VERY tight to the tube heater insulator on both the test jig and module.

 

 

  924   Tuesday, June 02, 2015, 09:43 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 installed

Ta #45 has been removed from TM4 and SIC#31installed.

  925   Tuesday, June 02, 2015, 10:39 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical Check

Electrical check on TM#4 with SiC#31. See attached PDF for details.

  926   Tuesday, June 02, 2015, 11:54 Travis CaveConditioning StationStandard OperationTM4SiC#31Module moved

TM#4 with SiC#31 has been moved from the south hot cell to the conditioning station.

  931   Wednesday, June 03, 2015, 13:01 Anders MjosConditioning StationStandard OperationTM4SiC#31Conditioning SiC#31

PNG1 connected to PNG in service cap (as per David W)

 Wednesday, June 03, 2015, 12:59: Water on

Wednesday, June 03, 2015, 13:04: Staging enabled.

Wednesday, June 03, 2015, 14:02: Auto-ramping to 580 and 200 A at 2 and 1 A/min.

Wednesday, June 03, 2015, 14:03 : BIAS/EL/EE to 20/10/1.5 kV


ISAC operations monitored TCS from Wednesday to Monday


Monday, June 08, 2015, 08:55 : Started cool-down of target

Monday, June 08, 2015, 09:19: BIAS/EL/EE off

Monday, June 08, 2015, 09:32: EE configured to conditioning mode

Monday, June 08, 2015, 10:12 : TGHT and TBHT off

Monday, June 08, 2015, 10:25: BIAS/EL to 20/10 kV

Monday, June 08, 2015, 10:32: BIAS/EL to 30/15 kV

Monday, June 08, 2015, 10:45: BIAS/EL to 40/20 kV. Some bias sparking from ~39 kV

Monday, June 08, 2015, 13:40: BIAS/EL to 47.5/20 kV

Monday, June 08, 2015, 14:35: BIAS/EL to 50/20 kV

Monday, June 08, 2015, 14:39: BIAS/EL to 50/25 kV

Monday, June 08, 2015, 16:54: BIAS/EL to 53/25 kV

Monday, June 08, 2015, 17:03: BIAS/EL/EE off


Tuesday, June 09, 2015, 08:02: BIAS/EL to 30/15 kV

Tuesday, June 09, 2015, 08:07: BIAS/EL to 40/20 kV.

Tuesday, June 09, 2015, 08:13: BIAS/EL to 50/25 kV

Tuesday, June 09, 2015, 08:27: BIAS/EL to 53/25 kV 

Tuesday, June 09, 2015, 08:57: BIAS/EL to 55/25 kV  

Tuesday, June 09, 2015, 09:31: Power supplies tripped on IG2 vacuum after a spark at ~57.5 kV

Tuesday, June 09, 2015, 09:40: BIAS/EL to 40/20 kV.

Tuesday, June 09, 2015, 10:00 : BIAS/EL to 55/25 kV  

Tuesday, June 09, 2015, 10:09: BIAS/EL to 57.5/25 kV

Tuesday, June 09, 2015, 10:22: Sparking activity at 58 kV. Tripped TP2 and BV2. Reduced to 50 kV. Leakage current increased.

Tuesday, June 09, 2015, 10:33: Sparking activity at 55 kV. Reduce to 45 kV. Increased BIAS current limit from 0.25 to 0.30 mA

Tuesday, June 09, 2015, 10:41: BIAS/EL to 50/25 kV. BIAS RDCUR 0.17 mA, was 0.08 mA at 8:13 this morning.

Tuesday, June 09, 2015, 11:28 : Restarted TP2. Tripped.

Tuesday, June 09, 2015, 11:50:  Increased BIAS current limit from 0.30 to 0.35 mA

Tuesday, June 09, 2015, 11:55 : BIAS/EL to 54.5/25 kV for 5 min, 0.12 mA . Reducing to 40 kV for lunch break.

Tuesday, June 09, 2015, 13:07: BIAS/EL to 50/25 kV 

Tuesday, June 09, 2015, 13:27: BIAS/EL to 55/25 kV 

Tuesday, June 09, 2015, 13:40: BIAS/EL to 57/25 kV 

Tuesday, June 09, 2015, 13:49: BIAS/EL to 57.5/25 kV. Increased BIAS current limit from 0.35 to 0.40 mA

Tuesday, June 09, 2015, 14:30: IG1 tripped after spark. Controller seems to be broken. Forced IG1. Fault report submitted June 10th.

Tuesday, June 09, 2015, 14:58: BIAS/EL to 45/25 kV

Tuesday, June 09, 2015, 15:46: BIAS/EL to 55/25 kV

Tuesday, June 09, 2015, 15:55: BIAS/EL to 56/25 kV

Tuesday, June 09, 2015, 17:30: BIAS/EL to 57/25 kV 

Tuesday, June 09, 2015, 17:46: BIAS/EL to 57.5/25 kV 

Tuesday, June 09, 2015, 18:00: BIAS/EL to 58/25 kV

Tuesday, June 09, 2015, 18:30: No sparks for 30 min

Tuesday, June 09, 2015, 18:55: One spark observed. BIAS/EL off.

Tuesday, June 09, 2015, 18:56: Turbos stopped. Stopped water circuit.


Thursday, June 11, 2015: IG1 seems to work again after a power cycle. Controller tested with another IG. Closing Fault report

  938   Wednesday, June 10, 2015, 10:02 Travis CaveITEStandard OperationTM4SiC#31Module moved

TM#4 has been moved from the conditioning station to the east target station.

  1013   Monday, July 27, 2015, 12:12 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical Check

Electrical check of TM#4 post beam with target (SiC#31) on and module without target on. There is a short between the target and EE when the target is on and when the target was removed short went away. See the PDF for details.

  1022   Tuesday, July 28, 2015, 14:36 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 Autopsy

Extraction electrode was removed from SiC#31 and target inspected.

Pictures of findings can be found at          https://documents.triumf.ca/docushare/dsweb/View/Collection-15131

 

 

 

  1027   Thursday, July 30, 2015, 14:05 Travis CaveSpent Target VaultStandard Operation SiC#31Spent target moved

SiC#31 has been moved to the spent target vault. It is in pail #127 and placed in spot 3C of the vault is was 489mSv/hr when removed from the south hot cell. See attached pdf for vault status