1793
|
Tuesday, September 25, 2018, 08:01 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | nSiC#1 | nSiC#1 install |
On September 18th installation of nSiC#1 was attempted on TM2. As usual, new fasteners were tested previous to insertion into hot cell and employed during installation. the last fastener to be installed was for the circuit D block. The fastener/air ratchet stalled immediately indicating a problem. The fastener was removed and a an attempt was made trying a new spare fastener. That fastener also jammed right away but could not be removed or installed any further.
A breaker bar was employed to achieve more torque and the fastener was able to be loosened, although it would not come completely out, dangling and wobbling like it was free. A claw type bar was used to add slight pressure to the fastener while it was loosened allowing the fastener to undo the rest of the way.
Target was removed and discovered that that insulator supporting circuit c and d blocks was quite broken and that a few chunks had fallen off. It was also notice that boefore the breaker bar had been employed that a piece of ceramic was on the table suggesting that the ceramic had been at least partially broken at the time of removal of the previous target. Also, the threads of the insert for circuit d showed damage an swarf.
Swarf was vacuum claned out of the circuit d thread insert and a machine tap ran through the insert twice.
nSiC#1 was reinstalled with new waterline gaskets and new c and d circuit fasteners with a little bit of the first 2-3 threads lightly coated with vacuum grease.
High current fasteners torqued to 130 in lbs. |
Attachment 1: 20180919_132304.jpg
|
|
Attachment 2: 20180919_143535.jpg
|
|
1792
|
Tuesday, September 25, 2018, 07:54 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 is connected for HV test at TCS. |
water loops are by passed on top. All bias, EE, and EL are tied together. Started water system. |
1791
|
Monday, September 24, 2018, 14:50 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#23 | Spent Target Move |
The spent UC#23 target has been moved from the south hot cell to the spent target storage. It was placed in pail #170 and place in spot #4B in the vault. |
1790
|
Monday, September 24, 2018, 10:21 |
Anders Mjos | South Hot-Cell | Standard Operation | TM2 | UC#23 | Post Irradiation Examination (PIE) |
UC#23 experienced short between target and heat shield as it was heated during operation. The inspection of the target after irradiation revealed that the left target leg was close to the heat shield opening and likely the cause of the short. Marks could be seen on the leg indicating contact. See attached photo. More photos are available on DocuShare |
Attachment 1: 20180924_161322929_iOS.jpg
|
|
1789
|
Friday, September 21, 2018, 10:07 |
David Wang | ITW | Standard Operation | TM2 | SiC nano | TM2 with SiC nano target was has been connected in ITW. |
Tm2 with SiC nano has been connected in ITW. See attachment for checklist |
Attachment 1: TM2_with_SiC_nano_connection_in_ITW..pdf
|
|
1788
|
Friday, September 21, 2018, 10:06 |
David Wang | ITW | Standard Operation | TM2 | UCx23 | TM2 was disconnected in ITW. |
TM2 was disconnected in ITW this Tuesday. See attachment for checklist. |
Attachment 1: TM2_UCx_23#_disconnection_in_ITW..pdf
|
|
1787
|
Thursday, September 20, 2018, 14:36 |
Travis Cave | ITW | Standard Operation | TM2 | nSiC#1 | Module move |
TM#2 with nSiC#1 has been moved from the south hot cell to the west target station. |
1786
|
Thursday, September 20, 2018, 14:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | nSiC#1 | Electrical Check |
TM#2 with the nSiC#1 target had its check done on it at the south hot cell see attached for results. |
Attachment 1: Electrical_Chk_TM2_SHC_nSiC#1_Sept-20-2018.pdf
|
|
1785
|
Thursday, September 20, 2018, 08:36 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Electrical Check |
Results of the electrical check on TM#2 with no target after Chad cleaned out the bolt hole on the module where the target mounts. |
Attachment 1: Electrical_Chk_TM2_no_tgt_Sept-20-2018.pdf
|
|
1784
|
Tuesday, September 18, 2018, 12:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | UC#23 | Module move |
TM#2 with UC#23 has been moved from ITW to the south hot cell. The shield plug was also installed remotely as well. |
1783
|
Friday, September 14, 2018, 09:39 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move |
TM#3 with no target has been moved from the north east silo to the conditioning station. |
1782
|
Thursday, September 13, 2018, 16:57 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding and mili-ohm testing |
The following equipment has been connected to the building ground located in the Target Hall by the TCS using 1/2" flat bonding strap:
- NHC roof structure
- NHC/TCS partition wall
- NHC work table
The following equipment has been connected to the building ground by connecting to the work table inside the NHC using 1/2" flat bonding strap:
- Air and gas supply line mounting bracket inside NHC
- Receptacle box mounting bracket inside NHC
- Diagnostic signal box mounting bracket inside NHC
The resistance between the following locations and the copper grounding plate located at the base of the NHCSA north wall were measured. The resistance of the wire used was 258.10mΩ, and has been subtracted from the following results.
Measurements taken in NHCSA:
- Control panel below viewing window (base plate of box): 4.67mΩ
- Oil window frame (bare metal drain valve): 55.34mΩ
- Left manipulator (ground plate near e-stop button): 73.46mΩ
- Right manipulator (ground plate near e-stop button): 202.58mΩ
- Air and gas supply line mounting bracket: 40.68mΩ
- Diagnostic connector box: 12.15mΩ
- Steel conduit for 110V supply to hot cell interior: 4.81mΩ
Measurements taken inside NHC:
- Work table: 4.51mΩ
- Pre-filter bolted to partition wall: 4.84mΩ
- Table hatch lid: open load
- Left manipulator thru tube: 515.8mΩ
- Right manipulator thru tube: 342.0mΩ
- Left manipulator (slave boot plate bolt): 885.9mΩ
- Right manipulator (slave boot plate bolt): 1444.0mΩ
- Grounding strap for air/gas plate: 4.84mΩ
- Outside of SHV connector on diagnostic signal box: 4.56mΩ
- Exterior of 110V electrical conduit: 3.88mΩ
- Male Staubli connector for 1st gas line: 53.7mΩ
- Welded stud for window cover panel: 6.06mΩ
- Grounding strap for partition wall: 4.39mΩ
- Roof structure (measured inside un-painted bolt hole): ~0mΩ
- Stainless steel module flange: ~0mΩ
Dedicated grounding will be added in the near future for the oil window frame and the manipulator thru-tubes. Testing will then be repeated for those items.
Dec 18, 2018 update:
The oil window frame and both manipulators (where they bolt to the thru-tubes) were connected to the building ground using 1/2" flat bonding strap connected at the cold side of each piece of equipment, and running to the grounded copper sheet located in the NHC service area at floor level. The connection is made inside the electrical racks located directly west of the NHC operator area on the cold side. This work was done by Travis Cave in October 2018.
Mili-ohm testing for these items has not yet been repeated.
Jan 14, 2019 update:
Grounding was added from the metal plate near the e-stop button on the master arm of both manipulators. The same 1/2" flat bonding strap was used which was tied into other bonding strap which runns to the grounded copper sheet in the NHCSA.
Mili-ohm testing was repeated for the following items:
- Oil window frame (bare metal drain valve): 13.6mΩ
- Left manipulator (ground plate near e-stop button): 16.1mΩ
- Right manipulator (ground plate near e-stop button): 16.5mΩ
|
1781
|
Wednesday, September 12, 2018, 15:30 |
Isaac Earle | North Hot-Cell | Development | | | Installation of NHC operator-level lighting completed |
Installation of of operator-level lighting in the NHC was completed today according to drawing IRH1801. 2" x 2" Panduit was mounted to the wall on aluminum brackets to support the power cables. These lights can be replaced remotely by unplugging the power cords using the manipulators, lifting the cable out of the Panduit with a hooked pole tool through the manipulator slave end removal roof hatch, lifting the light fixture off the support bracket with the pole tool, then installing a new fixture in the opposite order. This RH procedure will be tested at a later date as part of NHC commissioning.
|
1780
|
Wednesday, September 12, 2018, 15:22 |
Isaac Earle | North Hot-Cell | Development | | | NHC air and gas supply lines - test and leak check |
Testing was completed today on the NHC air and gas supply lines. For each line a Staubli plug was installed on the fitting inside the hot cell, the line was charged with compressed air (50psi for gas lines #1, #2, and #3; 100psi for the air lines #4 and #5). All connections inside and outside the cell were checked for leaks using Snoop including connections for the solenoid valves. No leaks were found. Correct operation of the solenoids was confirmed as well as correct plumbing (no lines crossed). |
1779
|
Friday, September 07, 2018, 10:55 |
David Wang | ITE | Standard Operation | TM4 | UCx 24# | TM4 has been connected to ITE/ Checklist |
TM4 has been connected to ITE on Sep 04th. See attachment for checklist. |
Attachment 1: TM4_UCx_24#__connection_check_list.pdf
|
|
1778
|
Friday, September 07, 2018, 10:47 |
David Wang | ITE | Repair | TM4 | UCx24 | TM4 TP2 replacement |
TM4 TP2 could not be started after module was connected back to ITE on Sep 04th. It was replaced with a new pump on Sep 05th. The new pump works fine. |
1777
|
Thursday, September 06, 2018, 10:25 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#34, Ta#45,46,47, 50 | Spent Target Move |
Targets SiC#34 , Ta#45,46,47,50 have been moved from the spent target vault to the mini vault. |
1776
|
Tuesday, September 04, 2018, 09:57 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#24 | Module move |
TM#4 with UC#24 has been moved from the conditioning station to the east target station. |
1775
|
Tuesday, September 04, 2018, 08:18 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx 24# | Stppped TM4 and TCS vacuum and water system at TCS. |
I stopped TM4 and TCS vacuum system at TCS. TCS and TM4 is venting with argon now. |
1774
|
Thursday, August 30, 2018, 14:16 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#56, UC#24, and no target | Electrical Check |
Results of the electrical check with the spent Ta#56 attached, no target attached and the UC#24 attached. These test were performed on TM#4. |
Attachment 1: TM#4_Ta#56_Electrical_Check_Post_Beam_at_SHC.pdf
|
|
Attachment 2: TM#4_No_Target_Electrical_Check_Aug-29-2018.pdf
|
|
Attachment 3: TM#4_UC#24_Electrical_Check_SHC.pdf
|
|