Wednesday, October 14, 2014
The BIAS voltage was brought up between 1:30pm and 5pm. Sparks tripped the BIAS power supply at voltages between 20 - 24 kV. Multiple attempts were made. The current was about 50-60 uA.
Wednesday, October 15, 2014
Temperature in the cooling circuit is too hight to do a HV test. The cooling circuit was started, but shuts off after ~10 m
Thursday, October 16, 2014
David and I found that the fans on the cooling unit on the roof did not run and that the compressors get hot and likely trip on over temperature protection (hot to the touch). We found the manual in the control panel of the unit.
10am: HV to 20kV before a spark tripped the PS. Current at 40 uA - resistivity at 11.9 Mohm
5pm: HV to 20kV before fluctuations in current, then a spark tripped the PS. Current around 40 uA. Resistivity 12.6 Mohm
Friday, October 17, 2014
8am: Staging did not start over night. TS5 temp is 31 deg C, which would have tripped power supplies. Reset and enabled staging.
The system increased staging until all 3 compressors were running.
9am: Cooling supply temperature reached ~3 deg C. Disabled staging and switched off all pumps
2pm: Switched off water circulation for the weekend.
|
Friday, November 06, 2015, 14:35: Roughing
Turbos was started around 4pm. Later it was found that the manual valve for the two turbo pumps on the service cap was closed. The valve was open and pumping resumed. The roughing vacuum was high and increased into Saturday morning. The vacuum system was switched off on Saturday.
Purged MP1 using the purging function. Performance recovered. Started rouging.
Monday, November 09, 2015, 09:18: Started TP1S
Monday, November 09, 2015, 09:22: Started TP1 and TP2
Monday, November 09, 2015, 09:33: All 3 turbos at speed
Leak found on F/T for multipin connector
Tuesday, November 10, 2015, 09:53: stopped turbos |
Tuesday, November 10, 2015, 16:53: Roughing
Tuesday, November 10, 2015, 18:24: TP1S started
Tuesday, November 10, 2015, 18:30: TP1 and TP2 started
Tuesday, November 10, 2015, 18:41: All 3 turbos at speed.
Thursday, November 12, 2015, 08:30: Purged backing pump using purging function. Vacuum in backing line recovered to previous value.
Module connected for HV testing. No target heating possible. All F/Ts tied together to HV common. EZL connected.
Friday, November 13, 2015, 11:20: Started water package
Friday, November 13, 2015, 11:52: 1kV on BIAS and 1 kV on EL
Friday, November 13, 2015, 12:54: BIAS/EL 10 / 5 kV
Friday, November 13, 2015, 12:59: BIAS/EL 15 / 7.5 kV
Friday, November 13, 2015, 13:04: BIAS/EL 20 / 10 kV
Friday, November 13, 2015, 13:08 : BIAS/EL 22 / 11 kV. Some sparks.
Friday, November 13, 2015, 13:17: Sparking at 22.5 kV. Had to return to 20 kV to recover. Back at 22.5
Friday, November 13, 2015, 13:21 : BIAS/EL 24 / 12 kV.
Friday, November 13, 2015, 13:27: Heavy spakring around 24.5 kV. Had to return to 20 kV to recover.
Friday, November 13, 2015, 13:31: Attempted to increase voltage again. Sparking started around 23 kV. Had to lower to 20 kV.
Friday, November 13, 2015, 13:36: 9 sparks for the last 5 min.
Friday, November 13, 2015, 13:45: Spark rate reduced, but multiple sparks encountered again at 20.5 kV. Reduced back to 20 kV
Friday, November 13, 2015, 13:50: Increased sparking at 20 kV. Had to lower to 18 kV
Friday, November 13, 2015, 14:07: Back at 20 kV
Friday, November 13, 2015, 14:13: BIAS and EL off
Monday, November 16, 2015, 08:18: Fault on chiller. Reset chiller unit on the roof. |