  426   Monday, August 26, 2013, 18:22 Grant MinorSouth Hot-CellRepairTM3 TM3 Rev 3 - all connetions made except steerers, IMG, and entrance window

Today Chad finished making all connections to the new source tray, except for:

- steerers - broken wire, must be repaired at a later date

- IMG gauge - bracket required, old bracket thrown out with previous tray by accident, see ITA3301, must be installed at a later date

- entrance window - the window lines on module side were left blanked-off for leak checking, containment box must be removed in the next few days to complete steerer repairs so these lines were not connected to save work from having to be repeated

The containment box was replaced, and TM3 was moved to the CS for pump-down and leak checking (see other e-log).  David reported at 6:15 pm that the turbos were turned on at the CS and the vacuum looked normal (so far).

As stated above, Chad realized today that he had thrown out the old IMG gauge bracket with the previous source tray, and a new one must be manufactured.  The assembly is described by ITA3301.  Three components must be manufactured (ITA3302, ITA3303, and ITA2673).  A stock split-ring clamp for ITA2673 (MDC #716001) was graciously donated by Dimo Yosifov.  Grant Minor submitted a work order to the machine shop today for 2 each of ITA3302 and ITA3303.

Attachment 1: TM3_ST_install_before_move_to_CS_26Aug2013.JPG
TM3_ST_install_before_move_to_CS_26Aug2013.JPG
Attachment 2: TM3_ST_install_before_move_to_CS_26Aug2013-001.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-001.JPG
Attachment 3: TM3_ST_install_before_move_to_CS_26Aug2013-002.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-002.JPG
Attachment 4: TM3_ST_install_before_move_to_CS_26Aug2013-003.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-003.JPG
Attachment 5: TM3_ST_install_before_move_to_CS_26Aug2013-004.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-004.JPG
Attachment 6: TM3_ST_install_before_move_to_CS_26Aug2013-005.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-005.JPG
Attachment 7: TM3_ST_install_before_move_to_CS_26Aug2013-006.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-006.JPG
Attachment 8: TM3_ST_install_before_move_to_CS_26Aug2013-016.JPG
TM3_ST_install_before_move_to_CS_26Aug2013-016.JPG
  131   Thursday, June 21, 2012, 14:30 chad fisherSouth Hot-CellRepairTM3N/ATM3 Refurbishment Start

Started refurb of TM3.

Planned activities:

Inspection

Water line blank off

Started 1:00pm

  • Video inspection before containment box removed - noticed discoloration on top right (if looking from h/c window) 4" insulator
  • Containment box cover removed
  • Containment box removed

As I am much older, wiser and handsomer then last time I removed this style of box, I realised there was a better, safer procedure for the removal...I will be updating the doc. accordingly.

End 2:25 pm

 

  322   Wednesday, April 24, 2013, 14:09 chad fisherSouth Hot-CellRepairTM3 TM3 Refurbishment E.O.D.

Optics tray has been removed from module.

Waterblock jig installation has commenced. Of note, jig installation on TM3 has proven more dificult than the previous installation on TM2. Many of the waterblock assemblies are skewed (not perpendicular to plane that they should be...perpendicular to).

As I am away tomorrow, jig installation willl continue on Friday. With the source tray hopefully being removed on Monday.

  133   Monday, June 25, 2012, 07:53 chad fisherSouth Hot-CellRepairTM3N/ATM3 Refurb. Work

On Friday, June 22 the following work was carried out.

  • Further inspection of the source tray.
  • Testing of existing tray removal and installation tool...it works fine, there was just a specific method for proper coupling to the target module. There was no documentation for this tool, so it took a little bit of insight with the drawings and a little trial and error. A document should be written for this tool so its proper use is documented...I will do this.
  • Blank-offs installed on heat shield water lines.
  • New gaskets installed on window water lines.
  • Containment box re-installed.

Pictures can be found at: http://documents.triumf.ca/docushare/dsweb/View/Collection-8639


 

  299   Tuesday, April 16, 2013, 11:20 chad fisherSouth Hot-CellRepairTM3 TM3 Referb. start

Front containment box cover has been removed and heat shield circuit blank offs removed in preparation for installation of dummy target.

 image #1 - initail view after front panel removal.

image #2 - Heat shield circuit blank offs removed.

Ready for baseline electrical tests and 9 pin cinnector tests.

Attachment 1: IMG_3523.JPG
IMG_3523.JPG
Attachment 2: IMG_3524.JPG
IMG_3524.JPG
  1491   Wednesday, April 12, 2017, 12:51 David WangSouth Hot-CellRepairTM3 TM3 Ram readings @ SHC

 We have a ram installed on SHC pole which is 0.5 meter to  module shielding block surface. the readings we got today during TM3 move:
at containment box center (highest reading): 3.14 msv/hr.
at bottom  of shielding blocks: 960 usv/hr.
at 1/4  of  shielding blocks height from  bottom :700usv/hr.
at 1/2 of shielding blocks height from bottom: 340usv/hr.
at 3/4 of shielding blocks height from bottom:140u/sv/hr.
   The Ram is behind the pole and measured the surface which is 90 degree right side of that opened service tray side. 

  129   Wednesday, June 20, 2012, 11:39 Grant MinorSouth Hot-CellDevelopmentTM3N/ATM3 Planned Activites at South Hot Cell Jun 20 to 29 2012

(Copy of e-mail correspondence sent June 20th 2012)

After some discussions this morning I’ve decided on the following best path forward for TM3 at the Hot Cell leading up to the Canada Day long weekend.

 

General Goals:

-          Blank-off TM3 water line terminations (coil, heat shield, water-cooled window)

-          Test sliding tray removal tool to determine fit on TM3 chassis

 

We will skip the Conditioning Station leak tests and return TM3 directly to a silo for the following reasons:

-          We will have a visitor next week and this will impact Chad’s time available to do Hot Cell work

-          Helium pressure leak checks on the blanked-off circuits are only one small portion of a large set of diagnostic tests (leak, electrical, HV, etc.) that must ultimately be performed on TM3 to determine its fitness. This full set of tests must be carefully documented in a procedure and executed systematically when there is adequate time at the CS to do all of them, with results recorded.  There is currently not adequate time for this work between now and Canada Day.

-          If we were to detect a leak from one of these tests, it would not tell us anything about where the leak is in that given circuit (there are multiple possible points).  The service cap would have to be opened regardless, which we don’t have time for.

-          The aforementioned bullets above lead me to conclude that the extra work required for two module moves for one set of partial leak checks is not a value-added exercise: In other words, the module will have to go back to the CS, regardless of what we do over the next week for more tests.  The time savings of trying to squeeze it in next week are really negligible and it makes for a tight schedule for not much benefit.

 

Chad:  Please prepare a detailed work plan for your hot cell jobs including a list of the tools required and what leak checks you will do specifically after you have installed the blank-offs.  You may refer to existing procedures if you already have these written.  I would like to review this plan and I am expecting that an e-log will be filed daily and this work plan should be referred to as an attachment.

 

Proposed Schedule Jun 20 to 29

 

Wednesday Jun 20 (1 working day)

-          Setup for TM3 move from Silo to HC (Travis, David)

 

Thursday Jun 21 (1 working day)

-          TM3 moved from silo to HC (Travis, Don Dale, David)

 

Friday Jun 22 to Wednesday Jun 27 (4 working days)

-          Chad performs the following HC work on TM3:

·         Removes containment box

·         Installs water-line blank-offs

·         Checks Sliding Tray Removal Tool Fit

-          Vacuum leak checks of blanked-off lines at the HC (Chad, David, VG)

-          Chad buttons up TM3

-          In parallel - David performs block moves as required

 

Thursday Jun 28 (1 working day)

-          TM3 moved from HC to Silo (Travis, Don Dale, David)

 

Friday Jun 29 (1 working day)

-          Contingency

 

RH Group: Please move ahead with the work as outlined above.  Please comment if you have any concerns or proposed changes to this plan.  Thanks very much to all for your assistance,

 

Grant

 

-------------------------------------------------

Grant Minor, M.A.Sc., P.Eng.

TRIUMF Remote Handling Group Leader

Nuclear Engineer

4004 Wesbrook Mall, Vancouver

BC, Canada, V6T2A3

gminor@triumf.ca

(604) 222-7359

http://www.triumf.ca/profiles/4557

-------------------------------------------------

  2509   Wednesday, December 13, 2023, 11:42 Adam NewsomeSouth Hot-CellStandard OperationTM3 TM3 Move - TCS TO SHC

TM3 has been moved from the target conditioning station to the south hot cell.

  2507   Tuesday, November 28, 2023, 12:58 Adam NewsomeSouth Hot-CellStandard OperationTM3 TM3 Move - Silo to SHC

TM3 was moved from the Silo to South Hot Cell.

  2510   Friday, December 15, 2023, 11:07 Adam NewsomeConditioning StationStandard OperationTM3 TM3 Move - SHC to TCS

TM3 was moved from the SHC to the TCS (no target installed).

  2551   Friday, March 15, 2024, 10:04 Adam NewsomeSouth Hot-CellStandard OperationTM3 TM3 Move - SHC to NE Silo

TM3 was moved from SHC to NE silo. Cable tray was recently installed.

  1972   Thursday, August 29, 2019, 12:54 Adam NewsomeSouth Hot-CellStandard OperationTM3 TM3 Move

TM3 has been moved from the Middle-East silo to the South Hot Cell.

  1973   Tuesday, September 03, 2019, 10:48 Adam NewsomeSouth Hot-CellStandard OperationTM3 TM3 Move

TM3 has been moved from the South Hot-Cell to the Middle-East silo.

  2171   Monday, December 07, 2020, 12:20 Adam NewsomeConditioning StationDevelopmentTM3 TM3 Move

TM3 has been moved from the South Hot Cell to the Conditioning Station. No containment box.

  2172   Thursday, December 10, 2020, 15:07 Adam NewsomeSouth Hot-CellDevelopmentTM3 TM3 Move

TM3 was remotely moved from the conditioning station to the South Hot Cell. No containment box.

  2175   Monday, January 04, 2021, 12:13 Adam NewsomeConditioning StationDevelopmentTM3 TM3 Move

TM3 was remotely moved from the South Hot Cell to the conditioning station. No containment box.

  1514   Sunday, April 30, 2017, 20:57 Aurelia LaxdalSouth Hot-CellRepairTM3no targetTM3 May 1-15, 2017 Tentative Schedule at the SHC and TCS

Please see attachment for TM3 May 1-15, 2017 Tentative Schedule at the SHC and TCS.

Attachment 1: May_2107_TM3_Schedule_at_the_South_Hot_Cell_and_TCS.docx
  1494   Thursday, April 13, 2017, 10:32 chad fisherSouth Hot-CellRepairTM3 TM3 Lower Service Tray Video Inspection

A video inspection of the lower service tray was performed this morning. Camera was inserted upwards into the service tray/service chase from the containment box. One potential spark mark was identified as well as epoxy not flush with insulator. Fiberglass does not extend into service tray/chase much and does not look, from initial inspection that it will be too difficult to remove.

Video can be found in docushare Document-142295

  1508   Wednesday, April 26, 2017, 16:52 Aurelia LaxdalSouth Hot-CellRepairTM3 TM3 Lower Service Tray Video Inspection

chad fisher wrote:

A video inspection of the lower service tray was performed this morning. Camera was inserted upwards into the service tray/service chase from the containment box. One potential spark mark was identified as well as epoxy not flush with insulator. Fiberglass does not extend into service tray/chase much and does not look, from initial inspection that it will be too difficult to remove.

Video can be found in docushare Document-142295

 The attached picture is from the video: showing the fiber glass inside the Service Tray.

Attachment 1: FiberGlassInST.tiff
  1493   Wednesday, April 12, 2017, 16:39 Aurelia LaxdalSouth Hot-CellRepairTM3no targetTM3 Inspection at the South Hot Cell

Found spark signs on TM3's containment on the side of the water blocks. They may be OLD or/and NEW sparking signs, but this in not determined at this moment. Please see picture: first attachment. First and second attachment show the profiles of water block and HV lines.

Attachment 1: DSC_0886.JPG
DSC_0886.JPG
Attachment 2: DSC_0883.JPG
DSC_0883.JPG