348
|
Wednesday, May 15, 2013, 16:51 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No Source Tray | Repeat of HV Test | The HV test completed on Monday was
repeated today over a much longer time period.
By taking longer there was slightly less |
|
349
|
Wednesday, May 15, 2013, 17:32 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | | TM3 in place but not connected | To confirm that the sparking was
coming from the module rather than the conditioning
station TM3 was grounded and the conditioning |
|
350
|
Wednesday, May 15, 2013, 18:12 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No source tray | HV test repeat | After discussion with Friedhelm it
was decided to continue trying to condition
the module today before moving it tomorrow. |
|
352
|
Friday, May 17, 2013, 12:02 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | | module move | TM#3 with no target or source trays has
been moved from the conditioning station
to the NE silo. |
|
354
|
Tuesday, May 21, 2013, 11:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No Source Tray | May 16th Long HV conditioning | On May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more |
|
378
|
Thursday, June 13, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM3 | | Source Tray/Extraction Column Removal | TM3 Rev 2 source tray/extraction column
insertion into its storage was completed
yesterday and it was then removed from the |
|
380
|
Tuesday, June 18, 2013, 14:00 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up testing / water block connections | The testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven |
|
381
|
Wednesday, June 19, 2013, 08:15 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock up water block connections | All water block connections on the mock-up
have bben achieved. It is now ready for leak
checking. |
![20130619_080806[1].jpg 20130619_080806[1].jpg](attachment.png) |
383
|
Friday, June 21, 2013, 09:26 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up Leak Check Results | The Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight! |
|
391
|
Tuesday, July 02, 2013, 09:37 |
chad fisher | South Hot-Cell | Development | TM3 | | TM3 Rev.2 Source Tray Disposal | Tm3 Rev.2 source tary has been transfered
to the vault tunnel storage. |
|
395
|
Wednesday, July 03, 2013, 10:43 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
was moved from the north east silo to the
south hot cell the move went well. |
|
397
|
Friday, July 05, 2013, 09:22 |
chad fisher | South Hot-Cell | Repair | TM3 | | Service Tray Water Block Inspection | I have inspected the service tray water
block and suggest that they SHOULD be cleaned/polished
before we install the new source tray. |
|
398
|
Friday, July 05, 2013, 10:02 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No source tray | TM3 module move to TCS | TM3 has been moved from the south hot cell
to the conditioning station. David and I
completed the move. All went well. |
|
401
|
Wednesday, July 17, 2013, 08:29 |
David Wang | Conditioning Station | Development | TM3 | | TM3 leak check in CS without source tray. | Leak checked TM3 without source tray in
CS this morning. The CS and TM3 vacuum: IG1(top
of the TM3 service cap)4.9x E-7Torr, IG2(diagnostic |
|
402
|
Wednesday, July 17, 2013, 10:10 |
David Wang | Conditioning Station | Development | TM3 | | CS cooling and vacuum system have been turned off | CS water cooling and vacuum system have
been turned off at 10:00 AM this morning.The
TM3 will be disconnected and moved to silo |
|
403
|
Thursday, July 18, 2013, 10:08 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
has been moved from the conditioning station
to the north east silo, move went well. |
|
404
|
Monday, July 22, 2013, 15:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No Source Tray | HV testing update | I have fallen behind on the
HV testing that has been completed on TM3.
Data can be found on docushare in the TM3 |
|
418
|
Wednesday, August 14, 2013, 11:50 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | | module move | TM#3 and its new source tray have been
both moved into the south hot cell. |
|
420
|
Thursday, August 15, 2013, 09:32 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 source tray installation status |
The installation of the module
side water block jig has been successful.
During |
|
423
|
Wednesday, August 21, 2013, 20:36 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 module-side water block sealing surface inspection (post polishing) | The water block sealing surfaces on the
module-side of TM3 were polished this week
by Chad Fisher, using his air-ratchet controlled |
 |