891
|
Monday, April 20, 2015, 10:12 |
Anders Mjos | Conditioning Station | Standard Operation | TM1 | UC#12 | Conditioning UC#12 | Monday, April 20, 2015, 09:35: Started
cooling water circulation
HV cover did not fit due to interference |
|
|
894
|
Tuesday, April 21, 2015, 17:14 |
Isaac Earle | South Hot-Cell | Standard Operation | TM1 | UC#12 | UC#12 Installed in TM1 | On Friday April 17th, UC#12 target was
installed in TM1. One of the copper
water lines was bent slightly as the target |
 |
|
904
|
Tuesday, April 28, 2015, 11:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module move | TM#1 with UC#12 has been moved from the
conditioning station to the west target station. |
|
|
969
|
Tuesday, June 30, 2015, 11:27 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module moved | TM#1 with UC#12 has been moved from the
west station to the south hot cell. |
|
|
975
|
Thursday, July 02, 2015, 11:51 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#12 | Spent target moved | UC#12 has been moved from the south hot
cell and placed into storage. It is in pail
#125 and in spot 1C of the vault it had a |
|
|
794
|
Wednesday, November 19, 2014, 09:18 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#11 | Electrical check | TM#4 with UC#11 electrical check done.
See attached PDF for the results. |
|
|
796
|
Thursday, November 20, 2014, 11:49 |
Travis Cave | ITE | Standard Operation | TM4 | UC#11 | module move | TM#4 with UCx#11has been moved from the
conditioning station to the east target station. |
|
|
862
|
Monday, March 16, 2015, 09:41 |
Travis Cave | ITE | Standard Operation | TM4 | UC#11 | Module move | TM#4 with UC#11 moved from the east target
station to the south hot cell. |
|
|
864
|
Tuesday, March 17, 2015, 10:33 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#11 | Spent Target Move | The spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details. |
|
|
753
|
Tuesday, September 23, 2014, 13:31 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10, Ta#44 | Electrical check | Electrical checks of TM#4 with UC#10 post
beam and Ta#44 before beam see attached PDF
for details. |
 |
|
729
|
Monday, August 11, 2014, 10:34 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#10 | module move | TM#4 with UC#10 has been moved from the
conditioning station to the east target station. |
|
|
730
|
Monday, August 11, 2014, 10:38 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10 | Electrical check | Electrical check of TM#4 with UC#10 from
thursday. |
|
|
750
|
Tuesday, September 23, 2014, 10:50 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10 | module move | TM#4 with UC#10 has been moved from the
east target station to the south hot cell. |
|
|
757
|
Friday, September 26, 2014, 10:56 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#10 | Spent target move | UC#10 has been moved from the south hot
cell to the spent target vault. It was placed
in Pail #119 and in slot 8B. For further |
|
|
2009
|
Tuesday, October 22, 2019, 11:19 |
Adam Newsome | South Hot-Cell | Standard Operation | TM4 | UC# 28 | TM4 Move | TM4 with UC# 28 target has been moved from
ITW to the South Hot Cell. Shield plug installed
in ITW. |
|
|
154
|
Tuesday, July 31, 2012, 12:50 |
David Wang | South Hot-Cell | Standard Operation | TM1 | UC x | TM1 heat shield circuit leak check with UC x target | Chad and i did a leak check on TM1heat
shield with UCx target on.The circuit are
pumped down to the bottom leak rate |
|
|
2724
|
Thursday, November 28, 2024, 16:13 |
Aaron Tam | South Hot-Cell | Standard Operation | | TiC#9 Parasitics | TiC#9 Parasitics Leak Check and removal from hotcell | November 27th, 2024 - Aaron Tam with
Farran & David
Parasitic Assembly Leak Check (Aaron, |
    |
|
2677
|
Tuesday, September 10, 2024, 12:41 |
Frank Song | South Hot-Cell | Standard Operation | TM4 | TiC#9 | electrical check/leak check | TM4 with new target TiC#9 Surface
installed in SHC was leak/electric checked
before moving to TCS. See attached pic pls. |
|
|
2684
|
Tuesday, September 17, 2024, 13:42 |
Frank Song | ITW | Standard Operation | TM4 | TiC#9 | Module Connection | TM4 with target TiC#9 is connected
in ITW. See attachment. |
|
|
2710
|
Tuesday, November 05, 2024, 09:49 |
Frank Song | ITW | Standard Operation | TM4 | TiC#9 | module disconnection | TM4 with spent target TiC#9 was disconnected
in 29-10-2024 and it is being moved from
ITW to SHC. |
|