2198
|
Thursday, March 11, 2021, 11:42 |
Frank Song | ITE | Maintenance | | | ITE water flow wheels and coils replacement. |
ITE water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump, dump plug, 2A window, and tank return circuits are replaced with new parts. |
|
2197
|
Friday, March 05, 2021, 09:12 |
Matthew Gareau | North Hot-Cell | Development | TM3 | | Containment box door removal and swivel arm test |
First thing I entered into the NHC to install to the target kart mounting clip, and remove excess tools and materials from the hotcell
After the TM3 without a target was lowered into the NHC.
Once inside, with the use of the manipulators, I was able to remove the containment box door, place it on the swivel arm, move the arm out of the way, after the door was return to the containment box and reattached.
|
|
2196
|
Thursday, March 04, 2021, 16:30 |
Isaac Earle | North Hot-Cell | Development | | | NHC gas delivery lines leak checked |
The North Hot Cell gas delivery lines (labeled 1, 2, and 3 on the hot and cold side panels) were leak checked today. 5psi helium gas was applied to each line in turn with the appropriate solenoid valve opened and a Staubli connector with plastic tubing and the leak check wand attached to the matching connector inside the cell. The end of the wand was sealed using tape. The Agilent G8601 leak detector was used on "sniffing" mode to check for escape of helium gas from all joints and connectors. With the sniffing line attached the leak detector test port pressure was 3.9E-1 Torr and the baseline leak rate was 1.7E-6 Torr*L/s. There was no response while testing all of the three lines. For all three there was a leak detector response after disconnecting the Staubli fitting, which confirmed that the lines were properly charged with helium. |
|
2195
|
Thursday, March 04, 2021, 13:54 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TM3 has been moved to NHC from silo |
TM3 has been moved from silo to NHC. The move is successful. NHC ram stand and NHC protection railings are checked and installed. Everything works fine.
2021-03-05. TM3 has been moved from NHC to silo. The move is successful. |
|
2194
|
Thursday, March 04, 2021, 11:20 |
David Wang | ITW | Maintenance | | | ITW water flow wheels and coils replacement. |
ITW water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump,dump plug, 2A window, and tank return circuits are replaced with new parts. |
|
2193
|
Tuesday, March 02, 2021, 08:12 |
David Wang | Conditioning Station | Standard Operation | | | TCS leak check. |
TCS leak check: TCS IG1S1.6 XE- 6 torr. LD 0.0XE-9atm.cc/sec.We used a long pole to spray helium to TCS vacuum seals on diagnostic box and vessel body. Lots helium have been sprayed around the check area. no leak has been found. |
|
2192
|
Thursday, February 25, 2021, 10:09 |
Frank Song | ITE | Repair | | | Disconnect Entrance Module in ITE |
David and I disconnected entrance module in ITE by following the procedure # 190510. And, the yoke was installed and left on for remote handling later. |
|
2191
|
Tuesday, February 23, 2021, 09:00 |
David Wang | Assembly/Bench Test | Maintenance | | | target staion vacuum pumps inspection. |
Edi and I inspected roughing pump ITM MP1, primary backup pump ITHMP1, and secondary backup pump ITHMP2. We checked oil level and color on all pumps. Refilled lubricant to ITMMP1. ITHMP1 and MP2 oil level is fine. ITH MP1 oil color is darker than MP2. But, both them are ok still. Shielding block has been restored after the job. |
|
2190
|
Thursday, February 18, 2021, 12:59 |
David Wang | Assembly/Bench Test | Maintenance | | | TM3 source tray and old resin can storage in lower cyclotron basement |
TM3 old source tray, old target hall high active water resin tank, and old 2A window RH clamp are transferred from TH to cyclotron lower vault basement 10 and 10A location for storage. They are placed beside and in front of old TM1 and TM2 source tray boxes which stored there in 2018. |
|
2189
|
Thursday, February 18, 2021, 12:33 |
David Wang | ITE | Repair | | | ITE:TP1S |
ITE TP1S new pump is installed today. Reset pump life time on controller to 0 hr. |
|
2188
|
Tuesday, February 16, 2021, 14:00 |
Adam Newsome | Crane | Development | | | Crane pendant upgrade |
The crane pendant for the main hoist was upgraded to a FLEX EX2 style pendant by Canco Cranes. The installation work was performed by Matt at Canco, supervised by Tom Kauss, David Wang, and Adam Newsome. Installation work was performed in two phases since the initial installation did not provide adequate range and an antenna issue needed to be resolved (I2021-01-14-1, and I2021-02-16-1).
Items installed include:
- New pendant
- New antennae
- New receiver box, mounted on main crane control panel in the crane control room
The old receiver control box will be kept for some time in case there is a need to revert to the previous system for some reason.
The new system was tested by David Wang - including using the pendant at the far end of the target hall where range was previously an issue. Everything is reported to be in working condition. Remote mode is functioning as expected.
|
Attachment 1: PXL_20210216_183711834.jpg
|
|
|
2187
|
Friday, February 12, 2021, 07:07 |
David Wang | ITE | Maintenance | | | ITW and ITE clean up. |
Vacuum cleaned ITW and ITE station. |
|
2186
|
Wednesday, February 10, 2021, 13:30 |
David Wang | Safe Module Parking | Standard Operation | | | TM2 and TM4 electrical check without targets. |
TM2 at SMP under vacuum. TM4 at silo. Frank and I did the tests. Everything is fine on TM4 check. On TM2, all mega test at 500V are around 200K ohms which is so abnormal. We will move TM2 to TCS and start investigation there. |
Attachment 1: TM2_and_TM4_electrical_check_without_target.pdf
|
|
|
2185
|
Wednesday, February 10, 2021, 11:34 |
David Wang | Assembly/Bench Test | Standard Operation | | | Old resin can and 2A window RH clamp field measurement at silo. |
Old resin can: 0.5 meter 360 degree rotation above silo area, 350u sv/hr. On contact 3.0 to 3.5 msv/hr. It was replaced during 2017 winter shut down, and stored in silo since then.
2a window RH clamp: 0.5 meter, 160 usv/hr. On contact, hottest spot 3.5msv/hr, general,1.8 msv/hr.
Both of them were raise out of storage silo with TH crane. Pole monitor was used for field check. |
|
2184
|
Wednesday, February 03, 2021, 09:14 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 from TCS to SW silo. |
TM4 is moved from TCS to SW silo. The moving is smooth.
|
|
2183
|
Wednesday, January 27, 2021, 14:30 |
David Wang | Cooling | Development | | | High active water system purging |
High active water are purged to holding tank at B2 level. There should be around 48 gallons are purged out of system. No purging on dump circuits on both ITW/ ITE. |
|
2182
|
Monday, January 25, 2021, 12:33 |
David Wang | ITW | Standard Operation | | | ITW bias HV test |
Ramp up ITW bias to 57KV. no spark. 200uA leaking current at 57KV. The test is done without target module in station. ITW water circuits are looped in pit. EE , EL are switched off during the test. |
|
2181
|
Monday, January 25, 2021, 10:57 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 steers short investigation. |
Cables were disconnected for steers in containment box. The Megga measurement (500V) result from the top of the module:
Left to right: OL, left to top OL, left to bottom OL, right to top OL, right to bottom OL, Top to bottom OL. And all of them to ground are OL. No short on cables from module top to steers itself. The short should be inside the steers. It will be confirmed with directly test on steers. |
|
2180
|
Friday, January 22, 2021, 12:34 |
David Wang | ITE | Standard Operation | | | ITE HV test. |
ITE annual HV test is done. No module in station. The bias power supply has been ramped up to 49KV on control page. We still have voltage limit issue on this PS at 48KV so it only can go to 47.7 KV on PS panel. No major spark during test.. The test result is same as last year test which was did in March 2020. |
|
2179
|
Tuesday, January 19, 2021, 11:32 |
Travis Cave | Safe Module Parking | Standard Operation | TM2 | Nb#9 | Module move |
TM#2 with Nb#9 was moved from ITW to SHC and then with no target it was moved from the SHC to the SMP. |