  1605   Monday, August 28, 2017, 14:40 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Electrical CheckThe results of the electrical check of
TM#4 with UC#21 attached.
 TM4_UC21_elecchk_SHC.PDF 
  1610   Tuesday, September 05, 2017, 10:25 Travis CaveITEStandard OperationTM4UC#21Module move TM#4 with UC#21 has been moved from
the conditioning station to the east target
station.
  
  1643   Tuesday, October 17, 2017, 10:56 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Module move TM#4 with UC#21 has been moved from
the east target station to the south hot
cell.
  
  1650   Monday, October 23, 2017, 13:38 Travis CaveSpent Target VaultStandard Operation UC#21Spent Target moveThe spent UC#21 has been moved from the
south hot cell to the spent target vault.
See attached for details
 Vault_Storage_October_23_2017.pdf 
  1536   Tuesday, May 16, 2017, 13:23 chad fisherSouth Hot-CellStandard OperationTM4UC#20UC#20 InstalledUCx#19 has been removed from TM4 and UCx#20
installed.
UCx#19 still had water in it at pressure
  
  1537   Tuesday, May 16, 2017, 14:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Electrical CheckTM#4 with UC#20 has had the electrical
check done on it  at the south hot cell,
see attached for details
 TM4_UC20_Elec_chk_SHC.PDF 
  1538   Tuesday, May 16, 2017, 14:19 Travis CaveConditioning StationStandard OperationTM4UC#20module movedTM#4 with UC#20 has been moved from the
south hot cell to the conditioning station.
  
  1543   Thursday, May 18, 2017, 11:36 Travis CaveConditioning StationStandard OperationTM4UC#20Electrical CheckElectrical check of TM#4 with UC#20 at
the conditioning station under vacuum. See
attached for details.
 TM4_UC20_Elec_chk_CS_vac.PDF 
  1546   Tuesday, May 23, 2017, 10:41 Travis CaveITEStandard OperationTM4UC#20Module move TM#4 with UC#20 has been moved from
the conditioning station to the east target
station.
  
  1565   Monday, June 26, 2017, 11:42 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Module move TM#4 with UC#20 has been moved from
the east target station to the south hot
cell. Also the shield plug was remotely installed
  
  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)The target was inspected by Chad and Anders.
Photos are available on DocuShare.
It was noticed that the target tube heater
  
  1575   Thursday, June 29, 2017, 14:42 Travis CaveSpent Target VaultStandard Operation UC#20Spent Target Move The spent UC#20 has been moved from
the south hot cell to the spent target vault.
It was placed in pail #150 and spot 1B in
 Vault_Storage_June_29_2017.pdf 
  1468   Tuesday, March 28, 2017, 10:30 Travis CaveSouth Hot-CellStandard OperationTM4UC#19Electrical CheckElectrical check done on TM#4 with UC#19.
See attached PDF for results.
 TM4__UC19_SHC.PDF 
  1470   Wednesday, March 29, 2017, 11:42 Anders MjosConditioning StationStandard OperationTM4UC#19Conditioning UC#19 Wednesday, March 29, 2017, 11:37:
RGA on
Wednesday, March 29, 2017, 13:51:
 UC#19.docxTCS-2017-03-29_UC#19.rgaTCS-2017-03-30_UC#19.rgaTCS-2017-04-03_UC#19.rga 
  1473   Tuesday, April 04, 2017, 09:29 Travis CaveITEStandard OperationTM4UC#19module movedTM#4 with UC#19 has been moved from the
conditioning station to the east target station.
  
  1535   Tuesday, May 16, 2017, 10:28 Travis CaveSouth Hot-CellStandard OperationTM4UC#19module movedTM#4 with UC#19 has been moved from ITE
to the south hot cell.
  
  1542   Thursday, May 18, 2017, 10:41 Travis CaveSpent Target VaultStandard Operation UC#19Spent Target moveThe spent UC#19 target has been moved from
the south hot cell into the spent target
storage. It was placed in pail #145 and put
 Vault_Storage_May_18_2017.pdf 
  1401   Wednesday, November 23, 2016, 14:21 Travis CaveConditioning StationStandard OperationTM2UC#18module movedTM#2 with UC#18 has been moved from the
south hot cell to the conditioning station.
  
  1402   Wednesday, November 23, 2016, 14:25 Travis CaveSouth Hot-CellStandard OperationTM2UC#18Electrical CheckResults of TM#2 with UC#18 electrical at
the south hot cell. See attached PDF for
details.
 TM2_elechk_UC18_SHC.PDF 
  1405   Thursday, November 24, 2016, 09:33 Anders MjosConditioning StationStandard OperationTM2UC#18Conditioning UC#18Thursday, November 24, 2016, 09:33: Water
package on
Thursday, November 24, 2016, 09:43:
  