  1791   Monday, September 24, 2018, 14:50 Travis CaveSpent Target VaultStandard Operation UC#23Spent Target Move

 The spent UC#23 target has been moved from the south hot cell to the spent target storage. It was placed in pail #170 and place in spot #4B in the vault.

  2029   Thursday, November 14, 2019, 13:52 Travis CaveSpent Target VaultStandard Operation UC#22,23,24Targets repackaged

 The targets UC#22,23,24 have been repackaged into the newer stronger pails, and have been placed back in the mini vault with new numbers. See attached PDF for details.

  1730   Thursday, June 07, 2018, 11:33 Travis CaveSouth Hot-CellStandard OperationTM4UC#22Electrical Check

 The results of TM#4 with UC#22 electrical check. See attached PDF.

  1731   Thursday, June 07, 2018, 11:37 Travis CaveITEStandard OperationTM4UC#22Module move

 TM#4 ,with UC#22, was moved from the south hot cell to the east target station. Upon lowering the module down it made contact with the IMC, At that point the module was removed and placed back in the south hot cell. The IMC was inspected and problem corrected and the module was moved back to the east target station without a problem.

  1732   Friday, June 08, 2018, 10:22 Anders MjosITEStandard OperationTM4UC#22Module move

Travis Cave wrote:

 TM#4 ,with UC#22, was moved from the south hot cell to the east target station. Upon lowering the module down it made contact with the IMC, At that point the module was removed and placed back in the south hot cell. The IMC was inspected and problem corrected and the module was moved back to the east target station without a problem.

 The IMC (ITA0160) appears to have a dent in it from the contact with the Target Module. The pressure on the IMC was found to be about negative ~3 mmHg and was increased to ~20 mmHg to attempt to retract the IMC further away from the TM. This pressure is similar to the pressure used at the Conditioning Station. The bellows appears not to be symmetrically compressed. It should be inspected again and pressure checked and monitored for upcoming module moves.

  1737   Thursday, June 14, 2018, 11:37 David WangITEStandard OperationTM4UC#22TM4 UC 22# checklist.

See attachments

  1753   Monday, July 16, 2018, 17:41 Anders MjosITEStandard OperationTM4UC#22Target module disconnected

The water and electrical connections were disconnected today as protons remained off after power interruption during the weekend. Vacuum is still connected and operating.

 The vacuum system are disconnected 2018-07-17.  See attachment .

  1760   Tuesday, July 31, 2018, 11:16 Travis CaveSpent Target VaultStandard Operation UC#22Spent Target Move

 Yesterday the spent UC#22 target was moved from the south hot cell to the spent target vault. It was placed in pail #167 and placed in spot 4A see attached PDF for details.

  1604   Monday, August 28, 2017, 14:34 Travis CaveConditioning StationStandard OperationTM4UC#21Module move

 TM#4 with UC#21 has been moved from the south hot cell to the conditioning station.

  1605   Monday, August 28, 2017, 14:40 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Electrical Check

The results of the electrical check of TM#4 with UC#21 attached.

  1610   Tuesday, September 05, 2017, 10:25 Travis CaveITEStandard OperationTM4UC#21Module move

 TM#4 with UC#21 has been moved from the conditioning station to the east target station.

  1643   Tuesday, October 17, 2017, 10:56 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Module move

 TM#4 with UC#21 has been moved from the east target station to the south hot cell.

  1650   Monday, October 23, 2017, 13:38 Travis CaveSpent Target VaultStandard Operation UC#21Spent Target move

The spent UC#21 has been moved from the south hot cell to the spent target vault. See attached for details

  1536   Tuesday, May 16, 2017, 13:23 chad fisherSouth Hot-CellStandard OperationTM4UC#20UC#20 Installed

UCx#19 has been removed from TM4 and UCx#20 installed.

UCx#19 still had water in it at pressure and sprayed when the VCR was undone. It was quickly re-tightened but not before significant water pooled beside the main Mykroy standoff and table. Contacted Anders would suggested to soak it up with some wipes and continue, which I did.

New target fasteners including high current. High current fasteners torqued to 130 in lbs.

  1537   Tuesday, May 16, 2017, 14:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Electrical Check

TM#4 with UC#20 has had the electrical check done on it  at the south hot cell, see attached for details

  1538   Tuesday, May 16, 2017, 14:19 Travis CaveConditioning StationStandard OperationTM4UC#20module moved

TM#4 with UC#20 has been moved from the south hot cell to the conditioning station.

  1543   Thursday, May 18, 2017, 11:36 Travis CaveConditioning StationStandard OperationTM4UC#20Electrical Check

Electrical check of TM#4 with UC#20 at the conditioning station under vacuum. See attached for details.

  1546   Tuesday, May 23, 2017, 10:41 Travis CaveITEStandard OperationTM4UC#20Module move

 TM#4 with UC#20 has been moved from the conditioning station to the east target station.

  1565   Monday, June 26, 2017, 11:42 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Module move

 TM#4 with UC#20 has been moved from the east target station to the south hot cell. Also the shield plug was remotely installed as well after David set it up.

  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)

The target was inspected by Chad and Anders. Photos are available on DocuShare. It was noticed that the target tube heater terminals had lifted up from the insulator on the target assembly as seen in this Photo. This has later been detemined to be from the assembly, where additional clearance was required and achieved by installing washers.