1822
|
Thursday, November 22, 2018, 08:52 |
Anders Mjos | ITE | Standard Operation | TM4 | Ta#57 | Closed ITE dump water |
Paddle wheel signal was tripping proton beam in ITW. Valved off ITE dump to divert flow to ITW. Field around valve was about 600 uSv/h |
1827
|
Tuesday, November 27, 2018, 11:05 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#57 | Module move |
TM#4 with Ta#57 has been moved from the east target station to the south hot cell. |
1828
|
Tuesday, November 27, 2018, 13:31 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#57 | Ta#57 removal |
Ta#57 has been removed from TM4. |
1830
|
Wednesday, November 28, 2018, 07:04 |
David Wang | ITE | Development | TM4 | LpTa 56 | New high current flexible cables inspection after LpTa#56 beam run. |
Inspected new high current flexible cables during TM4 disconnection. The new cables and adapters work fine. |
1831
|
Wednesday, November 28, 2018, 11:31 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#57 and UC#26 | Electrical Check |
Electrical check of TM#4 with the old Ta#57, no target and with new IG-LIS UC#26 target. See attached PDF for details. |
1832
|
Wednesday, November 28, 2018, 13:38 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#26 | Module move |
TM#4 with UC#26 has been moved from the south hot cell to the conditioning station. |
1833
|
Thursday, November 29, 2018, 06:38 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Leak check TM4 UCx 26 at SHC. |
Chad and I did a leak check on TM4 HS line with UCx 26# installed . Base LR 0.0X E-9 atm.cc/sec. Base pressure 0.0XE-4 torr. No response on leak detector during leak check. |
1835
|
Tuesday, December 04, 2018, 10:26 |
Travis Cave | ITE | Standard Operation | TM4 | UC#26 | Module move |
TM#4 with UC#26 has been moved from the conditioning station to the east target station. |
1836
|
Tuesday, December 04, 2018, 12:36 |
David Wang | ITE | Standard Operation | TM4 | UCx 26. | TM4 has been connected in ITE/ Checklist. |
TM4 has been connected in ITE. See attachment for connection checklist |
1840
|
Tuesday, December 11, 2018, 14:35 |
Anders Mjos | ITE | Standard Operation | TM4 | UC#26 | Block move |
Blocks were moved from ITW to ITE by Frank and David. ITE water flow to dump was re-opened (ITW remains open). A dose badge was installed in the operation storage area. Dose rates were measured to ~10 mSv/h at 1pm. Beam went off approximately 8:30am (with a short period of 2uA ending at 11am). |
1868
|
Friday, February 15, 2019, 12:05 |
David Wang | ITE | Maintenance | TM4 | | ITE annual vacuum leak check. |
Helium pressure test on all water lines: 70psi , 3 minutes. HS has a quick response to 9Xe-9atm.cc/sec for 20 seconds. No response on other lines. All water lines are good. Air to vacuum leack check on ITE and TM4: TM4 IG1 / Steers side panel has a low E-6 atm.cc/sec leak. The o-ring need to be changed when TM4 is located at TCS. All other air to vacuum seals are good on both primary and secondary vacuum vessel. |
1869
|
Friday, February 15, 2019, 12:09 |
David Wang | ITE | Maintenance | TM4 | | ITE water system maintenance. |
The ITE water system maintenance job is done. Changed all paddle wheels and coils on ITE flow sensors. All using water poly-tubes in ITE are replaced . Started high active water pump, and checked ITE water signals. They are good. No leak has been found on replaced tubes and related fittings. |
1911
|
Tuesday, April 30, 2019, 08:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#26 | Module move |
TM#4 with UC#26 has been moved from ITE to the south hot cell. |
1912
|
Tuesday, April 30, 2019, 11:19 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#26 | Electrical Check |
Electrical check of TM#4 with UC#26 post beam at the south hot cell. See attached. |
1913
|
Wednesday, May 01, 2019, 07:49 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UC#26 | UC#26 removal |
UC#26 has been removed from TM4. |
1914
|
Wednesday, May 01, 2019, 09:34 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Module move |
TM#4 has now been moved to the south west silo. |
1915
|
Wednesday, May 01, 2019, 10:45 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Electrical Check |
Electrical check of the TM#4 with no target attached at the south hot cell before being moved to the south west silo. |
1927
|
Wednesday, May 22, 2019, 11:50 |
David Wang | ITE | Standard Operation | TM4 | | TM2 has been connected in ITE. |
TM2 has been connected in ITE. high active water system and vacuum pumps are started. The pumping down on TM2 and ITE is good so far.
See attachment for connection checklist. |
1931
|
Friday, May 24, 2019, 09:11 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Module move |
TM#4 has been moved from the south west silo to the south hot cell. |
1933
|
Thursday, June 06, 2019, 10:01 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target, no source Tray | Electrical Check |
Results from the electrical check of TM#4 at the south hot cell with no source tray. R&U are shorted and when meggered A&P have a value of 193k ohms. See attached for details. |