  RH-ISAC, Page 17 of 138  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1258   Tuesday, June 07, 2016, 18:17 David WangConditioning StationStandard OperationTM4UC#16TM4 and TCS turbo pumps are started.TM4 and TCS vacuum system are connected.
  Turbo pumps are started.  Everything
is fine so far.
  
  1259   Wednesday, June 08, 2016, 08:25 Anders MjosConditioning StationStandard OperationTM4UC#16Conditioning UC#16 Wednesday, June 08, 2016, 08:15:
RGA on

Thursday, June 09, 2016,
 UC#16.docxTCS-2016-06-08_UC#16.rga 
  1260   Thursday, June 09, 2016, 08:37 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 helium pressure test at TCSI did a helium pressure test on TM4 at
TCS with UCX16 target installed on the module.
No leak has been found on all using water
 TM4_withUCx16_helium_pressure_test_at_TCS.pdf 
  1261   Thursday, June 09, 2016, 09:44 David WangConditioning StationStandard OperationTM4UC#16TM4 has been connected at TCSIt is ready for HV conditioning/ heating.    
  1263   Tuesday, June 14, 2016, 08:04 David WangConditioning StationStandard OperationTM4UC#16TM4 has been disconnected at TCSThe TM4 and TCS are vented with argon.    
  1264   Tuesday, June 14, 2016, 10:51 Travis CaveITEStandard OperationTM4UC#16module movedTM#4 with UC#16 has been moved from the
conditioning station to the east target station.
  
  1265   Tuesday, June 14, 2016, 11:20 David WangITEStandard OperationTM4 TM4 has been connected in ITETM4 and ITE are under roughing now.   
  1295   Tuesday, August 02, 2016, 11:02 Travis CaveITEStandard OperationTM4UC#16module movedTM#4 with UC#16 has been moved from the
east station to the south hot cell. The shield
plug was also install remotely once it was
  
  1296   Tuesday, August 02, 2016, 13:32 chad fisherSouth Hot-CellStandard OperationTM4UC#16UC#16 Removed #17 installedUCx#16 has been removed from TM$ and UCx#17
installed, high current conductors toqued
to 130 in lbs.
  
  1297   Tuesday, August 02, 2016, 14:52 Travis CaveSouth Hot-CellStandard OperationTM4UC#17module movedTM#4 with UC#17 is now in the conditioning
station.
  
  1298   Tuesday, August 02, 2016, 15:22 David WangConditioning StationStandard OperationTM4UC#17TM4 with new target has been connected at TCSIt is being pumped now at TCS.   
  1299   Wednesday, August 03, 2016, 08:08 Anders MjosConditioning StationStandard OperationTM4UC#17Conditioning UC#17Wednesday, August 03, 2016, 08:08: RGA
on
Wednesday, August 03, 2016, 11:25:
 UC#17.docxTCS-2016-08-03_UC#17.rgaTCS-2016-08-08_UC#17.rga 
  1301   Wednesday, August 03, 2016, 09:45 David WangConditioning StationStandard OperationTM4UC#17Helium pressure test on TM4 HS line at TCS Helium pressure test on TM4 HS line at
TCS  is done.Leak detector 0.0X E-9atm.cc/sec. 
5minutes, 70psi helium.   
  
  1302   Wednesday, August 03, 2016, 09:49 David WangConditioning StationStandard OperationTM4 TM4 is ready for conditioing at TCS.I started TCS water system and installed
HV cover onto TM4.  The TM4 containment
box is supplied with water also. TM4 is ready
  
  1304   Wednesday, August 03, 2016, 10:02 Travis CaveSouth Hot-CellStandard OperationTM4UC#17Electrical CheckThe result of yesterdays electrical check
on TM#4 with UC#17.
 TM4_elechk_UC17_SHC.PDF 
  1309   Tuesday, August 09, 2016, 07:15 David WangConditioning StationStandard OperationTM4UCx17TM4 has been disconnected at TCSI stopped TCS water pumps this morning
. The argon venting for TCS is in processing.
  
  1310   Tuesday, August 09, 2016, 10:05 Travis CaveITEStandard OperationTM4UC#17module movedTM#4 with UC#17 is now in the east target
station.
  
  1313   Wednesday, August 10, 2016, 11:30 David WangITEStandard OperationTM4UC#17TM4 has been connected at ITEDan and I connected TM4 in ITE yesterday.
It is pumping down at ITE now. Everything
is fine so far.
  
  1319   Monday, August 15, 2016, 10:08 David WangITEStandard OperationTM4UC#175 Shielding blocks have been transferred from ITW to ITE.Dan and I transferred 5 shielding blocks
from ITW to ITE. The ITE is configured to
take proton beam.
  
  1320   Monday, August 15, 2016, 10:15 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Weekly update target hall schedule. Everything
on schedule are finished  on time.  
See attachment.  
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 