  18   Wednesday, August 03, 2011, 11:24 Travis CaveITWStandard OperationTM1Ta#37Module move

TM#1 with Ta#37 has been moved from the conditioning station to the the west target station, move went well.

  27   Wednesday, September 14, 2011, 10:32 Travis CaveSpent Target VaultStandard Operation Ta#37Spent target move

Ta#37 has been moved from the south hot cell into the storage vault. The target is in pail #89 and in spot 6A in the vault. It was 840uSv/hr upon removal from the south hot cell. There are 7 free spots left in the vault.

  28   Wednesday, September 28, 2011, 09:07 Travis CaveITEStandard OperationTM4Ta#36Move of TM#4 from East target station to south hot cell.

Move of TM#4 with Ta#36 from East target station to south hot cell, move went well.

  30   Wednesday, September 28, 2011, 11:59 Travis CaveSouth Hot-CellStandard OperationTM4no targetTM#4 moved from South Hot Cell to to North East Silo.

TM#4 moved from South Hot Cell to to North East Silo, move went well.

  31   Thursday, September 29, 2011, 11:11 Travis CaveSpent Target VaultStandard Operation Ta#36Spent target move

The spent Ta#36 has been moved to the storage vault. It was placed in pail #90, and placed into slot 3B, it was 111mSv/hr upon removal from the south hot cell. There are 6 free slots left in the storage vault.

  32   Monday, October 03, 2011, 11:00 Travis CaveITWStandard OperationTM1UCx#2Move from west station to south hot cell

TM#1 with UCx#2 has been moved from the west station to the south hot cell. Move went well.

  34   Monday, October 03, 2011, 14:52 Travis CaveSouth Hot-CellStandard OperationTM1TaC#1Electrical check

TM#1 with TaC#1 installed passed the electrical test. With a value of 882MOhms that was meggered from the heat shield to the chassis, all other measurements are within spec.

  35   Tuesday, October 04, 2011, 14:13 Travis CaveITWStandard OperationTM1TaC#1Move ot TM#1

Move of TM#1 with the TaC#1 target has been moved from the south hot cell to the west target station.

  36   Wednesday, October 05, 2011, 09:41 Travis CaveSpent Target VaultStandard Operation UCx#2Spent target move

The spent UCx #2 target has been moved into storage. It was placed in tray 5A and is in Pail #91, it was 8.91mSv/hr upon removal from the south hot cell. There are 5 free slots left in the storage vault.

  37   Tuesday, October 25, 2011, 08:47 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredElectrical check

TM#4 with SiC#26 HP has been checked electrically it has passed. It was noted that the Megger check of the Oven to Chassis (earth ground) and Oven to 60kV Common is low but will not hinder running, according to Don Jackson.  Also yesterday the transition piece that sits on the 55 pin connector was damaged from excessive handling, it was removed and repaired and it now back in place.

  38   Tuesday, October 25, 2011, 11:58 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredModule move

TM#4 with SiC#26 HP has been moved from the south hot cell to the conditioning station.

  40   Friday, October 28, 2011, 08:24 Travis CaveConditioning StationStandard OperationTM4SiC#26 High PoweredModule move

TM#4 moved from conditioning station to south hot cell. For further leak checking.

  45   Monday, October 31, 2011, 08:51 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredModule move

TM#4 with SiC#26 HP moved from the south hot cell to the conditioning station.

  48   Friday, November 04, 2011, 11:12 Travis CaveConditioning StationStandard OperationTM4SiC#26 High PoweredModule move

TM#4 with SiC#26 HP move from the conditioning station to the East Target Station, move went well.

  49   Thursday, November 10, 2011, 14:33 Travis CaveSpent Target VaultStandard Operation  Spent Target Assay

For the week of November 7th 2011, four of a possible ten targets that are in storage were assayed. Targets are as follows:

Target             General average field @ 1 metre from edge of pail

SiC#24           1.99 mSv/hr

Nb#4               3.89 mSv/hr

Ta#25              4.57 mSv/hr

Ta#37              0.47 mSv/hr

 

These four are all viable spent targets to be shipped. We still need another couple of days of "UNINTERRUPTED" time to assay the remaining six targets, for us to have enough to make a ship of five to Chalk River.

  50   Monday, November 14, 2011, 14:07 Travis CaveITWStandard OperationTM1TaC#1Module move

TM#1 with TaC#1 from the west target station to the south hot cell. Move went well.

  51   Tuesday, November 15, 2011, 13:08 Travis CaveConditioning StationStandard OperationTM1 Move ot TM#1

TM#1 has been moved from the south hot cell to the conditioning station. Move went well.

  54   Thursday, November 17, 2011, 11:51 Travis CaveSpent Target VaultStandard Operation TaC#1Spent target move

TaC#1 was moved from the south hot cell to the storage vault. It was placed in pail#92 and put in vault slot 7B. It was 239mSv/hr upon removal from the south hot cell.

  55   Thursday, November 17, 2011, 11:52 Travis CaveConditioning StationStandard OperationTM1no targetModule move

TM#1 moved from the conditioning station to the south hot cell. Move went well.

  56   Friday, November 18, 2011, 09:44 Travis CaveSouth Hot-CellStandard OperationTM1UCx#3Electrical check

Electrical checks of TM#1 with UCx#3 have been completed. They all appear to be with in operational range. All megger checks were done at 500 volts. See attached file for details.