2738
|
Friday, January 03, 2025, 09:59 |
Adam Newsome | Facilities | Standard Operation | | | Safety Walkaround complete - ISAC Hot Cells, Target Hall |
A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified:
- Hot Cells:
- NHC right manipulator gripper stuck (known, repair planned)
- Target Hall:
- 50% of overhead light bulbs burnt out (David Wang contacted Electrical Services to rectify)
- One RH camera for target pit not working (Travis Cave notified)
Action has been taken on all deficiencies. |
2740
|
Friday, January 03, 2025, 12:34 |
Frank Song | 5 Shielding Blocks | Maintenance | | UCx#47 | shielding blocks moving |
Five shielding blocks are moved from ITE to storage area ( one of them is sitting on B2 as limit of room) for target stations maintenance in 2025 winter shut down . |
2744
|
Thursday, January 09, 2025, 11:08 |
David Wang | Facilities | Maintenance | | | ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings |
ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings and investigation in pit. A fault 17644 has been issued. this pump will be replaced in March when general fielding in vacuum pit is reasonable for the job. |
2746
|
Monday, January 13, 2025, 10:02 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#46 | Spent Target Move |
UC#46 was placed in pail# 301 in spot 1B and was 26.3mSv/hr when removed from the SHC. See attached PDF for vault
details. |
Attachment 1: Target_Index_2025-01-13.pdf
|
|