Monday, September 16, 2024, 08:23, chad fisher, North Hot-Cell, Repair, , , Model N Remote end #9352 reapir
|
On Friday, September 6, 2024 Model 'N' remote arm #9352 was removed from the NHC right side installed position to investigate an ongoing issue
with the tong motion circuit (no motion on the remote side when handle on operator side operated).
Inspection revealed that the tong cable on this arm have hopped its cable drum and rapped around the shaft of the cable drum. As well, the tong |
Monday, September 16, 2024, 08:48, chad fisher, Manipulator Maintenance, Maintenance, , , CRL Technicain Manipulator Maitenance Trip
|
Over the course of September 9th - September 13, 2024 a CRL manipulator technician carried out the following manipulator maintenance:
NHC operator side arm #9763 (right side installed position) - Inspection and re-tensioning of tong cable prior to re-installation (was a little
too tight). Operational. |
Monday, September 23, 2024, 11:26, David Wang, South Hot-Cell, Standard Operation, TM3, , TM3 window line has been leak checked.
|
TM3 window line has been leak checked after containment box removal and installation for insulator installation on water cup C. No leak.
|
Monday, September 23, 2024, 11:31, David Wang, South Hot-Cell, Development, TM3, , 10 pins lectrical check result after insulator is installed on water cap C.
|
10 pins lectrical check result after insulator is installed on water cap C.
pin 14 to 60kv bias has 20 Kohm @250V Megga check. The rest check on ohmmeter and megga @250 are either OLor over 25Mohm which are good. |
Monday, September 23, 2024, 16:06, Aaron Tam, South Hot-Cell, Repair, TM3, , Insulator Addition to Water block
|
September 23, 2024 - C. Fisher
Containment box removed
Insulator installed
New window line VCR seals installed
Dropped bolt
from TiC#8 removed
Containment box reinstalled
September 23, 2024 - A. Tam |
Tuesday, September 24, 2024, 09:37, Frank Song, ITE/ITW, Standard Operation, , , shielding blocks transfer
|
5 shielding blocks have been moved from ITE to ITW. |
Wednesday, September 25, 2024, 07:25, David Wang, Cooling, Maintenance, , , HALCW O2 level sensor maintenance.
|
HALCW O2 level sensor annual maintenance is done. sensor membrane has been changed and electrolyte has been refilled. gauge is calibrated. It works normal
after the job. |
Wednesday, September 25, 2024, 09:12, David Wang, South Hot-Cell, Maintenance, TM3, , Tm3 has been moved from SHC to silo.
|
Tm3 has been moved from SHC to silo. the move is smooth. |
Friday, September 27, 2024, 07:29, David Wang, Conditioning Station, Repair, , , TCS water system resistivity analyzer has been repaired.
|
TCS water system resistivity analyzer has been repaired. Two diodes and one capacitor on PS board were broken. They were replaced. Installed analyzer
back and tested it in system. it works fine. Operator closed e-fault, removed force on TS5, and enabled alarm on TS5 and TC1. |
Tuesday, October 01, 2024, 10:55, David Wang, South Hot-Cell, Standard Operation, TM2, , TM2 has been moved from ITE to SHC.
|
TM2 has been moved from ITE to SHC. Peter did the move with Travis on help. The move is smooth. |
Tuesday, October 08, 2024, 11:45, David Wang, South Hot-Cell, Standard Operation, TM2, , Tm2 electrical check with Ta#68 installed at SHC.
|
ABCD was dead shorted to 60kv bias during the first time measurement after target installation. Target was removed and reinstalled again with new VCR
seals by Ferran. during target removal process, short disappeared when Aaron remove bolts on CD tube heaters terminal. leak check and electrical
check result are good after second time target installation. |
Thursday, October 10, 2024, 12:20, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround complete - ISAC Hot Cells, Target Hall
|
A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Friday, October 11, 2024, 15:59, Aaron Tam, Facilities, Repair, , , ISAC B2 North Hot Cell Phone Fixed
|
Resolution comment / Commentaire de résolution:
Fixed issue by changing patch cord that was connected to the
switch from patch panel. |
Tuesday, October 15, 2024, 12:57, Frank Song, ITW/ITE, Standard Operation, , , shielding blocks transfer
|
5 shielding blocks are transferred from ITW to ITE, Target Area is secured again after moving. |
Thursday, October 24, 2024, 10:37, David Wang, Conditioning Station, Standard Operation, , , TCS water system functionnal test.
|
TCS water system has been started for functional test. System parameters including pressure, all temperature sensors, flow rate sensors, resistivity
are ok. I will watch on chiller CP1/2/3 in rest of the week and make sure chiller CP1/2/ 3 auto stage in/out work fine. |
Monday, November 18, 2024, 12:18, Aaron Tam, South Hot-Cell, Repair, , , SHC West Manipulator Repair
|
November 14, 2024 - Aaron Tam w/ Chad Fisher
Following ID: 2716
"Nov. 8, 2024 - Aaron Tam |
Monday, November 25, 2024, 09:56, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 move - silo to SHC
|
TM3 was moved from silo to SHC with no target. Move successful. |
Tuesday, November 26, 2024, 13:54, Adam Newsome, Conditioning Station, Standard Operation, TM3, , TM3 move - SHC to TCS
|
TM3 was moved from SHC to TCS with UCx#47. The move was smooth. |
Tuesday, December 03, 2024, 10:51, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM2 move - ITE to SHC
|
TM2 was moved from ITE to SHC with Ta#68 target. During the move, a railing was lightly bumped by the corner of the module - no obvious damage or issues
have been observed. Otherwise, the move was smooth. |
Tuesday, December 03, 2024, 12:28, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM3 move - TCS to ITE
|
TM3 was moved with UCx#47 from TCS to ITE. The move was smooth. |
|