47
|
Wednesday, November 02, 2011, 13:12 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | SiC#26 High Powered | High Voltage (HV) testing | The silicon carbide targets voltage
was raised to 42 kV today before continuous
current draw was observed. It took roughly |
|
|
46
|
Tuesday, November 01, 2011, 11:50 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 leak test on conditioning station | I did a leak check again on TM4 today.
This time, the leak detector pump to the
bottom on both base pressure(0.0xE-4 torr) |
|
|
45
|
Monday, October 31, 2011, 08:51 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | SiC#26 High Powered | Module move | TM#4 with SiC#26 HP moved from the south
hot cell to the conditioning station. |
|
|
44
|
Friday, October 28, 2011, 14:42 |
Bevan Moss | South Hot-Cell | Maintenance | TM4 | | Leak check on service cap feed through | After Chad and Davids leak check
results from the containment box it was decided
to perform a leak check on the feed through |
|
|
43
|
Friday, October 28, 2011, 14:29 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | | Leak Check on October 27/10/2011 | A leak check was performed on the module
on October 27/10/2011 by David Wang and was
reported to Bevan Moss but it never made |
|
|
42
|
Friday, October 28, 2011, 09:37 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | SiC#26 HP Febiad | SiC#26 installed on TM4 | HP febiad target SiC#26 was installed onto
Tm4 on Monday morning.
"JP's" connector required |
|
|
41
|
Friday, October 28, 2011, 09:30 |
chad fisher | South Hot-Cell | Repair | TM4 | | Tube Heater + Leak Check C.B. | Base Pressure: 0.0x10-4
Stable Leak Rate: 0.0x10-9
Leak check of tube heater circuit, |
|
|
40
|
Friday, October 28, 2011, 08:24 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | SiC#26 High Powered | Module move | TM#4 moved from conditioning station to
south hot cell. For further leak checking. |
|
|
39
|
Tuesday, October 25, 2011, 16:57 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | | Turbo Pump 1 issues | Roughing on TM1 started at ~15:00 today
by ~16:30 the module had reached a pressure
of ~200 mTorr and the turbo pumps were turned |
|
|
38
|
Tuesday, October 25, 2011, 11:58 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | SiC#26 High Powered | Module move | TM#4 with SiC#26 HP has been moved from
the south hot cell to the conditioning station. |
|
|
37
|
Tuesday, October 25, 2011, 08:47 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | SiC#26 High Powered | Electrical check | TM#4 with SiC#26 HP has been checked electrically
it has passed. It was noted that the Megger
check of the Oven to Chassis (earth ground) |
|
|
36
|
Wednesday, October 05, 2011, 09:41 |
Travis Cave | Spent Target Vault | Standard Operation | | UCx#2 | Spent target move | The spent UCx #2 target has been moved
into storage. It was placed in tray 5A and
is in Pail #91, it was 8.91mSv/hr upon removal |
|
|
35
|
Tuesday, October 04, 2011, 14:13 |
Travis Cave | ITW | Standard Operation | TM1 | TaC#1 | Move ot TM#1 | Move of TM#1 with the TaC#1 target has
been moved from the south hot cell to the
west target station. |
|
|
34
|
Monday, October 03, 2011, 14:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | TaC#1 | Electrical check | TM#1 with TaC#1 installed passed the electrical
test. With a value of 882MOhms that was meggered
from the heat shield to the chassis, all |
|
|
33
|
Monday, October 03, 2011, 11:54 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#2 - TaC#1 | Target change UCx#2-TaC#1 | UCx#2 has been removed from Tm1 and put
in a bucket with a slow argon feed and a
lid placed lossely on top. |
|
|
32
|
Monday, October 03, 2011, 11:00 |
Travis Cave | ITW | Standard Operation | TM1 | UCx#2 | Move from west station to south hot cell | TM#1 with UCx#2 has been moved from the
west station to the south hot cell. Move
went well. |
|
|
31
|
Thursday, September 29, 2011, 11:11 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#36 | Spent target move | The spent Ta#36 has been moved to the storage
vault. It was placed in pail #90, and placed
into slot 3B, it was 111mSv/hr upon removal |
|
|
30
|
Wednesday, September 28, 2011, 11:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | TM#4 moved from South Hot Cell to to North East Silo. | TM#4 moved from South Hot Cell to to North
East Silo, move went well. |
|
|
29
|
Wednesday, September 28, 2011, 10:06 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#36 | Ta#36 Removal | Ta#36 was removed from target module 4.
The standard, unexplained, un-investegated,
un-resolved "arc" were again present |
|
|
28
|
Wednesday, September 28, 2011, 09:07 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#36 | Move of TM#4 from East target station to south hot cell. | Move of TM#4 with Ta#36 from East target
station to south hot cell, move went well. |
|