Monday, July 16, 2012, 11:55, Bevan Moss, Crane, Repair, , , Crane has stopped working
|
Bevan Moss wrote:
In the AM today David and I used the crane to raise the ground plate sheet metal into place. This afternoon when I |
Tuesday, April 04, 2017, 14:39, David Wang, Crane, Standard Operation, , , Crane check main hoist on jogging with shielding plug lifted.
|
Today, I checked TH crane main hoist when shielding plug is installed into ITE pit. I did some jogging actions on main hoist during the operation.
Everything looks fine. No burning smell, no strange noise. An outside crane expert suggest that jogging is the worst working situation for crane. We have
to use jogging actions during our crane operation. But, we could try to use less jogging when operate the crane. |
Monday, December 21, 2020, 11:22, Adam Newsome, Crane, Standard Operation, , , Crane Shutdown for Power Outage
|
The Target Hall Crane has been shut down in preparation for the power outage tomorrow (Dec 22). Power will be restored on Dec 23.
Dec 23 update: power has been restored. The crane appears to be in working condition as there is no fault indicator on the PLC. |
Tuesday, December 19, 2017, 10:40, Don Jackson, Crane, Maintenance, , , Crane Power during winter break
|
The power to the crane and controls were turned off using the power switch in the Crane Control room. The main disconnect switch in the target
hall was not touched.
All site power will be off for a period of time during the Christmas break and this removes the crane from any issues when power is restored. |
Monday, November 22, 2021, 12:44, Adam Newsome, Crane, Repair, , , Crane PLC Fault: 0004h
|
An issue was observed in which the target hall crane was not functioning: the N-E-S-W and up/down motions did not work, however the rotation motion did
work. These symptoms were similar to what was observed in the past under https://elog.triumf.ca/TIS/RH-ISAC/2039
and https://elog.triumf.ca/TIS/RH-ISAC/1845 |
Monday, January 05, 2015, 12:47, Anders Mjos, Conditioning Station, Development, TM2, , Cooling package started
|
by "enable staging" button. MP3 has to be turned off-on to open WPV1 |
Tuesday, November 12, 2013, 14:33, Bevan Moss, Conditioning Station, Repair, , , Cooling manifold returned
|
The cooling manifold for the conditioning station high power water cooled lines has been returned. The cooling package can once again be operated |
Monday, May 27, 2013, 10:37, Bevan Moss, Conditioning Station, Maintenance, TM4, , Cooling Systems topped off
|
Rob walker has flushed and refilled the primary side of the system (note the water still looks nasty). This morning the primary side of system needed
to be bled as there were air pockets. Also TK2 had reached its low point and needed to be topped up. |
Monday, March 25, 2013, 09:35, Bevan Moss, Conditioning Station, Standard Operation, TM4, CS Test Target #1, Cooling Package and Vacuum Stopped
|
The cooling package and vacuum was stopped today at 9:26 so the module can be move. |
Thursday, March 14, 2013, 10:04, Bevan Moss, Conditioning Station, Standard Operation, TM4, CS Test Target 1, Cooling Package Started
|
The cooling package was started at 10:00 today. See attached picture. There is another snap shot at 10:03. |
Thursday, March 14, 2013, 11:56, Bevan Moss, Conditioning Station, Standard Operation, TM4, CS Test Target 1, Cooling Package Started
|
Bevan Moss wrote:
The cooling package was started at 10:00 today. See attached picture. There is another snap shot |
Monday, April 22, 2013, 11:31, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Cooling Package Started
|
Cooling Package was started at 9:25 this morning inlet conductivity is 0.08 Mohm at 22.9C. Resistance reached 5.33 Mohm by 11:30 |
Monday, October 21, 2013, 10:52, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Cooling On and Electrical Connections Made
|
The electrical connection have been made and cooling package was started at ~10:50am today |
Friday, July 03, 2015, 09:27, Anders Mjos, Conditioning Station, Development, , , Controls working on access control in EPICS
|
Some reboots will be done. |
Wednesday, October 22, 2014, 13:05, Anders Mjos, Conditioning Station, Maintenance, , , Controls upgrade on TCS
|
See work permit for details |
Tuesday, February 19, 2019, 10:20, chad fisher, South Hot-Cell, Repair, TM2, , Containment box removed
|
Containment box has been removed from TM2 in preparation for source tray removal. I will walk Aaron through removal of the optics tray today also. |
Friday, May 10, 2013, 09:26, chad fisher, South Hot-Cell, Repair, TM3, , Containment box reinstalled
|
the containment box has been reinstalled onto TM3. After electrical checks it is ready to move to the conditioning station...for electrical tests. |
Friday, February 07, 2020, 08:05, chad fisher, South Hot-Cell, Development, TM4, , Containment box off for IGLIS
|
The containment box has been removed from TM4 in prep for the IGLIS wiring job. |
Friday, March 05, 2021, 09:12, Matthew Gareau, North Hot-Cell, Development, TM3, , Containment box door removal and swivel arm test
|
First thing I entered into the NHC to install to the target kart mounting clip, and remove excess tools and materials from the hotcell
After the TM3 without a target was lowered into the NHC.
Once inside, with the use of the manipulators, I was able to remove the containment box door, place it on the swivel arm, move the arm out of the |
Wednesday, September 25, 2013, 06:59, maicodallavalle, South Hot-Cell, Standard Operation, TM3, , Containment box cover
|
The containment box cover has had all the bolts installed and all bolts were checked with a mirror. TM3 has been raised and is ready for the last
electrical test before it goes to the conditioning station. |
|