  2126   Tuesday, July 21, 2020, 14:22 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism TestThe emergency close mechanism for the Storage
Vault door was tested by Adam Newsome and
Travis Cave. The door was opened to its fully
  
  2128   Monday, July 27, 2020, 10:00 Travis CaveSouth Hot-CellMaintenance  Entrance module move The West Entrance module has been
moved from the west target station to the
south hot cell for repairs.
  
  2129   Tuesday, July 28, 2020, 09:26 chad fisherSouth Hot-CellRepair  Entrance Module Wire ScannerEntrance module wire scanner has been replaced.
Pictures to follow.
  
  2130   Wednesday, July 29, 2020, 09:20 Travis CaveITWMaintenance  Entrance module move The West Entrance module has been
moved from the south hot cell back to the
West Target Station.
  
  2132   Thursday, August 06, 2020, 14:33 Adam NewsomeSpent Target VaultDevelopment  Safety Group Relay Interface InstallationA relay contact-based interface module
was installed in between Safety Group's storage
vault door enable junction box and Remote
 IMG_20200806_091438.jpg 
  2135   Wednesday, August 19, 2020, 10:17 Adam NewsomeSouth Hot-CellStandard Operation  ITW Entrance Module moved to SHCITW Entrance Module was moved from west
station to South Hot Cell.
  
  2136   Monday, August 24, 2020, 10:11 Adam NewsomeITWStandard Operation  Entrance Module to ITWEntrance Module was moved from South Hot
Cell to ITW Station.
Note: weight of entrance module,
  
  2141   Thursday, August 27, 2020, 11:14 Travis CaveSpent Target VaultStandard Operation Graphite #1Spent Target Move Graphite #1 along with the broke
2A2M19 wire scanner have been placed in the
spent target vault see attached PDF for deatails.
 Target_Index_2020-08-27.pdf 
  2143   Tuesday, September 08, 2020, 10:37 Travis CaveITWStandard Operation no targetEntrance module move The West Entrance module has been
moved to the south hot cell for repairs.
  
  2147   Thursday, September 24, 2020, 10:34 Travis CaveSpent Target VaultStandard Operation UC#30Spent Target Move UC#30 has been placed into the spent
target vault, it was placed in pail 238 and
in spot 1A of the vault. It was 81.5 mSv/hr
 Target_Index_2020-09-24.pdf 
  2158   Tuesday, October 27, 2020, 11:46 Matthew GareauNorth Hot-CellRepair  Ratcheting repair issues with both left and right master  

  
  2159   Friday, October 30, 2020, 09:02 Travis CaveSpent Target VaultStandard Operation Ta#48,51,54 SiC#35, and UC#25Repacking of the targets. Targets Ta#48,51,54 SiC#35,
and UC#25 were repacked and placed in the
mini vault. In the following order back to
 Target_Index_2020-10-30.pdf 
  2161   Thursday, November 05, 2020, 10:23 David WangSpent Target VaultStandard Operation  TM2 old source tray and TM4 optic tray in vault tray#9.TM2 old source tray and TM4 optic tray
are stored together in vault tray#9. The
fielding measurement at SHC post 0.5 meter
  
  2163   Thursday, November 12, 2020, 10:02 Travis CaveSpent Target VaultStandard Operation UC#31Spent Target Move UC#31 has been moved from the south
hot cell to the spent target vault. It is
in spot 8B of the vault in pail # 224 and
  
  2167   Thursday, November 19, 2020, 12:00 Adam NewsomeSpent Target VaultStandard Operation C#2Spent Target MoveC#2 has been moved from the south hot cell
to the spent target  vault. It is in spot
8A of the vault in pail # 235 and was 185
  
  2173   Monday, December 21, 2020, 11:22 Adam NewsomeCraneStandard Operation  Crane Shutdown for Power OutageThe Target Hall Crane has been shut down
in preparation for the power outage tomorrow
(Dec 22). Power will be restored on Dec 23.
  
  2174   Thursday, December 24, 2020, 09:00 Matthew GareauNorth Hot-CellDevelopment   NHC USB connection    
  2180   Friday, January 22, 2021, 12:34 David WangITEStandard Operation  ITE HV test.ITE annual HV test is done. No module in
station. The bias power supply has been ramped
up to 49KV on control page. We still have
  
  2182   Monday, January 25, 2021, 12:33 David WangITWStandard Operation  ITW bias HV testRamp up ITW bias to 57KV. no spark. 200uA
leaking current at 57KV. The test is done
without target module in station.  
  
  2183   Wednesday, January 27, 2021, 14:30 David WangCoolingDevelopment  High active water system purgingHigh active water are purged to holding
tank at B2  level. There should be around
48 gallons are purged out of system. No purging
  