Message ID: 2111
Entry time: Friday, June 26, 2020, 10:43
|
Author: |
Adam Newsome |
Category: |
Spent Target Vault |
Type: |
Standard Operation |
Module: |
|
Target/Number: |
|
Subject: |
Routine mechanical inspection: storage vault and mini-storage drive systems |
|
|
An inspection was performed on drive systems for both storage vaults (main and mini) by Adam Newsome and Dan McDonald. The functionality was not tested. Overall, nothing concerning was discovered.
Main Storage Vault:
- Chain inspected (OK) and lubricated
- Gearbox inspected - OK
- All drive system set screws checked and tightened (note: chain drive screw slightly loose)
- Sprocket alignment checked - OK
- Limit switches checked - OK
- Emergency close mechanism cable checked - OK
Mini-Storage:
- Chain inspected - OK
- Set screw checked - OK
- Gearbox inspected - OK (need inventory/spare in stock)
- Roller wheels checked - OK
|
|
|
|
|