  1409   Tuesday, November 29, 2016, 07:50 David WangConditioning StationStandard OperationTM2 TM2 is disconnected at TCS.Argon venting is done.   
  1412   Wednesday, November 30, 2016, 16:31 David WangConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.All water circuits are by passed on the
top of TM3. Water pumps and vacuum turbo-
pumps are started. Everything is ready for
  
  1414   Monday, December 05, 2016, 10:04 Aurelia LaxdalConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.


   
        
            
  
  1417   Friday, December 09, 2016, 18:05 Aurelia LaxdalConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.


   
        
            
  
  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pumpTCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S.
We will use TCS to take TM2 tomorrow afternoon.
  
  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut downUpdated target hall schedule for 2017 winter
shut down. See attachments 1,2
Update schedule after Febiad beam
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1425   Tuesday, January 24, 2017, 15:24 David WangConditioning StationStandard OperationTM2 TM2 electrical check and leack check.I did electrical check before and after
Fefiad target installation on TM2. The RU
(coil) Is till short to 60KV as before. Other
  
  1426   Tuesday, January 24, 2017, 15:29 David WangConditioning StationStandard OperationTM2 TM2 has been moved to TCS .I connected TCS vacuum system to TM2. The
station is under roughing now. All turbo
pumps will be started soon.
  
  1431   Friday, January 27, 2017, 10:52 David WangConditioning StationStandard OperationTM2 TM2 has been moved from TCS to ITEThe move is successful.   
  1433   Friday, February 03, 2017, 11:49 David WangConditioning StationStandard Operation  Update 2017 winter shutdown TH schedule.Update 2017 winter shut down target hall
schedule. See attachments
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1436   Thursday, February 09, 2017, 09:24 David WangConditioning StationDevelopment  Target module window cooling lines at TCS.Target module window  cooling lines
at TCS has been modified to use spare 2 channel
in TCS: WFB1. The old cooling lines used
  
  1438   Friday, February 10, 2017, 09:56 David WangConditioning StationStandard Operation  water has been refilled to TCS:TK2 TCS:TK2 , Water has been refilled to 28.5"
level. It was 15.1". Fall protection
equipment  are used during the job.
  
  1455   Tuesday, March 21, 2017, 10:06 Travis CaveConditioning StationStandard OperationTM4no targetmodule movedTM#4 has been moved from the SW Silo to
the conditioning station.
  
  1456   Tuesday, March 21, 2017, 11:59 David WangConditioning StationRepairTM4 Rust inpsection on TM4 service cap inside surface and shielding plug surface. Yasmine and I did a rust inpsection on
TM4 service cap inide surface and shielding
plug surface. No rust has been found. Also,
 11x 
  1460   Thursday, March 23, 2017, 11:42 David WangConditioning StationMaintenanceTM4 TM4 Sevice cap rust are cleaned out.TM4 service cap rust are cleaned out at
TCS. All top surface of TM4 are wiped and
cleaned . The module looks good now. see
 TM4_clean_up_at_TCS_006.JPGTM4_clean_up_at_TCS_007.JPGTM4_clean_up_at_TCS_002.JPGTM4_clean_up_at_TCS_008.JPGTM4_clean_up_at_TCS_005.JPG 
  1470   Wednesday, March 29, 2017, 11:42 Anders MjosConditioning StationStandard OperationTM4UC#19Conditioning UC#19 Wednesday, March 29, 2017, 11:37:
RGA on
Wednesday, March 29, 2017, 13:51:
 UC#19.docxTCS-2017-03-29_UC#19.rgaTCS-2017-03-30_UC#19.rgaTCS-2017-04-03_UC#19.rga 
  1471   Wednesday, March 29, 2017, 14:11 David WangConditioning StationStandard OperationTM4 small leak on TM4 Ta(-) water line.A small leak has been found on TM4 Ta(-)
which is marked as "B" on terminal
blocks. The LD base Leak rate is 1.2XE-8
 TM4_2017_leak_check_in_ITE.png 
  1472   Thursday, March 30, 2017, 11:21 David WangConditioning StationRepairTM4 Leak check on TM4 Ta(-) water lines in service capLeak check on TM4 Ta(-) water lines in
service cap is done. LD base LR after 50minutes
pumping down:0.0xE-9 atm.cc/sec. base pressure:
  
  1474   Tuesday, April 04, 2017, 10:23 David WangConditioning StationStandard OperationTM4 Helium pressure leak check on TM4 Ta(-) water lines This morning, The helium pressure leak
check on TM4 Ta(-) is done after TM4 finished
conditioning yesterday.  LD base LR:8.0XE-9
  
  1475   Tuesday, April 04, 2017, 10:24 David WangConditioning StationStandard OperationTM4 Stopped TCS pumps this morning Argon vented TCS and TM4 after pumps
are stopped.
  