Thursday, October 31, 2019, 08:49, Anders Mjos, Conditioning Station, Repair, , , Water leak on non-active cooling water circuit
|
Yesterday a leak was discovered in the ISAC-I experimental hall. The leak appears to be at the connection between the evaporator and the return water
line. 1 in of water was lost from TCS:TK1. The water is currently valved off to prevent further leakage.
A fault reportt has been submitted to mechanical |
Tuesday, November 12, 2019, 10:07, Travis Cave, Spent Target Vault, Standard Operation, , Ta#59, Spent Target Move
|
The spent Ta#59 was moved from the south hot cell to the spent target vault. See the attached for details. |
Thursday, November 14, 2019, 13:52, Travis Cave, Spent Target Vault, Standard Operation, , UC#22,23,24, Targets repackaged
|
The targets UC#22,23,24 have been repackaged into the newer stronger pails, and have been placed back in the mini vault with new numbers. See attached
PDF for details. |
Tuesday, December 03, 2019, 12:45, Adam Newsome, Spent Target Vault, Standard Operation, , SiC#38, SiC#38 in Pail 205 moved to Storage Vault: 4B
|
SiC#38 in Pail 205 was moved to section 4B of the storage vault. Dose rate when retrieving from Hot Cell was 22.2 mSv/h. |
Thursday, December 12, 2019, 14:39, Isaac Earle, Safe Module Parking, Development, , , SMP assembly shifted 1.0" north
|
The SMP assembly was shifted approximately 1.0" north today by pushing it, braced against the south wall, using a 100 Ton capacity air lifting bag
supplied by Beamlines Group. The move was one of the action items identified at the Gate 4A/4B close-out review. During commissioning of the
SMP, TM3 was installed into the vacuum vessel, which required the crane to be all the way at its south limit, so the move is to provide some margin for |
Thursday, January 02, 2020, 09:55, David Wang, Cooling, Standard Operation, , , I turned on HALC water pump MP2.
|
HALCW MP2 is switched onnow. There is a small amount of air trapped in system. The pump works fine. Water level and system resistivity will be
monitored for a while.
LALCW P5 and P6 are switched on for cooling HALCW. HALCW MP2 is in operation now. |
Thursday, January 02, 2020, 10:10, David Wang, Crane, Standard Operation, , , TH crane issue.
|
Target hall crane does not work properly after TH crane main power is switched off during Christmas time in control room. I switched the main power
back this morning. The only movement could be operated is crane rotation. Power is supplied crane. The control on N-S, E-W and up-down movements
do not work. We had the same problem last year. After trouble shooting, It was pointed to a PLC battery issue. Control group changed the battery and reloaded |
Friday, January 03, 2020, 13:15, Adam Newsome, Crane, Repair, , , Target Hall Crane PLC Module/Battery Replacement
|
The Target Hall Crane bridge and trolley motion was lost after a period of the crane having power disconnected over winter holidays. This is reported in
the following e-log: https://elog.triumf.ca/TIS/RH-ISAC/2039. This issue is a duplicate of what happened in 2019 at this time: https://elog.triumf.ca/TIS/RH-ISAC/1845
|
Tuesday, January 07, 2020, 08:02, David Wang, Cooling, Standard Operation, , , Switch on HALCW MP2
|
HALCW MP2 is switched on this morning after yesterday cooling tower maintenance. LALCW P5 and P6 pumps are started by isac operator as well. The
system is good so far. |
Tuesday, January 07, 2020, 09:37, David Wang, ITW, Standard Operation, , , 5 shielding blocks are moved out of ITW top.
|
5 shielding blocks are moved out of itw top. |
Wednesday, January 08, 2020, 10:34, David Wang, Assembly/Bench Test, Development, , , Module lifting assembly ITA0490
|
The second module lifting assembly ITA0490 is moved into TH and installed onto TM3 . It will stay with TM3. I adjusted the CofG on the assembly.
It is same to the first lifting assembly we are using now. After adjustment, The installation of assembly on TM3 are smooth. |
Friday, January 10, 2020, 10:26, David Wang, ITE, Standard Operation, , , ITE water signal inerlock check.
|
ITE water signal interlock check is done. Everything is good. It is a annual check we do in winter shut down time. |
Monday, January 13, 2020, 14:19, Travis Cave, Spent Target Vault, Standard Operation, , Ta#49 and Ta#52, spent target repackaging and moved to mini vault.
|
Targeta Ta#49 and Ta#52 have been repackaged anf moved to the mini vault. Ta#49 was taken out of pail number 146 and placed into pail 229. Ta#52
was taken out of pail number 152 and placed into pail 230. |
Monday, January 27, 2020, 10:40, David Wang, Cooling, Maintenance, , , ITE/ITW supply water presuure on dump circuits.
|
With both stations in operation,ITE dump supply gauge reading is 27 psi. ITW is 20 Psi. I adjusted ITW dump pressure to 25 psi by changing the
return line side pressure relieve valve.
ITE full operation+ ITW no TM: ITE dump pressure 27psi, ITW dump pressure 27psi. |
Thursday, February 06, 2020, 13:31, Adam Newsome, Spent Target Vault, Standard Operation, , UC#29, UC#29 moved to vault location 6A, in pail 225
|
UC#29 in pail 225 was moved to the storage vault, location 6A. Field measured at 22.4 mSv/hr at ~1m. |
Thursday, February 20, 2020, 09:27, David Wang, Spent Target Vault, Standard Operation, , , Inventory of mini storage and vault.
|
Repacked nSiC#1 in SHC and moved it to mini storage vault. Transferred UCx26 and UCx28# from vault to mini-storage. See attachment for vault and mini-storage
inventory. |
Thursday, February 27, 2020, 16:08, Anders Mjos, North Hot-Cell, Maintenance, , , Hot Cell Entry
|
Chad entered the NHC today to tighten set-screws on both slave side manipulators and re-align the West side slave. Work took place using the HC Confined
Space Entry procedure. See attached checklist. WP I2020-02-27-4 |
Friday, February 28, 2020, 09:36, David Wang, ITE, Repair, , , Entrance module TP1S broken piesces clean up.
|
Using the camera, Frank and I inspected the broken blades in vacuum duct bending section. We are pretty sure some of the broken parts are
fallen into bottom of entrance module and vacuum vessel since the broken pars are over on the edge of bending section. The blades rotated at high
speed. Basically, They were shoot to the duct opening when they were broken from the pump. Frank and I carefully swiped all broken parts from the |
Wednesday, March 04, 2020, 11:52, David Wang, ITE, Standard Operation, , , ITE HV test without module
|
ITE bias test is done to 48KV. No spark. We can not raise bias above 48KV. It looks like we have a current limit issue on control system when testing
above 48KV. John Cow checked current limit on PS locally. It is set to 8mA which is much higher than the test current. Isac operator issued an e-fault
to control group. |
Friday, March 06, 2020, 09:35, David Wang, Spent Target Vault, Standard Operation, , SiC #39, Spent target SiC#39 removal from SHC to storage vault.
|
Spent target SiC#39 is removed from SHC to storage vault at 4C in pail #227.The move is successful. Note:The small aluminum block holding wire
on pail lid could be contaminated by SHC manipulator during the lid installation in SHC. |
|