Entry  Thursday, January 30, 2020, 12:06, David Wang, ITW, Standard Operation, TM4, , ITW primary and secondary vacuum seals leak check.  

Connected LD to ITW(TM4) TP1. Base LR 0.0Xe-9 atm.cc/sec. Base pressure 0.0Xe-4 torr. All ITW primary and secondary air to vacuum seals are helium spray checked. There is a 5XE-9 atm.cc/sec leak on  exit2 module top cover plate o-ring seal. The location is on west  side, south corner of the plate. Hi- vacuum resin are sprayed to leak area, and leak checked  again. The leak is gone.   The other seals on ITW vacuum vessel are good.

 

Entry  Monday, February 03, 2020, 09:10, David Wang, ITW, Standard Operation, TM4, , ITW TPs are switched off. started of ITW argon venting. 

ITW is argon venting now.

Argon venting of ITW is done. It took about 4.0 to 4.5 hours to vent the ITW with 2-3 psi argon. The CG4 and CG4S showed 35 to 36 torr on epic page when mechanical gauge is 760torr in electrical. Argon gas bottle is closed in electrical room.

Entry  Wednesday, February 05, 2020, 10:49, David Wang, Conditioning Station, Standard Operation, TM4, , Remove of TM4 from SHC to TCS. 

TM4 has been moved from SHC to TCS. No target on module. The move is successful.

Entry  Wednesday, February 05, 2020, 10:54, David Wang, Conditioning Station, Standard Operation, TM4, , Roughing out TM4 at TCS. 

TCS MP1 is started to rough out TM4 and TCS. TCS and TM4 will be under roughing only today and tomorrow. No plan to start TCS and TM4 turbo pumps this time.

Entry  Thursday, February 06, 2020, 13:32, Adam Newsome, South Hot-Cell, Maintenance, TM4, , TM4 moved from Conditioning Station to South Hot Cell 

 TM4 was moved from conditioning station to south hot cell in preparation for wiring replacement. No target.

Entry  Friday, February 07, 2020, 08:05, chad fisher, South Hot-Cell, Development, TM4, , Containment box off for IGLIS 

The containment box has been removed from TM4 in prep for the IGLIS wiring job.

Entry  Friday, February 14, 2020, 14:06, David Wang, Conditioning Station, Standard Operation, TM4, , TCS vacuum system and water sytem are switched on. 

All turbo pumps are started. 

Entry  Friday, February 14, 2020, 14:13, David Wang, South Hot-Cell, Standard Operation, TM4, , SIS dummy target for IGLIS TM4 electrical check Dumm_SIS_target_for_IGLIS_test_on_TM4.pdf

Electrical check and HS, window leak check result at SHC. See attachment.

Entry  Thursday, February 20, 2020, 09:27, David Wang, Spent Target Vault, Standard Operation, , , Inventory of mini storage and vault. Mini_Vault_2020-02-20.pdfVault__2020-02-20.pdf

Repacked nSiC#1 in SHC and moved it to mini storage vault. Transferred UCx26 and UCx28# from vault to mini-storage. See attachment for vault and mini-storage inventory.

Entry  Wednesday, February 26, 2020, 08:45, David Wang, Conditioning Station, Standard Operation, TM4, , Remove of TM4 from TCS to SW silo 

TM4 has been moved from TCS to SW silo. The move is fine.

Entry  Thursday, February 27, 2020, 10:37, David Wang, Safe Module Parking, Standard Operation, TM2, , Start of SMP vacuum pump. 

TM2 in SMP with old SiC #39 target on it. SMP vacuum pump is started.

Entry  Thursday, February 27, 2020, 16:08, Anders Mjos, North Hot-Cell, Maintenance, , , Hot Cell Entry NHC_2020-02-27.pdf

Chad entered the NHC today to tighten set-screws on both slave side manipulators and re-align the West side slave. Work took place using the HC Confined Space Entry procedure. See attached checklist. WP I2020-02-27-4

Entry  Friday, February 28, 2020, 09:36, David Wang, ITE, Repair, , , Entrance module TP1S broken piesces clean up.  

Using the camera,  Frank and I inspected the broken blades in vacuum duct bending section. We are pretty sure some of  the broken parts are fallen into  bottom of entrance module and vacuum vessel since the broken pars are over on the edge of bending section. The blades rotated at high speed. Basically, They were shoot to the duct opening when they were broken from the pump. Frank and I carefully swiped all broken parts  from the edges  back to center of duct first. Then, We use vacuum cleaner sucked all broken parts out of the entrance module. We can see lots aluminum dust  during the clean up. This kind of aluminum dust also could  fallen down to bottom of module and vessel.  After clean up, We inspected duct with camera. We can see all broken pieces and dust are cleaned out.  The removed broken pieces will be stored with broken pump when the vessel bottom clean up is done.

Entry  Wednesday, March 04, 2020, 11:52, David Wang, ITE, Standard Operation, , , ITE HV test without module 

ITE bias test is done to 48KV. No spark. We can not raise bias above 48KV. It looks like we have a current limit issue on control system when testing above 48KV.  John Cow checked current limit on PS locally. It is set to 8mA which is much higher than the test current. Isac operator issued an e-fault to control group.  

 John Chow did a local test on PS. Everything works fine.The problem is on control system. We have a 48KV voltage limit problem on control system. We decide to end the test now. 48KV is good enough before this year mini-shut down. 

Entry  Wednesday, March 04, 2020, 14:30, David Wang, Safe Module Parking, Standard Operation, TM2, , Remove of TM2 from SMP to SHC. 

Frank and I removed TM2 from SMP to SHC. The move is successful.

Entry  Friday, March 06, 2020, 09:51, David Wang, South Hot-Cell, Standard Operation, TM2, , TM2 was moved from SHC to SMP yesterday. 

TM2 was moved from SHC to SMP yesterday.  The move is successful. TM2 is located at SMP. There is no hot target on module so SMP vacuum is not started.

Entry  Monday, March 09, 2020, 14:31, David Wang, ITE/ITW, Standard Operation, , , TH emergency exit test.  

Frank and I did the test.  The emergency exit hatch on roof was opened and closed twice. Everything works fine.

Entry  Wednesday, March 11, 2020, 10:39, Travis Cave, ITE, Maintenance, , , Entrance module move 

 The entrance module has been moved to the east station to the south hot cell for inspection from the turbo pump explosion.

Entry  Thursday, March 12, 2020, 13:42, David Wang, ITE/ITW, Development, , , New ITE IGLIS cables installation  

New IGLIS cables installation is done. Two bundle of new cables are pulled from ITE to electrical room. They are in one PVC conduit. The old cables are not removed yet. I will pull old cables out when new cables are installed onto device in ITE Faraday cage.

Entry  Thursday, March 12, 2020, 13:48, David Wang, ITE, Repair, , , Entrance module TP1S broken piesces clean up. 

The broken pieces in ITE entrance vacuum pit are vacuumed out.  At SHC, There are 4 pieces on module collimator block top,  wiring scanner top. Chad removed them out at SHC. Electrical check at module top is done by diagnostics group. Everything works fine.