Thursday, October 31, 2019, 10:17 |
David Wang | Assembly/Bench Test | Maintenance | TM2 | | Febiad target gas line leak check. |
Feibiad gas line for ITE and its adapter fittings for TM2 are tested today by installing them on a dummy water stem. No leak on VCO fitting, adapter o-rings, and all Swagelock fittings of this assembly. Manual valve on gas line works fine. The positional check on gas line between TM2 and ITW will be fulfilled next Tuesday during module disconnection. |
2037
|
Thursday, December 12, 2019, 14:39 |
Isaac Earle | Safe Module Parking | Development | | | SMP assembly shifted 1.0" north |
The SMP assembly was shifted approximately 1.0" north today by pushing it, braced against the south wall, using a 100 Ton capacity air lifting bag supplied by Beamlines Group. The move was one of the action items identified at the Gate 4A/4B close-out review. During commissioning of the SMP, TM3 was installed into the vacuum vessel, which required the crane to be all the way at its south limit, so the move is to provide some margin for future use, particularly if TM1 is put in the SMP as the extent of its shielding is slightly larger than the other modules.
One of the air fittings for the lid actuation cylinder on the north side was damaged during the move. It was replaced and correct functionality of lid actuation was then confirmed. |
2038
|
Thursday, January 02, 2020, 09:55 |
David Wang | Cooling | Standard Operation | | | I turned on HALC water pump MP2. |
HALCW MP2 is switched onnow. There is a small amount of air trapped in system. The pump works fine. Water level and system resistivity will be monitored for a while.
LALCW P5 and P6 are switched on for cooling HALCW. HALCW MP2 is in operation now. |
2039
|
Thursday, January 02, 2020, 10:10 |
David Wang | Crane | Standard Operation | | | TH crane issue. |
Target hall crane does not work properly after TH crane main power is switched off during Christmas time in control room. I switched the main power back this morning. The only movement could be operated is crane rotation. Power is supplied crane. The control on N-S, E-W and up-down movements do not work. We had the same problem last year. After trouble shooting, It was pointed to a PLC battery issue. Control group changed the battery and reloaded the program. I guess the battery is drained out very fast for some reason. So, We face the same problem again this year.
Adam checked control room main power supply. I checked in TH crane again. The problem is still there. We can confirm this is the same issue like last year. |
2040
|
Friday, January 03, 2020, 13:15 |
Adam Newsome | Crane | Repair | | | Target Hall Crane PLC Module/Battery Replacement |
The Target Hall Crane bridge and trolley motion was lost after a period of the crane having power disconnected over winter holidays. This is reported in the following e-log: https://elog.triumf.ca/TIS/RH-ISAC/2039. This issue is a duplicate of what happened in 2019 at this time: https://elog.triumf.ca/TIS/RH-ISAC/1845
It was determined from troubleshooting via PLC indicator lights that the memory battery had died during the power-off time, and because of this, the program stored was lost. Note that this is an anomaly - the battery should have lasted much longer than the shutoff duration of ~2 weeks.
The SLC500 module was replaced with a spare, which contained a new battery. The old SLC500 module is still functioning but the battery has been removed (spares will be ordered) - this module is stored in a cabinet drawer in the control room. It will need to be re-programmed if re-installed as the program was lost. The original program titled TargetHallCrane.RSS was downloaded to the module. The crane was tested in local mode and determined to be functioning.
The following links are resources for resolving this issue:
https://isaccontrols.wiki.triumf.ca/index.php/ISAC_Target_Hall_Crane
https://isaccontrols.wiki.triumf.ca/index.php/SHUTDOWN_2015_Tasks#ISAC_Target_Hall_Crane_Controls_DM_-_Completed
|
2041
|
Tuesday, January 07, 2020, 08:02 |
David Wang | Cooling | Standard Operation | | | Switch on HALCW MP2 |
HALCW MP2 is switched on this morning after yesterday cooling tower maintenance. LALCW P5 and P6 pumps are started by isac operator as well. The system is good so far. |
2042
|
Tuesday, January 07, 2020, 09:37 |
David Wang | ITW | Standard Operation | | | 5 shielding blocks are moved out of ITW top. |
5 shielding blocks are moved out of itw top. |
2043
|
Wednesday, January 08, 2020, 10:34 |
David Wang | Assembly/Bench Test | Development | | | Module lifting assembly ITA0490 |
The second module lifting assembly ITA0490 is moved into TH and installed onto TM3 . It will stay with TM3. I adjusted the CofG on the assembly. It is same to the first lifting assembly we are using now. After adjustment, The installation of assembly on TM3 are smooth. |
2045
|
Thursday, January 09, 2020, 14:14 |
David Wang | Conditioning Station | Standard Operation | TM3 | | Start of TCS roughing pump for TM3. |
I started TCS roughing pump. TM3 TP1 and TP2 will be started tomorrow morning. |
2046
|
Friday, January 10, 2020, 10:26 |
David Wang | ITE | Standard Operation | | | ITE water signal inerlock check. |
ITE water signal interlock check is done. Everything is good. It is a annual check we do in winter shut down time. |
2048
|
Tuesday, January 14, 2020, 10:12 |
David Wang | Conditioning Station | Standard Operation | TM3 | | Helium spray leak check on TCS. |
Using a long pole with a probe to spray helium on TCS vacuum seals and joints which are installed in TCS service pit. No response has been found on leak detector during leak check. TCS is leak free. |
2049
|
Tuesday, January 14, 2020, 10:19 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TCS vacuum system is switched off. |
TM3 TP1 and TP2 work fine in past 4 days. During operation, The current draw on pumps were 0.7A to 0.8 A. TM3 will be moved back to silo tomorrow. |
2051
|
Friday, January 24, 2020, 08:19 |
David Wang | ITW | Standard Operation | TM4 | | ITW water signal interlock check. |
ITW water signal interlock check is done. Everything works fine. ITW 2A2 tank water signal is broken and is not ok on XT2A2 page. I will fix it next week. |
2052
|
Monday, January 27, 2020, 10:40 |
David Wang | Cooling | Maintenance | | | ITE/ITW supply water presuure on dump circuits. |
With both stations in operation,ITE dump supply gauge reading is 27 psi. ITW is 20 Psi. I adjusted ITW dump pressure to 25 psi by changing the return line side pressure relieve valve.
ITE full operation+ ITW no TM: ITE dump pressure 27psi, ITW dump pressure 27psi.
2019-01-30: Water only supply to 2A beam lines only on both side, No TM2 and TM4 in water loop. ITE dump pressure 27psi, ITW dump pressure 27psi. |
2053
|
Wednesday, January 29, 2020, 12:37 |
David Wang | ITE | Standard Operation | TM2 | | ITE primary/secondary vacuum vessel leak check. |
Leak check on ITE vacuum vessel is done. LD base leak rate 0.0XE-9atm.cc/sec. base pressure 0.0Xe-4torr. Sprayed helium on all ITE primary and secondary vacuum vessel seals(including TM2). No leak . Also,70psi helium pressurized TM2 waterlines inside the module for each circuit 3 minutes. No leak on all operating TM2 waterlines. |
2054
|
Thursday, January 30, 2020, 10:22 |
David Wang | ITW | Standard Operation | TM4 | | TM4 water lines helium pressure leak check. |
TM4 internal water lines helium pressure leak check at ITW : 70psi helium 5 minutes on each circuits. Base leak rate 0.0X E-9 atm.cc/sec. Base pressure 0.0X E-4torr. Only B line(Oven -) has a tiny 1.5Xe-9 atm.cc/sec response on LD during the check . All others all perfect good. |
2055
|
Thursday, January 30, 2020, 12:06 |
David Wang | ITW | Standard Operation | TM4 | | ITW primary and secondary vacuum seals leak check. |
Connected LD to ITW(TM4) TP1. Base LR 0.0Xe-9 atm.cc/sec. Base pressure 0.0Xe-4 torr. All ITW primary and secondary air to vacuum seals are helium spray checked. There is a 5XE-9 atm.cc/sec leak on exit2 module top cover plate o-ring seal. The location is on west side, south corner of the plate. Hi- vacuum resin are sprayed to leak area, and leak checked again. The leak is gone. The other seals on ITW vacuum vessel are good.
|
2056
|
Monday, February 03, 2020, 09:10 |
David Wang | ITW | Standard Operation | TM4 | | ITW TPs are switched off. started of ITW argon venting. |
ITW is argon venting now.
Argon venting of ITW is done. It took about 4.0 to 4.5 hours to vent the ITW with 2-3 psi argon. The CG4 and CG4S showed 35 to 36 torr on epic page when mechanical gauge is 760torr in electrical. Argon gas bottle is closed in electrical room. |
2060
|
Wednesday, February 05, 2020, 10:49 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Remove of TM4 from SHC to TCS. |
TM4 has been moved from SHC to TCS. No target on module. The move is successful. |
2061
|
Wednesday, February 05, 2020, 10:54 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Roughing out TM4 at TCS. |
TCS MP1 is started to rough out TM4 and TCS. TCS and TM4 will be under roughing only today and tomorrow. No plan to start TCS and TM4 turbo pumps this time. |