ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
1834
|
Friday, November 30, 2018, 10:28 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#57 | Spent Target Move | The spent Ta#57 target has been moved
from the south hot cell to the spent target
storage it was placed in pail 174 and placed |
|
1837
|
Friday, December 07, 2018, 08:47 |
chad fisher | North Hot-Cell | Repair | | | North hot cell spare slave repair | The tong cable on the spare north hot cell
slave has been repaired. Slave came from
the factory with the tong cables straddling |
|
1838
|
Friday, December 07, 2018, 10:37 |
chad fisher | North Hot-Cell | Repair | | | Ariel connector test | Completed testing of connectors for Ariel
using the north hot cell.
Video can be found on docushare; |
|
1839
|
Monday, December 10, 2018, 15:31 |
Isaac Earle | North Hot-Cell | Development | | | NHC remote connection testing with manipulators | The following tests have been successfully
completed using the NHC manipulators:
Ventilation pre-filter |
|
1841
|
Tuesday, December 18, 2018, 11:13 |
Isaac Earle | North Hot-Cell | Development | | | NHC manipulator slave-end swap, RH test, and various other work | The following
North Hot Cell work was completed over the
last week under work permit I2018-12-12-1: |
|
1842
|
Wednesday, December 19, 2018, 14:41 |
Anders Mjos | Conditioning Station | Standard Operation | | No target | Installed Shield Block on TCS | Frank and Anders installed lid on TCS and
started vacuum system yesterday. To run over
the Holidays. Retrieved dose badge from operational |
|
1843
|
Wednesday, January 02, 2019, 10:26 |
Anders Mjos | Conditioning Station | Standard Operation | | | Restarrted TP1S | Found pumps off after the holidays. Restarted
roughing pump and TP1S |
|
1844
|
Thursday, January 03, 2019, 13:30 |
David Wang | ITW | Repair | | | ITH:MP1 | ITH:MP1 inlet pressure showed 10torr after
power outage during holiday. All ITE/W turbo-pumps
were tripped because of it. Removed one shielding |
|
1845
|
Thursday, January 03, 2019, 13:41 |
David Wang | Crane | Repair | | | Target hall crane PLC issue. | Target hall crane did not work properly
after power outage during Christmas time.
The only movement could be operated is crane |
|
1847
|
Friday, January 04, 2019, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | NHC cameras tested | The NHC module support flange cameras (4
total) as well as the NHCSA camera were tested
today and confirmed to be working properly. |
|
1849
|
Wednesday, January 09, 2019, 06:26 |
David Wang | Conditioning Station | Standard Operation | | | TCS vacuum pumps have been stopped. | The tCS will be vented soon for TM2 move
later this week. |
|
1852
|
Wednesday, January 09, 2019, 13:29 |
David Wang | ITW | Repair | | | ITH:MP1 | ITH: MP1 has been replaced due to its poor
performance. Its motor and power cable
are taken out and reused on new pump. Vacuum |
|
1855
|
Friday, January 11, 2019, 11:26 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#25 | Spent Target Move | The spent target in the south hot
cell has been moved to the spent target vault.
It was placed in pail 204 and placed in spot |
|
1857
|
Friday, January 11, 2019, 13:59 |
Isaac Earle | Safe Module Parking | Development | | | SMP motor selection decision | SMP drivetrain design work is currently
underway. Alejandro has selected a
suitable 1200:1 reducer which will give a |
|
1859
|
Friday, January 18, 2019, 10:26 |
Isaac Earle | North Hot-Cell | Development | | | NHC sealing improvements and repeat of RH test for LED lights | The following NHC development work was
completed under WP I2019-01-09-4:
Location of RH feature |
|
1860
|
Monday, January 21, 2019, 16:27 |
Isaac Earle | North Hot-Cell | Development | | | NHC in-cell camera wired to right side monitor | The NHC right side monitor has been
wired to display the signal from the in-cell
camera. This was tested using a snake |
|
1862
|
Thursday, January 24, 2019, 10:34 |
David Wang | ITW | Maintenance | | | Changed 24VDC plugs of TP solenoid valves in ITW | 3 damaged 24VDC plugs of TP solenoid valves
are replaced. Inspected other plugs. All
of them are in good condition now. |
|
1864
|
Thursday, January 31, 2019, 14:16 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding approval | Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915). After discussing |
|
1865
|
Monday, February 11, 2019, 10:26 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box and vacuum vessel moved to Target Hall | On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical |
6x |
1873
|
Thursday, February 21, 2019, 15:10 |
Isaac Earle | Safe Module Parking | Development | | | Seismic requirements for SMP | Dragan Mitrovic, TRIUMF structural engineer,
was consulted earlier this week regarding
seismic requirements for the SMP assembly. |
|