ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
 |
1894
|
Monday, March 18, 2019, 07:25 |
David Wang | Conditioning Station | Maintenance | TM3 | | TCS vacuum pumps have been stopped. | The TCS will be vented soon for TM2
move. |
|
1896
|
Thursday, March 21, 2019, 09:56 |
chad fisher | South Hot-Cell | Repair | TM2 | | Tray insertion | This morning new water block fasteners
and gas line capture nut fasteners were inserted
into the hot cell. Window waterline blank |
 |
1897
|
Monday, March 25, 2019, 10:11 |
Aaron Schmidt | South Hot-Cell | Repair | TM2 | | LP-FEBIAD Test Target (empty) | Link to previous target information: https://elog.triumf.ca/TIS/RH-ISAC/1039
|
|
1903
|
Monday, April 01, 2019, 14:56 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box and vacuum vessel installed in final location | Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall. This |
   |
1904
|
Thursday, April 04, 2019, 14:49 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum vessel support roller friction check | With the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate |
|
1905
|
Friday, April 05, 2019, 13:44 |
chad fisher | Spent Target Vault | Development | | | 2019 Pail drop tests |
Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed. |
|
1906
|
Friday, April 12, 2019, 11:44 |
chad fisher | South Hot-Cell | Standard Operation | | | Pail transfer | Pail transfer was undertaken in the south
hot cell. went very well except near the
end the master tong cable of the right hand |
|
1907
|
Wednesday, April 17, 2019, 12:03 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair | Broken handle cable of east manipulator
has been replaced and manipulator is operational
again. |
|
1909
|
Monday, April 29, 2019, 07:56 |
chad fisher | South Hot-Cell | Development | | | Pail transfers | Two pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed |
 |
1917
|
Wednesday, May 08, 2019, 10:29 |
Travis Cave | South Hot-Cell | Standard Operation | | | Entrance module move | The entrance module has been moved
from the west station to the south hot cell. |
|
1918
|
Friday, May 10, 2019, 10:23 |
chad fisher | South Hot-Cell | Repair | | | West Entrance module wire scanner replacement | West entrance module - visible broken or
disconnected wire visible on old/existing
wire scanner. Wire scanner removed, new one |
 |
1919
|
Monday, May 13, 2019, 09:55 |
Travis Cave | ITW | Standard Operation | | | Entrance module move | The West Entrance module has been
moved from the south hot cell to the west
target station. |
|
1920
|
Monday, May 13, 2019, 11:22 |
David Wang | ITW | Repair | | | ITW entrance module has been connnected. | Entrance module has been connected back
to ITW. Everything is normal. |
|
1921
|
Wednesday, May 15, 2019, 16:06 |
Isaac Earle | Safe Module Parking | Development | | | SMP module support flange installed and leak checked | The SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683. Dow Corning 111 sealing |
   |
1925
|
Friday, May 17, 2019, 16:46 |
Adam Newsome | Safe Module Parking | Development | | | SMP Controls Installation Update |
The following controls-related |
   |
1927
|
Wednesday, May 22, 2019, 11:50 |
David Wang | ITE | Standard Operation | TM4 | | TM2 has been connected in ITE. | TM2 has been connected in ITE. high active
water system and vacuum pumps are started.
The pumping down on TM2 and ITE is good |
|
1928
|
Wednesday, May 22, 2019, 11:52 |
David Wang | Conditioning Station | Maintenance | TM1 | | TM1 inpsection. | TM1 shielding plates and their holding
bolts are inspected. No corrosion.
TM1 is located at TCS now. Both TP1 and TP2 |
|
1930
|
Thursday, May 23, 2019, 11:22 |
Travis Cave | South Hot-Cell | Maintenance | | | Removing garbage from the south hot cell. | A 55 Gal. drum was remotely lowered
into the south hot cell. It was then filled
with compressable waste. Then the drum was |
|
1932
|
Tuesday, June 04, 2019, 08:46 |
David Wang | ITE | Standard Operation | TM2 | | ITE water signal interlock check. | ITE water signal interlock check is done.
Everything is good. Coil 2 circuit
no longer used in ITE . PQRU are looped as |
|
1935
|
Friday, June 07, 2019, 13:11 |
David Wang | Conditioning Station | Development | TM4 | | TCS and TM4. | TM4 has been connected at TCS for HV test.
TCS water system and vacuum pumps are switched
on. |
|