Entry  Friday, April 27, 2018, 15:06, Keith C Ng, ITW, Repair, , , ITW beam tube repair 6x
Vacuumed out remainder of debris from the wall penetration, removed cradle and checked condition. Down stream support bracket sees advanced stages of
material loss (OBO 20-30% loss). See attached photos.
RPG reports that the removed beam tube has 15k CPM on the interior of the beam tube. 
Entry  Tuesday, May 01, 2018, 10:54, Keith C Ng, ITW, Repair, , , 2a2 window installation and beamtube repair 20180420_2a2beamtuberepair_P1040025.JPG2018_2a2window00017.jpg
Yesterday we installed the 2a2 window, the drive screw was torqued until 70
ft-lbs and we stopped, the yoke is not fully closed to its hard stop with roughly 7/8" to 3/4" still to go. Similar to identical conditions to
2a3 beamline window install, see https://elog.triumf.ca/TIS/RH-ISAC/647 for that install. Otherwise
Entry  Friday, May 04, 2018, 11:21, David Wang, ITW, Repair, , , 2A2 winodw leak check in TH 
Anders and I leak checked new 2A2 window seal on ITW side. Leak detector was connected  to ITW TP4.  Base  leak rate 0.0Xe-9 atm.cc/sec.
base pressure 0.0xe-4 torr.  Sprayed 15-20 psi directly underneath 2A2 window by using exist 2a2 window leak check copper tube. The leak detector
got response in 5 seconds when helium was applied. the leak rate was 5xe-6 atm.cc/sec. Once the helium source was closed, the leak rate dropped quickly
Entry  Wednesday, May 09, 2018, 08:48, David Wang, ITW, Repair, , , 2A2 winodw leak check on ITW vacuum vessel. 
Leak detector is connected to ITW TP4. LD Base leak rate 0.0XE-09 atm.cc/sec. Helium line is connected to existing window leak check 1/8 " copper
tube. Applied 18psi helium for 1 minute. No response on LD. The window seal is good on ITW vacuum vessel. 
Entry  Thursday, May 17, 2018, 13:17, Travis Cave, ITW, Standard Operation, , , Entrance module move 
 The west entrance module has been moved from the silo to the west target station.
Entry  Tuesday, May 22, 2018, 10:02, Anders Mjos, Conditioning Station, Repair, , , Water leak from TK1 over the weekend 2018-05-22_TCS_TK1_water_leak.pngBroken_Valve.jpg2018-05-22_TCS_TK1_water_leak_archiver.png
Link to e-log,
Link to efault
Tank level down from 76 to 55 in on TK1
Entry  Monday, May 28, 2018, 14:06, Travis Cave, Spent Target Vault, Standard Operation, , SiC#37, Spent Target Move Target_Index_2018-05-28.pdf
 SiC#37 has been moved from the South Hot Cell to the Spent Target Vault. It was placed in Pail #165 and put in spot 3B of the vault and it measured
25.8mSv/hr upon removal from the hot cell. See the attached PDF for details
Entry  Thursday, June 21, 2018, 17:15, Isaac Earle, North Hot-Cell, Development, , , Motorla CP200 radio with throat mic tested in NHC 
 A Motorla CP200 portable two-way radio was tested today for use inside the ISAC hot cells.  A High Technology Communications Throat microphone
PRO model from Planet Headset was used with the radio.  Chad entered the NHC wearing the throat mic and radio under a air supplied hood to mimic real
world conditions.  Communication was clear with the other person in the NHC service area, in the SHC service area, at various locations on the B1
Entry  Friday, June 22, 2018, 13:59, chad fisher, South Hot-Cell, Repair, , , Soth Hot Cell Fields 
Field measurements have been taken to determine the level before entry for repair of manipulators.
Field on contact at manipulator is 560 uSv/h, and at approximately 1/2 meter at table surface 920 uSv\h.
Entry  Monday, June 25, 2018, 11:31, chad fisher, South Hot-Cell, Standard Operation, , , Fields at Al cover 
The shield door has been opened and fields measured at 77 uSv/h on contact at the AL. panel.
Entry  Monday, June 25, 2018, 16:42, Anders Mjos, Conditioning Station, Development, , , Testing new high current connectors 
Shorted TGHT with new high current connector assembly and heated to 600 A. Temperature measured on half way point on cable ~ 70 deg C and on connector
~60 deg C at 600 A, 45 / 40 deg C at 400 A. Target Hall locked out during test
Entry  Tuesday, June 26, 2018, 08:56, chad fisher, South Hot-Cell, Standard Operation, , , South Hot Cell Fields 
hot items have been moved and shielded as much as possible. Field at left manipulator has been reduced from 560 uSv/h to 85 uSv/h.
Entry  Friday, June 29, 2018, 10:12, chad fisher, South Hot-Cell, Maintenance, , , Manipulator Tong Cable Replacement 
Tuesday, June 26 the broken tong cable was replaced on the west manipulator in the south hot cell. Wednesday the tong cable was preemptively replaced
on the east manipulator of the south hot cell.
Entry  Friday, June 29, 2018, 10:27, chad fisher, South Hot-Cell, Maintenance, , , South Hot Cell Filter Change 
At the end of manipulator repair Thursday the ventilation pre-filter in the hot cell was changed. Old filter remains in the hot cell until such time
as it can be removed.
Entry  Tuesday, July 03, 2018, 14:38, David Wang, ITW, Standard Operation, , , ITW water signals interlock check. 
Annual ITW water signals interlock check are done. Everything works good.
Entry  Thursday, July 19, 2018, 14:22, Isaac Earle, North Hot-Cell, Development, , , NHC diagnostic signals - connector and wiring details 
Installation of the diagnostic connections between the NHC hot and cold sides has been completed.  The cable bundle was prepared by Travis Cave
in the electronics workshop with connectors attached at one end only.  Metal fish tape was first ran through the conduit from the cold side to hot
side, the non-terminated end of the cable bundle was attached to the fish tape inside the cell, cable pulling lubricant was applied, then the cable bundle
Entry  Tuesday, July 31, 2018, 11:16, Travis Cave, Spent Target Vault, Standard Operation, , UC#22, Spent Target Move Target_Index_2018-07-30.pdf
 Yesterday the spent UC#22 target was moved from the south hot cell to the spent target vault. It was placed in pail #167 and placed in spot 4A
see attached PDF for details.
Entry  Wednesday, August 01, 2018, 09:47, Isaac Earle, North Hot-Cell, Development, , , NHC diagnostic signals and control panel tested 
 On July 30th the NHC diagnostic signals were tested:
- 9 pin CPC: a shorting plug was installed on the hot side - continuity check results were as expected
- 4 pin CPCs:  snake camera installed in both hot side connectors with portable monitor on cold side - both connectors worked as expected
Entry  Thursday, August 02, 2018, 07:57, David Wang, Conditioning Station, Standard Operation, , , Leak check on TM2 UCx #23 @ TCS and SHC. 
I did a helium pressure test on TM2 HS line at TCS. At 70psi helium, the leak rate is 2.5 xE-7 atm.cc/sec. I think this is the number that close to result
before which is 1.7xE-9 atm.cc/sec. WE know there is a small leak on this water block seal. Chad  and I did helium  spray check yesterday at
SHC. It was good at bottom scale.  No much worry on this low E-7 range leak. 
Entry  Thursday, August 02, 2018, 14:12, Travis Cave, Spent Target Vault, Standard Operation, , Nb#8, Spent Target Move Target_Index_2018-08-02.pdf
 The spent Nb#8 target was moved from the south hot cell to the spent target vault. It was placed in pail #168 and place in spot 2A in the vault.
See the attached pdf for vault details.