  1392   Monday, November 07, 2016, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#34Spent Target moveSpent SiC#34 was moved on the 3rd of November
and  placed in the spent target vault.
See attached pdf for details.
 Vault_Storage_November_3_2016.pdf 
  1395   Tuesday, November 08, 2016, 14:04 Isaac EarleNorth Hot-CellDevelopment  Interference check with TCS turbo pump and proposed NHC duct routingDavid Wang and I accessed the NHC today
to check if the proposed duct routing (IRH1618)
will interfere with servicing or replacement
 IMG_7577.JPGIMG_7583.JPGIMG_7582.JPG 
  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched offTCS will be vented tomorrow morning for
TM2 moving.
  
  1407   Friday, November 25, 2016, 09:04 Travis CaveSpent Target VaultStandard Operation SiC#35Spent Target moveOn November 24th 2016 the spent SiC#35
was moved from the south hot cell to the
spent target vault. see attached pdf for
 Vault_Storage_November_24_2016.pdf 
  1416   Friday, December 09, 2016, 14:58 Isaac EarleNorth Hot-CellDevelopment  NHC service area floor and top of roof block painted The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted
 NHC_SA_before_and_after.jpgNHC_roof_before_and_after.jpg 
  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pumpTCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S.
We will use TCS to take TM2 tomorrow afternoon.
  
  1421   Tuesday, January 17, 2017, 13:45 Isaac EarleNorth Hot-CellDevelopment  NHC ducting installed The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been
 IMG_7688.JPGIMG_7716.JPGIMG_7723.JPGIMG_7721.JPG 
  1423   Wednesday, January 18, 2017, 11:53 Isaac EarleNorth Hot-CellDevelopment  NHC partition wall installation complete The final panels of the partition
wall were installed today as per drawing
IRH1609.  Sealing, finishing, and painting
 IMG_7728.JPG 
  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut downUpdated target hall schedule for 2017 winter
shut down. See attachments 1,2
Update schedule after Febiad beam
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1430   Friday, January 27, 2017, 08:50 chad fisherSouth Hot-CellStandard Operation  UCx#18 and Ta#50 autopsy and spent target moveOn Thursday, January 26th UCx#18 and Ta#50
were inspected and packaged into spent target
pails, move to storage vault.
  
  1433   Friday, February 03, 2017, 11:49 David WangConditioning StationStandard Operation  Update 2017 winter shutdown TH schedule.Update 2017 winter shut down target hall
schedule. See attachments
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1434   Tuesday, February 07, 2017, 10:34 David WangITWMaintenance  ITW clean upITW has been cleaned up today.  All
station are vacuum cleaned. I wiped all HV
cover and HV area including conductors and
  
  1435   Tuesday, February 07, 2017, 15:57 Isaac EarleNorth Hot-CellDevelopment  Ventilation Ducting Gasket Installed Lead gasket IRH1633 was installed
today according to assembly drawing IRH1618
Rev B.
  
  1436   Thursday, February 09, 2017, 09:24 David WangConditioning StationDevelopment  Target module window cooling lines at TCS.Target module window  cooling lines
at TCS has been modified to use spare 2 channel
in TCS: WFB1. The old cooling lines used
  
  1437   Thursday, February 09, 2017, 14:07 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Shielding Window Gaskets Changed The North Hot Cell shielding window
gaskets have been changed and the window
has been filled with new oil.  Although
 23x 
  1438   Friday, February 10, 2017, 09:56 David WangConditioning StationStandard Operation  water has been refilled to TCS:TK2 TCS:TK2 , Water has been refilled to 28.5"
level. It was 15.1". Fall protection
equipment  are used during the job.
  
  1439   Wednesday, February 15, 2017, 12:07 chad fisherSouth Hot-CellMaintenance  Manipulator 'Z' motion cable replacement preparation statusAaron and I completed assembling (re-assembling)
the clean spare on Tuesday, February 14th
to assist in determining a procedure for
 20170215_113609.jpg 
  1440   Friday, February 24, 2017, 15:12 Isaac EarleNorth Hot-CellDevelopment  NHC interior walls/floor/ceiling re-finished, sealed, and paintedThe North Hot Cell interior walls, floor,
and ceiling were re-finished, sealed, and
painted by Omni Coating from Feb 6 - 17 under
 8x 
  1441   Monday, February 27, 2017, 14:23 chad fisherSouth Hot-CellRepair  Manip. 'Z' motion cable run throughAaron and I successfully completed a run
through on the procedure to replace the 'Z'
motion cable. I will be writing up the procedure
  
  1442   Tuesday, February 28, 2017, 17:51 Isaac EarleNorth Hot-CellDevelopment  NHC flanged ducting connection sealed The North Hot Cell ducting (IRH1617)
has been sealed with a bead of Sikaflex 1a
polyurethane construction sealant where the
 IMG_8012.JPG 