ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1353   Thursday, September 15, 2016, 11:05 Isaac EarleNorth Hot-CellDevelopment  NHC / SHC feedthrough panel removedThe sheet metal panel covering the NHC/SHC
feedthrough port was removed today using
a slide-hammer to pull out the concrete anchors
 original_panel.JPGpanel_removed.JPGtemp_panel.JPG 
  1354   Monday, September 19, 2016, 08:28 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)Post new  target hall Excel sheet
schedule for beam schedule 131. See attachment
1,2
 Target_Hall_shedule_131__Sep_to_Dec_2016.pdfTarget_Hall_shedule_131__Sep_to_Dec_2016.xlsxTarget_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf 
  1357   Tuesday, September 20, 2016, 11:48 David WangAssembly/Bench TestDevelopment  A silo and blue steel frame are removed out of TH A silo and blue steel frame are removed
out of TH this morning. They are transferred 
through ante room, and moved to experimental
  
  1362   Monday, September 26, 2016, 13:59 Travis CaveSpent Target VaultStandard Operation UC#17Spent Target moveThe spent UC#17 has been moved from the
south hot cell to the spent target vault.
See the attached pdf for details.
 Vault_Storage_September_26_2016.pdf 
  1366   Wednesday, September 28, 2016, 13:47 David WangConditioning StationStandard Operation  TCS pumping down during mini-shut down.A steel plate  is covered on TCS.
TCS roughing pump  is started now. The
TCS will be pumping down during mini-shut
  
  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016) Weekly update TH schedule for beam schedule
131. See attachments 1,2
 Target_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf 
  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stoppedArgon venting is started   
  1373   Thursday, October 20, 2016, 10:45 Travis CaveSpent Target VaultStandard Operation Ta#49Spent Target moveTa#49 has been removed from the south hot
cell and placed in the storage vault. It
is in pail 146 and in spot 6A.
  
  1375   Friday, October 21, 2016, 12:51 chad fisherSouth Hot-CellRepair  Manipulator RepairBroken cable has been replaced however
a cable has hopped some pulleys inside. After
two hours in cell the job was stopped with
  
  1377   Monday, October 24, 2016, 10:10 chad fisherSouth Hot-CellRepair  Manipulator Repair CompleteMaico entered the hot cell and re-strung
the skipped cable back onto the pulleys this
morning. Manipulator is now operational.
  
  1379   Monday, October 24, 2016, 12:22 chad fisherSouth Hot-CellRepair  TM2 Insulator replacementconductor insulators itd0053 and 54 have
been replaced on TM2. All fasteners (1/4-20
x 1 1/4 vented) torqued to 60 in lbs.
  
  1392   Monday, November 07, 2016, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#34Spent Target moveSpent SiC#34 was moved on the 3rd of November
and  placed in the spent target vault.
See attached pdf for details.
 Vault_Storage_November_3_2016.pdf 
  1395   Tuesday, November 08, 2016, 14:04 Isaac EarleNorth Hot-CellDevelopment  Interference check with TCS turbo pump and proposed NHC duct routingDavid Wang and I accessed the NHC today
to check if the proposed duct routing (IRH1618)
will interfere with servicing or replacement
 IMG_7577.JPGIMG_7583.JPGIMG_7582.JPG 
  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched offTCS will be vented tomorrow morning for
TM2 moving.
  
  1407   Friday, November 25, 2016, 09:04 Travis CaveSpent Target VaultStandard Operation SiC#35Spent Target moveOn November 24th 2016 the spent SiC#35
was moved from the south hot cell to the
spent target vault. see attached pdf for
 Vault_Storage_November_24_2016.pdf 
  1416   Friday, December 09, 2016, 14:58 Isaac EarleNorth Hot-CellDevelopment  NHC service area floor and top of roof block painted The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted
 NHC_SA_before_and_after.jpgNHC_roof_before_and_after.jpg 
  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pumpTCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S.
We will use TCS to take TM2 tomorrow afternoon.
  
  1421   Tuesday, January 17, 2017, 13:45 Isaac EarleNorth Hot-CellDevelopment  NHC ducting installed The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been
 IMG_7688.JPGIMG_7716.JPGIMG_7723.JPGIMG_7721.JPG 
  1423   Wednesday, January 18, 2017, 11:53 Isaac EarleNorth Hot-CellDevelopment  NHC partition wall installation complete The final panels of the partition
wall were installed today as per drawing
IRH1609.  Sealing, finishing, and painting
 IMG_7728.JPG 
  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut downUpdated target hall schedule for 2017 winter
shut down. See attachments 1,2
Update schedule after Febiad beam
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 