  1353   Thursday, September 15, 2016, 11:05 Isaac EarleNorth Hot-CellDevelopment  NHC / SHC feedthrough panel removed

The sheet metal panel covering the NHC/SHC feedthrough port was removed today using a slide-hammer to pull out the concrete anchors (this oversized panel would have interfered with the NHC partition wall).  50cpm was found on the inside of the panel, 100cpm on the NHC side lip of the feedthrough, and 350cpm on the face of the shielding bricks in the feedthrough.  Various dimensional measurements of the feedthrough were taken which will be added to the partition wall Solidworks model (IRH1609).  The panel was bagged for disposal and a temporary 20"x20" panel was put over the feedthrough and secured with duct tape.  A permanent panel with anchored supports that is compatible with the NHC partition wall will be designed and installed at a later date.  A swipe of the NHC walls and floor picked up 30cpm after completion of the job.  

Attachment 1: original_panel.JPG
original_panel.JPG
Attachment 2: panel_removed.JPG
panel_removed.JPG
Attachment 3: temp_panel.JPG
temp_panel.JPG
  1354   Monday, September 19, 2016, 08:28 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Post new  target hall Excel sheet schedule for beam schedule 131. See attachment 1,2

Post new target hall  MS project schedule for beam schedule131. See attachment 3,4

Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Attachment 2: Target_Hall_shedule_131__Sep_to_Dec_2016.xlsx
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 4: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1357   Tuesday, September 20, 2016, 11:48 David WangAssembly/Bench TestDevelopment  A silo and blue steel frame are removed out of TH

A silo and blue steel frame are removed out of TH this morning. They are transferred  through ante room, and moved to experimental hall TM assembly area for a long term storage. Swipes are done on the silo and frame before and during move. No contamination has been found .

  1362   Monday, September 26, 2016, 13:59 Travis CaveSpent Target VaultStandard Operation UC#17Spent Target move

The spent UC#17 has been moved from the south hot cell to the spent target vault. See the attached pdf for details.

Attachment 1: Vault_Storage_September_26_2016.pdf
Vault_Storage_September_26_2016.pdf Vault_Storage_September_26_2016.pdf Vault_Storage_September_26_2016.pdf Vault_Storage_September_26_2016.pdf
  1366   Wednesday, September 28, 2016, 13:47 David WangConditioning StationStandard Operation  TCS pumping down during mini-shut down.

A steel plate  is covered on TCS. TCS roughing pump  is started now. The TCS will be pumping down during mini-shut down.

  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Weekly update TH schedule for beam schedule 131. See attachments 1,2

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stopped

Argon venting is started

  1373   Thursday, October 20, 2016, 10:45 Travis CaveSpent Target VaultStandard Operation Ta#49Spent Target move

Ta#49 has been removed from the south hot cell and placed in the storage vault. It is in pail 146 and in spot 6A.

  1375   Friday, October 21, 2016, 12:51 chad fisherSouth Hot-CellRepair  Manipulator Repair

Broken cable has been replaced however a cable has hopped some pulleys inside. After two hours in cell the job was stopped with cables still off pulleys. Alternate tooling will have to be made and the job will continue Monday.

  1377   Monday, October 24, 2016, 10:10 chad fisherSouth Hot-CellRepair  Manipulator Repair Complete

Maico entered the hot cell and re-strung the skipped cable back onto the pulleys this morning. Manipulator is now operational.

  1379   Monday, October 24, 2016, 12:22 chad fisherSouth Hot-CellRepair  TM2 Insulator replacement

conductor insulators itd0053 and 54 have been replaced on TM2. All fasteners (1/4-20 x 1 1/4 vented) torqued to 60 in lbs.

  1392   Monday, November 07, 2016, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#34Spent Target move

Spent SiC#34 was moved on the 3rd of November and  placed in the spent target vault. See attached pdf for details.

Attachment 1: Vault_Storage_November_3_2016.pdf
Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf
  1395   Tuesday, November 08, 2016, 14:04 Isaac EarleNorth Hot-CellDevelopment  Interference check with TCS turbo pump and proposed NHC duct routing

David Wang and I accessed the NHC today to check if the proposed duct routing (IRH1618) will interfere with servicing or replacement of the TCS turbo pump.  A piece of plywood was placed in the future position of the NHC/TCS partition wall (IRH1609), and a ducting elbow was placed at the approximate position of the nearest elbow to the turbo pump.

David concluded that the ducting in the proposed location will not have any significant effect on replacement of the turbo pump, and he does not expect replacement will be difficult to perform after installation of the wall and NHC ducting.  Standing at floor level towards the east side of the TCS space and reaching upwards seemed to be the best way to reach the turbo pump flange bolts.  It was also noted that there was sufficient room in the TCS space for two workers to be in the area.

 

IMG_7577.JPG

 

IMG_7583.JPG

 

IMG_7582.JPG

  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched off

TCS will be vented tomorrow morning for TM2 moving.

  1407   Friday, November 25, 2016, 09:04 Travis CaveSpent Target VaultStandard Operation SiC#35Spent Target move

On November 24th 2016 the spent SiC#35 was moved from the south hot cell to the spent target vault. see attached pdf for details.

Attachment 1: Vault_Storage_November_24_2016.pdf
Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf
  1416   Friday, December 09, 2016, 14:58 Isaac EarleNorth Hot-CellDevelopment  NHC service area floor and top of roof block painted

 The concrete floor in the North Hot Cell service area and the top of the NHC roof block in the target hall have been painted with Macropoxy 646 oil based epoxy paint, colour Flint Grey.  Two coats were used for the NHC roof, and one for the service area floor.

 

NHC_SA_before_and_after.jpg

 

NHC_roof_before_and_after.jpg

  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pump

TCS TP1S has been started.

2017-01-23 afternoon: Stopped TP1S. We will use TCS to take TM2 tomorrow afternoon.

  1421   Tuesday, January 17, 2017, 13:45 Isaac EarleNorth Hot-CellDevelopment  NHC ducting installed

 The new ducting section connecting the existing duct termination in the TCS space to the NHC partition wall has been installed by Smith Sheet Metal contractors.  The installation drawing is IRH1618.  There was not enough clearance between the duct pipe and the TCS vessel to butt weld the new ductwork as originally intended.  Instead a flange was welded to the existing pipe and also to the new section and the two were bolted together.  Drawings of the modifications have been provided by the contractor, and as-built drawings will be completed at a later date.  There was not time for the contractor to fabricate a gasket for the flanged joint, so one will be installed by TRIUMF at a later date and included in the as-built drawing package.

Attachment 1: IMG_7688.JPG
IMG_7688.JPG
Attachment 2: IMG_7716.JPG
IMG_7716.JPG
Attachment 3: IMG_7723.JPG
IMG_7723.JPG
Attachment 4: IMG_7721.JPG
IMG_7721.JPG
  1423   Wednesday, January 18, 2017, 11:53 Isaac EarleNorth Hot-CellDevelopment  NHC partition wall installation complete

 The final panels of the partition wall were installed today as per drawing IRH1609.  Sealing, finishing, and painting of the NHC walls and floor can now commence.

 

IMG_7728.JPG

  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut down

Updated target hall schedule for 2017 winter shut down. See attachments 1,2

Update schedule after Febiad beam schedule changed to ITE. See attachments 3,4

Attachment 1: 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp
Attachment 2: 2017_Winter_Shut_Down_Target_Hall_Schedule.pdf
2017_Winter_Shut_Down_Target_Hall_Schedule.pdf
Attachment 3: 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp
Attachment 4: 2017_Winter_Shut_Down_Target_Hall_Schedule.pdf
2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 2017_Winter_Shut_Down_Target_Hall_Schedule.pdf