  608   Tuesday, February 25, 2014, 06:53 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(C-seal) installed on WB.

Chad and I did the leak check   on TM2 tube heater (+) water line  with blank off and C-seal  installed on  WB at South Hot Cell.The line was easy to pump down to 0.0xE-9atm.cc/sec and 0.0XE-4 torr on leak detector. Chad flushed lot helium around the water block (10 sec spray). No response had been found on leak detector.

  607   Monday, February 24, 2014, 13:52 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule move

TM#2 moved from the south hot cell to the conditioning station.

  606   Monday, February 24, 2014, 12:09 chad fisherSouth Hot-CellRepairTM2 C-seal blank off test

Circuit D has passed the vacuum leak check. Jig has been removed and containment box re-installed for move to conditioning station.

Attachment 1: TM2_20140224_1.jpg
TM2_20140224_1.jpg
  605   Monday, February 24, 2014, 11:05 chad fisherSouth Hot-CellRepairTM2 Circuit D blank off

The blank off with the o-ring has been removed, manipulator fixed, circuit D water block sealinhg surfaces cleaned and blank off with c-seals installed and torqued. Leak check will occur shortly.

  604   Thursday, February 20, 2014, 11:04 chad fisherSouth Hot-CellRepairTM2 Readying TM2 for C-Seal Leak Check

Containment box has been removed and water block jig installed.

Attachment 1: TM2_20140220_01.jpg
TM2_20140220_01.jpg
  603   Thursday, February 20, 2014, 09:45 Travis CaveConditioning StationStandard OperationTM2no targetmodule move

TM#2 has been moved from the conditioning station to the south hot cell.

  602   Tuesday, February 18, 2014, 11:26 David WangConditioning StationRepairTM2 I stopped turbo pumps and disconnected vacuum system on TM 2 and CS

I stopped turbo pumps and disconnected vacuum system on TM2 and CS. The TM2 will be moved to SHC for C seal installation on "D" water block.

  601   Monday, February 17, 2014, 09:32 David WangConditioning StationRepairTM2 helium pressure test on TM2 tube heater +(D) water line.

I did the helium pressure test on Tube heater+ line this morning. The vacuum on CS and TM2 are very good. The base lake rate on leak detector was 1.7xE-7 atm.cc/sec. Base pressure was 0.0xE-4torr.  I applied helium to the "D"line .The test started from 30psi up to 80psi on both side "D" line.The base leak rate slightly changed to 1.9xE-7 atm.cc/sec during the test,but not base pressure. At this base leak rate level, No obvious leak had been found . See attachment pictures. The test will be repeated later when the base leak rate could be pumped into E -8 or E-9(the best) range.            

Attachment 1: 002.JPG
002.JPG
Attachment 2: 003.JPG
003.JPG
Attachment 3: 004.JPG
004.JPG
Attachment 4: 012.JPG
012.JPG
Attachment 5: 016.JPG
016.JPG
Attachment 6: 018.JPG
018.JPG
  600   Thursday, February 13, 2014, 14:23 David WangSouth Hot-CellRepairTM2 Leak check on TM2 tube heater (+) water line with blank off(elastic seal) installed on WB.

Chad and I did the leak check on TM2 tube heater (+) water line  with blank off( + elastic o ring seal) installed on "D"  water block in SHC. We got the same no leak result as we got with rubber insert this morning.

Attachment 1: 005.JPG
005.JPG
Attachment 2: 001.JPG
001.JPG
  599   Thursday, February 13, 2014, 14:15 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.

David Wang wrote:

Chad and I did the pressure test on TM2tube heater+(D) water  line at SHC with shop air.We tested from 30psi to 80psi on both side of D line. The bubbles were found at 50-55psi on blank off seal in SHC.

 I would like to correct this E-LOG. There is no real  leaking bubble had been found during the whole test according to the information supplied by Chad  Fisher during  this afternoon meeting. I would like to attach some pictures took from TH during this test.

Attachment 1: 007.JPG
007.JPG
Attachment 2: 008.JPG
008.JPG
Attachment 3: 013.JPG
013.JPG
  598   Thursday, February 13, 2014, 13:30 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.

Chad and I did the pressure test on TM2tube heater+(D) water  line at SHC with shop air.We tested from 30psi to 80psi on both side of D line. The bubbles were found at 50-55psi on blank off seal in SHC.

  597   Thursday, February 13, 2014, 09:24 David WangSouth Hot-CellRepairTM2 Leak check TM2 tube heater (+) water line with rubber insert blocked WB in SHC

Chad and I  did the Leak checked TM2 tube heater (+) water line  with rubber insert plugged water block on " D"  in SHC. The Leak detector was very easy to pump down to the bottom leak rate and pressure. Chad checked the helium flow in SHC, and sprayed 10 second helium on  the block. There is no response had been found during the test. The test was repeated again and no leak has been found. See attachment pictures.

Attachment 1: 001.JPG
001.JPG
Attachment 2: 002.JPG
002.JPG
Attachment 3: 003.JPG
003.JPG
Attachment 4: 004.JPG
004.JPG
  596   Tuesday, February 11, 2014, 13:56 chad fisherSouth Hot-CellRepairTM2 waterblock cleaning

New cleaning and polishing pads have been inserted onto the hot cell as well as rubber bungs and a new blank off.

The inital waterblock cleaning with the "scotch bright" pads has been completed. See attached pictures...the first picture being before and the second after.

Tommorow the water block will have bungs put in and a leak check to check the block will take place. After that, the new blank off will be installed and tested.

 

Attachment 1: TM2_20140207_2.jpg
TM2_20140207_2.jpg
Attachment 2: TM2_20140211_2.jpg
TM2_20140211_2.jpg
  595   Friday, February 07, 2014, 10:29 chad fisherSouth Hot-CellRepairTM2 TM2 C.B. and circuit D

Containment box has been removed and the blank off from circuit D has been removed for inspection of both the blank off and water block sealing surface.

Attachment 1: TM2_20140207_1.jpg
TM2_20140207_1.jpg
Attachment 2: TM2_20140207_2.jpg
TM2_20140207_2.jpg
  594   Wednesday, February 05, 2014, 14:12 Travis CaveSpent Target VaultStandard Operation  Targets moved from mini storage to F-308s

All targets in the mini storage (4) have been moved from there and placed into the F-308s and those have been moved to the mech services room.

  593   Wednesday, February 05, 2014, 14:05 David WangSouth Hot-CellRepairTM2 Leak check TM2 tube heater (+) water line from inside service cap in TH.

Bevan and I did a leak check on TM2 tube heater+ from inside service cap in TH. The leak detector base leak rate 0.0xE-9 atm.cc/sec, base  pressure 0.0xE-4totrr. One of side panel on service cap was opened. Bevan sprayed the helium to the "D" line inside the blue insulator.The helium flow was checked , and he sprayed twice. No response has been found on leak detector.  See attachment pictures

Attachment 1: 005.JPG
005.JPG
Attachment 2: 008.JPG
008.JPG
Attachment 3: 005.JPG
005.JPG
  592   Tuesday, February 04, 2014, 09:42 David WangSouth Hot-CellRepairTM2 pressure test on TM2 tube heater +(D) water line.

Chad and I did a pressure test on TM2 tube Heater+(D) water line.I pressurized the D line with shop air from quick connectors(both ends) on service cap.chad applied bubble soap onto the D water block in SHC. The test started from 5psi,and increased 5psi each time to 40 psi. From 5 to 35 psi, no bubble has been found on water block. At 40 psi , bubble appeared from blind blank off seal , but not from soldering joints. Since the o-ring seal for the blank off is  vacuum seal , but not for pressurizing, It is understandable the seal could not hold 40 psi pressure air. No bubble had been found on the D water block soldering joints .See attachment pictures.

Attachment 1: 015.JPG
015.JPG
Attachment 2: 016.JPG
016.JPG
Attachment 3: 021.JPG
021.JPG
Attachment 4: 018.JPG
018.JPG
Attachment 5: 017.JPG
017.JPG
Attachment 6: 019.JPG
019.JPG
Attachment 7: 020.JPG
020.JPG
Attachment 8: 029.JPG
029.JPG
Attachment 9: 028.JPG
028.JPG
Attachment 10: 029.JPG
029.JPG
  591   Tuesday, February 04, 2014, 08:04 David WangSouth Hot-CellRepairTM2 Leak check TM2 tube heater (+) water line.

Chad and I leak checked TM2 tube heater(+) water line yesterday afternoon. The water line was difficult to pump down on base leak rate, but LD  base pressure was fine . The base pressure on leak detector was pumped to 0.0XE-4 torr quickly. The base leak rate only could be pumped  to  4.5 xE-8 atm.cc/sec after 1 hour waiting time. All vacuum connections to leak detector  in the target hall were leak checked and they were good. Chad checked helium flow in SHC. He sprayed helium twice on tube heater(+) water block soldering joints. I did not see any response on leak detector in TH.The base Leak rate and base pressure did not move up during the test.  See attachment pictures.

Attachment 1: IMG_0012.JPG
IMG_0012.JPG
Attachment 2: IMG_0013.JPG
IMG_0013.JPG
  590   Monday, February 03, 2014, 14:45 Travis CaveSpent Target VaultStandard Operation  Spent targets to mini storage and the F-308s to the Target Hall

Targets NiO#1(101), Nb#5(85), TaC#1(92), and ZrC#5(81) have been moved from the storage vault and placed in the mini storage. The F-308 flasks have also been moved in to the target hall as well. The attached are the current statuses of both vaults.

Attachment 1: Vault_Storage_February_3_2014.pdf
Vault_Storage_February_3_2014.pdf Vault_Storage_February_3_2014.pdf Vault_Storage_February_3_2014.pdf Vault_Storage_February_3_2014.pdf
Attachment 2: Mini_Vault_Storage_February_3_2014.pdf
Mini_Vault_Storage_February_3_2014.pdf Mini_Vault_Storage_February_3_2014.pdf Mini_Vault_Storage_February_3_2014.pdf Mini_Vault_Storage_February_3_2014.pdf
  589   Thursday, January 30, 2014, 13:46 Travis CaveConditioning StationStandard OperationTM2no targetmodule move

TM#2 has been moved from the conditioning station to the south hot cell.