2287
|
Monday, January 10, 2022, 12:38 |
David Wang | North Hot-Cell | Standard Operation | TM2 | | TM2 has been moved from ITW to NHC. |
Travis and Nadia moved TM2 from ITW to NHC this morning. The move is smooth and successful. |
2288
|
Tuesday, January 11, 2022, 11:50 |
David Wang | ITW | Maintenance | | | ITW Exit module 1 side sqaure panel O-ing seal replacement. |
Frank and I replaced ITW Exit module 1 side square service panel o-ring seal. Also, The target module pit top flange o-ring seal in ITW pit is replaced. |
2289
|
Tuesday, January 11, 2022, 11:51 |
David Wang | North Hot-Cell | Standard Operation | TM2 | | TM2 has been moved from NHC to SMP. |
TM2( no target ) has been moved from NHC to SMP. The moving is smooth and successful. |
2294
|
Wednesday, January 19, 2022, 13:26 |
David Wang | Crane | Standard Operation | | | Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02. |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.. He certified the use of these two frames. Inspection tags have been issued and attached to frames. He has inspection record on them. See attachments. |
Attachment 1: 2022-01-19_170.jpg
|
|
Attachment 2: 2022-01-19_173.jpg
|
|
Attachment 3: 2022-01-19_175.jpg
|
|
Attachment 4: 2022-01-19_176.jpg
|
|
2295
|
Wednesday, January 19, 2022, 13:36 |
David Wang | Crane | Standard Operation | | | Targe hall crane below hook attachment pins and plates annual inspection. |
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01. He certified the use of these pins and plates. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08. After inspection, The inspection tag was issued and attached to pin. Tom has an inspection record on this job. See attachments. |
Attachment 1: 2022-01-19_174.jpg
|
|
Attachment 2: 2022-01-19_172.jpg
|
|
2296
|
Thursday, January 20, 2022, 08:18 |
David Wang | North Hot-Cell | Standard Operation | TM4 | No target | TM4 was removed from NHC to S_W silo yesterday. |
TM4 was removed from NHC to S_W silo yesterday. The remove is smooth and successful. |
2298
|
Monday, January 24, 2022, 11:18 |
David Wang | ITE/ITW | Standard Operation | | | TH emergency exit hatch functional check |
TH emergency exit hatch which is located on TH west end roof is opened and closed for functional check. The hatch works fine. The limit switch on hatch is in position. No obstacle on hatch way to the roof. |
2299
|
Tuesday, January 25, 2022, 08:57 |
David Wang | ITE/ITW | Standard Operation | | | ITE/ITW have been cleaned with vacuum canister. |
ITE/ITW are cleaned with vacuum canister. HV cage inside and blue nylon insulators are wiped. Garbage inside the pits are cleaned out. |
2300
|
Tuesday, January 25, 2022, 12:49 |
David Wang | ITE/ITW | Standard Operation | | | Target station vacuum system visual inspection. |
Two shielding blocks above vacuum station at TH west end were opened for inspection. Checked ITH:MP1, MP2 lubricant color and level through sight gauge on pumps. They are still ok. Restored the shielding blocks. Checked ITM:MP1 by decay tank (Mirror checked sight gauge by north wall). Added lubricant to ITM:MP1 to middle level on sight gauge. |
2301
|
Wednesday, February 02, 2022, 11:05 |
David Wang | Crane | Standard Operation | | | Target hall overhand crane annual insepection. |
Tom Kauss finished target hall overhead crane annual inspection today. The crane works fine. He issued new inspection tag and e-logged the job. |
2302
|
Thursday, February 10, 2022, 11:45 |
David Wang | Spent Target Vault | Standard Operation | | UCx#33. | Spent target UCx #33 has been repacked with a new pail and lid in NHC. |
Spent target UCx #33 has been repacked with a new pail and lid in NHC. Old pail #255. New pail # 267. Location: Vault slot 1C. it is an investigation job for a possible leak pail in vault. |
2303
|
Thursday, February 10, 2022, 12:24 |
David Wang | ITW | Standard Operation | | | ITW HV test without mdoule. |
Carla did the test. and reported the result as following: HV testing of ITW is complete. It was pretty well behaved up to 59.5kV, and sat at 59kV for 30mins with no sparks (that EPICS caught). There was some strange behaviour of the current between 51kV and 53kV - it was jumping by 20uA or more - but there didn't seem to be any voltage response, and it went away after 53kV (though it returned on the way back down). The test was done in Feb 02. |
2304
|
Thursday, February 10, 2022, 12:42 |
David Wang | ITE | Standard Operation | | | ITE HV test woithout mdoule was done. |
Carla did the test. That is what she wrote in Feb 04th: "I am done with the HV testing at ITE - the results were the same as at ITW. It stayed at 59kV for 30 mins with no issues. Trying to go above 59.5kV is probably possible but a bit more risky. ITE also has a band, from 54-56kV, where the current jumps around like crazy". |
2307
|
Thursday, February 17, 2022, 13:24 |
David Wang | Spent Target Vault | Maintenance | | UCx #34 | Repackage of UCx #34in NHC. |
UCX34# in pail 258(Vault lot 7C) has been repacked today. It is an investigation to find a possible leak source of radioactive Iodine in vault. The new pail number is 268. It is back to vault 7c . I wrote down the information in log book. The job is smooth today. I retrieved UCx 34 old pail and liner to TH. The liner from UCx#34 only has 3000 counts. I bagged it. It could be used later. However, the pail has 500K counts contamination on bottom outside rim. It may accidently be slided out of plastic bag and touched the NHC table during the repackage. I bagged it and store it in silo area. When we do drum clean up, I will throw it in the drum. |
2308
|
Thursday, February 24, 2022, 13:23 |
David Wang | ITE/ITW | Maintenance | | | Polyurethane water cooling lines replacement in ITE and ITW. |
Polyurethane water cooling lines in ITE and ITW HV shroud are replaced. Both stations Ta, Tu, MSP, HS, Coil , EE in HV shroud are new lines. |
2310
|
Tuesday, March 01, 2022, 11:51 |
David Wang | Spent Target Vault | Maintenance | | | UCx #32 has been repacked in NHC. |
UCx 32# P2N target in vault slot 1B is repacked is morning for Ferran to take out his samples( in two small plastic containers) stored in pail last July when Chad did the spent target job. The job went well. Old pail # is 254# and new pail # is 233. It is put back to 1B in vault. |
2311
|
Wednesday, March 02, 2022, 10:51 |
David Wang | ITE/ITW | Standard Operation | | | Replaced old turbopump and 2A3M20 wire scanner are transferred to cyclotron tunnel. |
Replaced 9 old turbo pumps from ITE/ ITW and one 2A3M20 wire scanner from ITE are transferred to cyclotron tunnel for storage. It is TH RAD waste cleanup task in winter shut down. |
2317
|
Thursday, April 28, 2022, 08:16 |
David Wang | ITW | Standard Operation | TM2 | | Annual ITW water signal interlocks check . |
Annual ITW water signal interlocks check was done with TM2 in ITW. Water signal interlocks on all water circuits related to TM and 2A beam lines in ITW work fine. |
2325
|
Wednesday, May 25, 2022, 13:23 |
David Wang | ITE | Standard Operation | TM4 | | Annual ITE water signal interlocks. |
Annual ITE water signal interlocks check is done with Rob Shank. All ITE water signal interlocks work fine. |
2336
|
Wednesday, June 22, 2022, 09:03 |
David Wang | ITE | Standard Operation | TM4 | UCX37# P2N | Remotely removed TM2 from ITE to NHC |
TM2 with UCx#37 P2N target was removed from ITE to NHC yesterday morning. The move is good. |