ID Date Author Category Type Module Target/Number Subject Text Attachments
  768   Monday, October 20, 2014, 08:59 David WangConditioning StationDevelopmentTM3 Started TCS water system.I started TCS water system this morning
to check if the chillers work properly.
  
  767   Friday, October 17, 2014, 13:36 Anders MjosConditioning StationMaintenance  TCS:Chil staging not operationalNOTE: If cooling is required, the
compressors will have to be run manually.
Make sure to switch it off again when the
  
  766   Thursday, October 16, 2014, 15:40 Anders MjosConditioning StationMaintenance  Chiller unitNOTE: If there is a problem with
the chiller unit (ie Fault 1 or Fault 2),
a power cycle may reset the VFDs for the
 TCS_Cooling_System.pdf 
  765   Wednesday, October 15, 2014, 12:55 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moveTM#1 with no target has been moved from
the south hot cell to the south west silo.
  
  764   Tuesday, October 14, 2014, 17:19 Anders MjosConditioning StationStandard OperationTM3No targetHigh Voltage ConditioningWednesday, October 14, 2014
 The BIAS voltage was brought
up between 1:30pm and 5pm. Sparks tripped
 TCS_TM3.docx 
  763   Tuesday, October 14, 2014, 13:31 Travis CaveSouth Hot-CellStandard OperationTM1no targetElectrical checkElectrical check of TM#1 with no target
attached at the south hot cell see attached
PDF for details.
 TM1_elec_check_no_target.PDF 
  762   Tuesday, October 14, 2014, 12:19 David WangITWStandard OperationTM1 TM1 was disconnected in ITW.TM1 was disconnected in ITW this morning.
Heat shield circuit is purged.
  
  761   Tuesday, October 14, 2014, 11:52 Travis CaveSouth Hot-CellStandard OperationTM1ZrC#6Electrical checkTM#1 with ZrC#6 post beam electrical check
see attached pdf for results.
 TM1_ZrC6_postbeam.PDF 
  760   Tuesday, October 14, 2014, 11:51 Travis CaveSouth Hot-CellStandard OperationTM1ZrC#6module moveTM#1 with ZrC#6 has been moved from ITW
to the south hot cell.
  
  759   Friday, October 10, 2014, 10:47 David WangConditioning StationDevelopmentTM3 TM3 has been connected in CSTM3 has been connected in CS. All water
supplies are bypassed theTM3 on the top of
the service cap. TM3 TP2 was difficult to
  
  758   Wednesday, October 08, 2014, 09:39 Travis CaveConditioning StationStandard OperationTM3no targetmodule moveTM#3 has been moved from the North West
Silo to the conditioning station.
  
  757   Friday, September 26, 2014, 10:56 Travis CaveSpent Target VaultStandard Operation UC#10Spent target moveUC#10 has been moved from the south hot
cell to the spent target vault. It was placed
in Pail #119 and in slot 8B. For further
 Vault_Storage_September_26_2014.pdf 
  756   Wednesday, September 24, 2014, 15:16 David WangITEStandard OperationTM4Ta#44Reconnected TM4 in ITE.TM4 has been reconnected back to ITE. I
started all turbo pumps on ITE and TM4. The
ITE TP4s was extremely difficult to start.
  
  755   Wednesday, September 24, 2014, 15:03 David WangSouth Hot-CellStandard OperationTM4Ta#44Leak check on TM4 HS water line with new Ta#44 target. at SHCThis morning Chad and I leak checked TM4
HS line with new Ta#44 target installed.
I calibrated LD before the check. Before
  
  754   Wednesday, September 24, 2014, 10:41 Travis CaveITEStandard OperationTM4Ta#44module moveTM#4 with Ta#44 has been moved from the
south hot cell to the east target station.
  
  753   Tuesday, September 23, 2014, 13:31 Travis CaveSouth Hot-CellStandard OperationTM4UC#10, Ta#44Electrical checkElectrical checks of TM#4 with UC#10 post
beam and Ta#44 before beam see attached PDF
for details.
 TM4_UC10_postbeam_shc.PDFTM4_Ta44_elecchk_shc.PDF 
  752   Tuesday, September 23, 2014, 12:24 chad fisherSouth Hot-CellStandard OperationTM4Ta#44Ucx10 removed Ta#44 installedUcx#10 has been removed from TM4 and placed
in a pail with argon.
Ta#44 has been installed onto TM4
  
  751   Tuesday, September 23, 2014, 11:49 David WangITEStandard OperationTM4UCx #10TM4 has been disconnected in ITE.TM4 has been disconnected and moved to
SHC from ITE. ITE was vented with argon before
move.
  
  750   Tuesday, September 23, 2014, 10:50 Travis CaveSouth Hot-CellStandard OperationTM4UC#10module moveTM#4 with UC#10 has been moved from the
east target station to the south hot cell.
  
  749   Tuesday, September 16, 2014, 10:41 David WangITWStandard OperationTM1ZrC #45 Shielding blocks have been transferred from ITE to ITW.5 Shielding blocks have been transferred
from ITE to ITW. The ITW is configured to
take proton beam
  