561
|
Friday, November 29, 2013, 11:57 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Steerer short investegation |
|
|
560
|
Friday, November 29, 2013, 11:54 |
chad fisher | South Hot-Cell | Repair | TM3 | | Steerer short investegation | Using in cell camera and transit the suspect
line on the steerers was inspected as best
as possible. An existing photo of the complete |
  |
559
|
Wednesday, November 27, 2013, 15:24 |
Bevan Moss | South Hot-Cell | Maintenance | TM3 | | Wiring Harness Electrical Test | Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction |
|
558
|
Wednesday, November 27, 2013, 12:50 |
Bevan Moss | South Hot-Cell | Standard Operation | TM3 | | Ground devices wiring check | Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V |
|
557
|
Tuesday, November 26, 2013, 14:10 |
Travis Cave | Crane | Maintenance | | | Thermal relay replaced | The bad thermal motor protection relay
for the crane has been replaced with a new
unit. Crane was tested in pendant(local) |
|
556
|
Monday, November 25, 2013, 11:48 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the north east silo to the south hot cell. |
|
555
|
Friday, November 22, 2013, 10:29 |
Travis Cave | Spent Target Vault | Standard Operation | | NiO#2 | Spent target move | NiO#2 has been moved from the south hot
cell into spent target storage. It was placed
in pail 111 in slot 3C of the storage vault. |
|
554
|
Thursday, November 21, 2013, 12:12 |
Anders Mjos | South Hot-Cell | Standard Operation | TM3 | NiO#2 | End of beam target inspection - ANODE does not hold 250V | The target was inspected by Chad and Anders
in the Hot Cell. Electrical megger tests
were done during the assembly. It was found |
|
553
|
Wednesday, November 20, 2013, 13:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV testing of TM2 | HV testing without the cover continued
today. With the EINZEL lens at 30kV the target
module was able to achieve 58.7kV. At this |
 |
552
|
Wednesday, November 20, 2013, 09:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the south hot cell to the north east silo. |
|
551
|
Wednesday, November 20, 2013, 08:50 |
chad fisher | South Hot-Cell | Standard Operation | TM3 | NiO#2 | NiO#2 removed | NiO#2 has been removed from TM3 |
 |
550
|
Tuesday, November 19, 2013, 16:55 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV conditioning | HV conditioning of TM2 continued
today. At ~53.5kV the module started to spark
externally to the HV cover. This is the first |
   |
549
|
Tuesday, November 19, 2013, 14:24 |
David Wang | ITE | Repair | | | ITE TP3 | Hi
all, The old ITE TP3 pump is
moved out and the new pump is in |
|
548
|
Tuesday, November 19, 2013, 10:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | NiO#2 | module move | TM#3 with NiO#2 moved from ITE to the south
hot cell. |
|
547
|
Monday, November 18, 2013, 16:44 |
Bevan Moss | Conditioning Station | Standard Operation | | | Testing of cooling package | I have tested all of the compressors
for TCS. All are operational and cycled as
they should. |
|
546
|
Monday, November 18, 2013, 16:42 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Testing | The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this |
 |
545
|
Monday, November 18, 2013, 11:54 |
Bevan Moss | Conditioning Station | Repair | TM2 | | Fault on TCS Chill | This morning when I went to start
HV conditioning CP2 and CP3 both had faults
and the temperature of the water was ~27C. |
|
544
|
Friday, November 15, 2013, 16:48 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Testing | High voltage testing was started
on TM2 with no source tray today. The maximum
stable for 1 minute voltage reached was 47.5kV |
 |
543
|
Thursday, November 14, 2013, 08:08 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Blank off and jig removal | Firday, November 8 all water blocks (excluding
I and K) were blanked off and vacuum leak
checked. No responses were found. (First |
 |
542
|
Wednesday, November 13, 2013, 10:01 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 leak check at conditioning station | I leak checked TM2 at conditioning station
this morning. All air to vacuum seals on
the top of the module are good. All water |
|