  2108   Friday, June 19, 2020, 11:21 David WangITERepairTM4P2N test.ITE TP3 is replaced.ITE TP3 is replaced. ITE is under vacuum
again. All turbo pumps are started successfully.
Current draw on pumps are normal so far.
  
  2107   Thursday, June 18, 2020, 13:25 David WangITEStandard OperationTM4P2N test.Disconnect TM4 in ITE.TM4 has been disconnected in ITE. Vacuum
pumps and gauge are not disconnected yet.
  
  2106   Thursday, June 18, 2020, 13:22 David WangITWStandard OperationTM2C#1Remove of TM2 from ITE to SHC.Remotely remove TM2 from ITW to SHC. The
move is good.  Shielding plug is put
back to ITW. 
  
  2105   Thursday, June 18, 2020, 09:11 Travis CaveITWStandard OperationTM2Graphite #1Module move TM#2 with the graphite #1 target
has been moved from the south hot cell to
the west target station.
  
  2104   Wednesday, June 17, 2020, 09:53 David WangSouth Hot-CellStandard OperationTM2C#1C#1 target electrical check and leak check at SHC.Target to HS is 400 ohm. The rest check
is good. See attachment.
 C#1_target_electrical_and_leak_check.pdf 
  2103   Wednesday, June 17, 2020, 09:49 chad fisherSouth Hot-CellStandard OperationTM4C#1C#1 installedTarget C#1 has been installed on TM4 with
new high current fasteners torqued to 130in
lbs.
 C#1_Target.jpg 
  2102   Tuesday, June 16, 2020, 09:37 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move TM#2 with no target has been moved
from the south west silo to the south hot
cell.
  
  2101   Thursday, June 11, 2020, 12:36 David WangSafe Module ParkingRepairTM3 TM3 containment box and service tray field measurement. At 15cm distance: Containment box   
  2100   Thursday, June 11, 2020, 11:49 David WangITEMaintenance  ITW and ITE thermocouple status.     
  2099   Thursday, June 04, 2020, 10:51 David WangConditioning StationStandard Operation  TH floor mop up.Jason Sargeant mopped up TH floor this
morning. The mop head was checked after the
job. There are 1500 counts on it. He think
  
  2098   Thursday, June 04, 2020, 10:40 David WangConditioning StationMaintenance   Three manual valves are closed on TCS water system Three manual valves are closed on TCS water
system return line in experimental hall.
See attachments. It is for TCS TK2 water
 TCS_return_line_closed_valves_001.JPGTCS_return_line_closed_valves_002.JPG 
  2097   Monday, June 01, 2020, 12:46 David WangITEMaintenance  ITH:CM6 ,CM6S and ITM:CM3 calibration.Edi calibrated ITH:CM6, CM6S and ITM:CM3.
By the same time,  ITH:MP1 and MP2 
lubricate oil level are checked. Everything
  
  2096   Monday, June 01, 2020, 12:40 David WangCraneMaintenance  TH crane festoon cable maintenanceTom Kauss corrected the TH crane 
festoon cable loops. He lubricated festoon
cable wheels as well.    The maintenance
  
  2095   Friday, May 22, 2020, 13:26 David WangITWRepair  ITW water leak.A water leak was found on a fitting connecting
ITW dump return line pressure gauge on top
of exit module. TM tank flange, o-ring slot
 itw_water_leak_001.JPGitw_water_leak_005.JPGitw_water_leak_009.JPGitw_water_leak_013.JPG 
  2094   Wednesday, May 20, 2020, 13:30 David WangSafe Module ParkingMaintenance  Silo area radio active waste clean up. Sorted and packed one 55 gallon drum with
low contamination and active stuffs which
are placed around silo area in the past.
  
  2093   Wednesday, May 20, 2020, 13:19 David WangITEMaintenance  Restart of ITE turbo pumps. PLC6 drop out in weekend caused the ITH
MP1 and MP1s stopped. ITE turbo pumps were
running still after that. Without back up
  
  2092   Wednesday, May 20, 2020, 13:08 David WangCoolingStandard Operation  Start of HALCW sysytemHigh  active water pump is started.
The system resistance is recovering now.
Everything works fine so far. Check ITW and
  
  2091   Friday, March 27, 2020, 08:45 Matthew GareauNorth Hot-CellMaintenance  Issues with the manipulators This is a link to all of the issues
with the NHC manipulators that I know of

  
  2090   Thursday, March 19, 2020, 15:48 Anders MjosConditioning StationMaintenance  Filter replacement in water system March 5thFilters were replaced by Curtis von Cube
on March 5th. See work permit for details
I2020-03-05-5
  
  2089   Wednesday, March 18, 2020, 10:40 David WangITEDevelopmentTM4 TM4 P2N target connection checklist.TM4 has been connected in ITE. See checklist.  P2N_TM4_connection_checklist.pdf 