1588
|
Monday, July 31, 2017, 09:44 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move | TM#3 has been moved back to the NE
silo from the conditioning station. |
|
1587
|
Tuesday, July 18, 2017, 16:53 |
Anders Mjos | Conditioning Station | Development | TM3 | No target | Conditioning TM3 | Conditioning continues today with resistors
removed from the HV cable
Tuesday, July 18, 2017, 16:53: BIAS |
|
1586
|
Tuesday, July 18, 2017, 15:04 |
Travis Cave | Crane | Maintenance | | | Failure of the ISAC TH Crane Rotate. | Earlier in the day it was noted that
the rotate function of the crane had creased
operation. After David has finished the block |
|
1585
|
Monday, July 17, 2017, 17:50 |
Aurelia Laxdal | Conditioning Station | Development | TM3 | No target | Conditioning TM3 |
|
|
1584
|
Monday, July 17, 2017, 16:28 |
Anders Mjos | Conditioning Station | Development | TM3 | No target | Conditioning TM3 | 50 kV stable with less than 1 spark/h during
the weekend by RIB obs.
Today 57 kV reached, but observed |
|
1583
|
Thursday, July 13, 2017, 10:53 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move | TM#3 has been moved from the north
east silo to the conditioning station. |
|
1582
|
Wednesday, July 12, 2017, 11:05 |
Anders Mjos | Conditioning Station | Maintenance | | | Testing of new high voltage cable | The target hall has been locked-out as
per Document-70039.
Forced IG1, IG1S and IG2 to switch |
|
1581
|
Tuesday, July 11, 2017, 10:20 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#52 | Module move | TM#4 with Ta#52 has been moved from
the conditioning station to the east target
station. |
|
1580
|
Monday, July 10, 2017, 10:19 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system | Prepare for TM4 move tomorrow morning. |
|
1579
|
Monday, July 10, 2017, 09:09 |
Dan McDonald | North Hot-Cell | Repair | | | manipulator cart repair | A hydraulic leak was found on the
manipulator install and repair cart,
upon further investigation the cause was |
|
1578
|
Thursday, July 06, 2017, 14:23 |
Isaac Earle | North Hot-Cell | Repair | | | Slave side Z motion tape snapped on NHC right side manipulator | The NHC right side manipulator was evaluated
today to check if operation was normal through
all ranges of motion. The manipulator |
|
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
|
1576
|
Wednesday, July 05, 2017, 11:18 |
Anders Mjos | Conditioning Station | Maintenance | TM4 | Ta#52 | Changed electrical configuration to cathode bias | John Chow configured TCS to cathode
bias mode (IRH1538). The anode P/S is in
positive mode. |
|
1575
|
Thursday, June 29, 2017, 14:42 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#20 | Spent Target Move | The spent UC#20 has been moved from
the south hot cell to the spent target vault.
It was placed in pail #150 and spot 1B in |
|
1574
|
Thursday, June 29, 2017, 11:55 |
David Wang | Conditioning Station | Repair | | | TCS HV cable and feed through installation | John Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269 |
|
1573
|
Thursday, June 29, 2017, 11:12 |
Anders Mjos | South Hot-Cell | Standard Operation | TM4 | UC#20 | Post Irradiation Examination (PIE) | The target was inspected by Chad and Anders.
Photos are available on DocuShare.
It was noticed that the target tube heater |
|
1572
|
Wednesday, June 28, 2017, 16:43 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | Ta#52 | Conditioning Ta#52 | NEW HV cable for BIAS installed earlier
this week.
Wednesday, June 28, 2017, 16:42: |
|
1571
|
Wednesday, June 28, 2017, 10:00 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#52 | TM2 has been connected at TCS | I started TCS water system. |
|
1570
|
Wednesday, June 28, 2017, 09:14 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#52 | Electrical Check | Results of electrical check of TM#4 with
Ta#52 at the south hot cell and the conditioning
station under vacuum. |
|
1569
|
Tuesday, June 27, 2017, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected at TCS | Turbo -pumps are started . The vacuum looks
good so far. |
|