1333
|
Wednesday, August 24, 2016, 10:45 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 vacuum system has been connected at TCS | Start of roughing now. |
|
1332
|
Wednesday, August 24, 2016, 10:44 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. | Chad and I leak checked Tm2 Hs line with
new target installed. Base LR 0.0Xe-9 atm.cc/sec.
No leak has been found. This line will be |
|
1331
|
Wednesday, August 24, 2016, 10:41 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was disconnected in ITW yesterday. | TM2 was disconnected in ITW yesterday and
moved to SHC. |
|
1330
|
Wednesday, August 24, 2016, 09:19 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom Clean -up paint prep | Remaining items from anteroom have been
bagged and removed (save the boot boxes,
1 garbage can and 1 coverall garbage can). |
|
1329
|
Wednesday, August 24, 2016, 09:17 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | | Ta#49 | Ta#49 has been installed on TM2 and tested.
All high current fasteners torqued to 130
in lbs. |
|
1328
|
Tuesday, August 23, 2016, 13:31 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#33 | SiC#33 Removed | SiC#33 has been removed from TM2. |
|
1327
|
Tuesday, August 23, 2016, 10:39 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | SiC#33 | module moved | TM#3 with SiC#33 has been moved from the
west station to the south hot cell. |
|
1326
|
Tuesday, August 23, 2016, 08:05 |
chad fisher | South Hot-Cell | Maintenance | | | Post Hot Cell Entry Clean-up | Plastic has been removed from the floor
and any known active items in the hot cell
moved to the south east corner in an attempt |
|
1325
|
Thursday, August 18, 2016, 14:19 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 is now back in the the north east
silo. |
|
1324
|
Thursday, August 18, 2016, 13:57 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator maitenance | South hot cell was entered to check to
replace cable if needed. Wrist cable showed
no signs of fraying or broken strands. |
|
1323
|
Thursday, August 18, 2016, 10:35 |
Anders Mjos | Conditioning Station | Repair | | | VFD21 OL1 fault on Chiller |
|
|
1322
|
Tuesday, August 16, 2016, 12:35 |
David Wang | Conditioning Station | Repair | TM3 | | CS vacuum pumps have been stopped | The TCS is venting now. The TM3 blue insulator
replacement job will be started soon. |
|
1321
|
Tuesday, August 16, 2016, 11:27 |
chad fisher | South Hot-Cell | Maintenance | | | South Cell Field Readings | Field readings have been taken at the south
hot cell in preparation for entry into the
cell to fix manipulator. |
|
1320
|
Monday, August 15, 2016, 10:15 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) | Weekly update target hall schedule. Everything
on schedule are finished on time.
See attachment. |
|
1319
|
Monday, August 15, 2016, 10:08 |
David Wang | ITE | Standard Operation | TM4 | UC#17 | 5 Shielding blocks have been transferred from ITW to ITE. | Dan and I transferred 5 shielding blocks
from ITW to ITE. The ITE is configured to
take proton beam. |
|
1318
|
Friday, August 12, 2016, 10:59 |
Anders Mjos | Conditioning Station | Development | TM3 | | HV Test with Service Chase Panel removed | Water cooling is performed manually with
CP1. RGA is ON since yesterday. EE is not
connected and in conditioning mode. |
|
1317
|
Friday, August 12, 2016, 09:58 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator Maitenance | Disassembled the master side of the right
manipulator this morning to check the wrist
cable. The cable on the master side shows |
|
1316
|
Thursday, August 11, 2016, 10:37 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 service tray cover plate ITA2108 has been removed. | Requested by Aurelia, and approved by Friedhelm,
TM3 service tray cover plate ITA2108 has
been remove out of the module. The plated |
|
1315
|
Wednesday, August 10, 2016, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Ventilation Test Results | Testing was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve |
|
1314
|
Wednesday, August 10, 2016, 12:18 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom clearing | Black "radio active" materials
cabinet has been emptied, items bagged and
removed from the anteroom. Cabinet itself |
|