1048
|
Wednesday, August 26, 2015, 09:54 |
Anders Mjos | Conditioning Station | Maintenance | | | Topped up water in TCS:TK2 | Filled to 24.9 in |
|
1047
|
Wednesday, August 26, 2015, 09:20 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | ZrC #7 | Electrical Check | Electrical check of TM#2 with ZrC #7 installed |
|
1046
|
Tuesday, August 25, 2015, 13:54 |
Grant Minor | South Hot-Cell | Repair | TM2 | ZrC#7 | TM2 - Electrical / HV Short Repair and Current Status (ZrC target) | Hello all,
TM2's first performance in the Conditioning |
|
1045
|
Friday, August 21, 2015, 11:38 |
Anders Mjos | South Hot-Cell | Repair | TM2 | FEBIAD Test Target | Steerer wires found to be touching the gas lines | Yesterday TM2 was inspected in the SHC.
Spark marks were found both on the steerer
wires and on the ANODE wire. The steerer |
|
1044
|
Thursday, August 20, 2015, 13:48 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - Sep 08 2015 | Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to |
|
1043
|
Thursday, August 20, 2015, 11:00 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | Dummy Target | Electrical Check | TM#2 electrical check at the conditioning
station. All pumps were off but the module
was not vented. |
|
1042
|
Thursday, August 20, 2015, 10:15 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Dummy Target | Module moved | TM#2 is now in the south hot cell. |
|
1041
|
Thursday, August 20, 2015, 09:38 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 was disconnected at CS | TM2 was disconnected at CS. Travis and
I did electrical check before the venting.
After,The module was vented and moved to |
|
1040
|
Wednesday, August 19, 2015, 14:52 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 at CS | During the TM2 HV test at CS, It failed.
In order to confirm there is no any water
leak inside the module after the heaters |
|
1039
|
Monday, August 17, 2015, 10:44 |
Anders Mjos | Conditioning Station | Development | TM2 | LP-FEBIAD Test Target (empty) | Conditioning TM2 Source Tray with FEBIAD test target | TGHT, TBHT, ANODE and COIL power tested
(some amps/volts)
Monday, August 17, 2015, 10:43: BIAS/EL/EE |
|
1038
|
Friday, August 14, 2015, 10:00 |
David Wang | Conditioning Station | Repair | TM2 | | Started CS water package for TM2 | I finished the rest TM2 connections to
CS, and started CS cooling package. Everything
works fine so far. |
|
1037
|
Thursday, August 13, 2015, 17:17 |
David Wang | Conditioning Station | Repair | TM2 | Dummy target | TM2 at CS | TM2 has been moved to CS. All turbo-pumps
have been started. The pumping down is good
so far. I connected the leak detector |
|
1036
|
Thursday, August 13, 2015, 14:36 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | Dummy Target | Module moved | TM#2 with the dummy target has been moved
to the conditioning station. |
|
1035
|
Thursday, August 13, 2015, 13:46 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | As previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to |
|
1034
|
Thursday, August 13, 2015, 11:34 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Dummy Target | Electrical Check | Electrical check of TM2 without target
after that widget has installed, electrical
check with the shunts on, electrical check |
|
1033
|
Thursday, August 13, 2015, 09:17 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 status | Tuesday, August 11, insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested; |
|
1032
|
Monday, August 10, 2015, 14:07 |
Isaac Earle | South Hot-Cell | Repair | TM2 | | TM2 Containment Box Removed | The containment box was taken off TM2 in
preparation for installation of a new coil
line isolator. |
|
1031
|
Friday, August 07, 2015, 10:01 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - August 19 2015 | Weekly update target hall schedule and
activities. See attachment 1,2
Update and extend Target Hall schedule |
|
1030
|
Thursday, August 06, 2015, 11:40 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module moved | TM#2 is now in the south hot cell |
|
1029
|
Thursday, August 06, 2015, 10:26 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target Measurments and Assays | All targets but one ( SiC#31 went in last
week) have been measured or assayed. See
attached PDF for the details. |
|