  RH-ISAC, Page 87 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject Text Attachments
  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2 I finished the rest TM2 connections to
CS, and started CS cooling package. Everything
works fine so far.
  
  1037   Thursday, August 13, 2015, 17:17 David WangConditioning StationRepairTM2Dummy targetTM2 at CSTM2 has been moved to CS. All turbo-pumps
have been started. The pumping down is good
so far.  I connected the leak detector
  
  1036   Thursday, August 13, 2015, 14:36 Travis CaveConditioning StationStandard OperationTM2Dummy TargetModule movedTM#2 with the dummy target has been moved
to the conditioning station.
  
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 StatusAs previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to
  
  1034   Thursday, August 13, 2015, 11:34 Travis CaveSouth Hot-CellStandard OperationTM2Dummy TargetElectrical CheckElectrical check of TM2 without target
after that widget has installed, electrical
check with the shunts on, electrical check
 TM2_elechknotgtafterwidget.PDFTM2_elechknotgtshunt.PDFTM2_elecchkdummytgt.PDF 
  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 statusTuesday, August 11,  insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested;
 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg 
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box RemovedThe containment box was taken off TM2 in
preparation for installation of a new coil
line isolator.
  
  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015Weekly update target hall schedule and
activities. See attachment 1,2
Update and extend Target Hall schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1030   Thursday, August 06, 2015, 11:40 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 is now in the south hot cell   
  1029   Thursday, August 06, 2015, 10:26 Travis CaveSpent Target VaultStandard Operation  Spent Target Measurments and AssaysAll targets but one ( SiC#31 went in last
week) have been measured or assayed. See
attached PDF for the details.
 Vault_Storage_August_6_2015.pdf 
  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Weekly update of Target Hall schedule after
so many jobs have been finished in this week. 
See attachment 1, 2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1027   Thursday, July 30, 2015, 14:05 Travis CaveSpent Target VaultStandard Operation SiC#31Spent target movedSiC#31 has been moved to the spent target
vault. It is in pail #127 and placed in spot
3C of the vault is was 489mSv/hr when removed
 Vault_Storage_July_30_2015.pdf 
  1026   Wednesday, July 29, 2015, 10:14 David WangITEStandard OperationTM4 TM4 has been connected in ITEDan and I connected TM4 in ITE. We checked
all water signals on ITE cooling circuits.
Everything is good.
  
  1025   Wednesday, July 29, 2015, 08:59 Travis CaveITEStandard OperationTM4UC#13Module movedTM#4 with UC#13 has been moved from the
conditioning station to the east target station.
  
  1024   Wednesday, July 29, 2015, 06:24 David WangConditioning StationStandard OperationTM4UCx 13Stopped the CS and TM4 pumps and vent with argon.Dan and I stopped the CS and TM4 pumps.
We are venting the CS with argon for UCX13
target.
  
  1023   Tuesday, July 28, 2015, 14:40 chad fisherSouth Hot-CellStandard OperationTM4SiC#31 UCx#13SiC#31 removed UCx#13 installedSiC#31 has been removed from TM4 and UCx#13
installed. UCx#13 connection to the 9 pin
connector was VERY VERY tight to the tube
 20150727_115314.jpg 
  1022   Tuesday, July 28, 2015, 14:36 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 AutopsyExtraction electrode was removed from SiC#31
and target inspected.
Pictures of findings can be found
  
  1021   Tuesday, July 28, 2015, 14:31 Travis CaveConditioning StationStandard OperationTM4UC#13Electrical CheckTM#4 with UC#13 electrical check at the
conditioning station under vacuum. See attached
PDF.
 TM4UC13IGLISelecchkCS.PDF 
  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replacedTony and I replaced the ITE TP4 turbo pump
today. The pumping time on controller has
been reset to 0. The replaced broken 
  
  1019   Tuesday, July 28, 2015, 10:12 David WangConditioning StationStandard OperationTM4UCx 13Helium pressure test on TM4 HS line at CSI did the helium pressure test on TM4 HS
line at CS. Applied 70 psi helium  2
minutes. base leak rate0.0x E-9 atm.cc/sec. 
  