Entry  Wednesday, December 03, 2014, 10:16, Isaac Earle, 100KW Beam Dump, Development, Installation of Lower Lead Block and Beam Dump Insert 
On November 28th the lower lead shield was installed with 3/8" shimming at the front end, and 11/32" shimming at the rear end.  The south
and east faces were aligned as flush as possible with the lower center block.  The beam dump insert was then placed on the rails in the lower lead
shield.
Entry  Wednesday, November 26, 2014, 17:50, Isaac Earle, 100KW Beam Dump, Development, Installation of Lower Center Block (TSH0461) Beam_Dump_Lower_Center_Block_Alignment_-_Nov_25_2014_(from_Darren_Blom).txtIMG_1110.JPGIMG_1125.JPGIMG_4297.JPGIMG_4303.JPG
Painting and relabeling of the modified lower center block (TSH0461) was completed on Monday Nov 24.  The
height of the modified block was measured at the four corners using a tape measure and found to be approximately 533mm at all corners.
The block was lowered to the E-Hall and aligned on Tuesday Nov 25.   No cantilever lift was required because the catwalk above the hatch had
Entry  Tuesday, November 03, 2015, 13:15, Isaac Earle, 100KW Beam Dump, Development, Initial tests of beam dump water system controls 
During the maintenance period today the E-Hall tunnel was accessed to begin controls tests on the beam dump water system and initial fill of the system.
 This work was done by Bill Richert and Dave Morris while I observed.  Before work began I verified that pressure relief valves were installed
as per the P&ID (TEL5104 Rev A) - they have been installed but the exhaust ports from the valves have not yet been routed to the active drain.  They
Entry  Thursday, November 28, 2024, 09:04, Adam Newsome, Hot Cell 1, Repair, Hot Cell turntables not rotating, access hatch not moving 
It was reported that the hot cell turntables would not rotate and the access hatch could not be operated. The turntables' elevation motion was working
normally, and other cell functions were working. 
Upon investigation, after going online with the PLC and checking the interlocks for the turntable, it was determined that motion was being prevented
Entry  Wednesday, September 15, 2021, 15:10, Adam Newsome, T-Hall Crane, Maintenance, Hoist Broken Fault (actually: cable wrap issue) 
A fault occurred which presented as "114. Main Hoist Cable Broken (3200PX)". This occurred when a SEG block was suspended approximately 1 m
off the ground.
Upon inspection, it was determined that the cable was in fact not broken, but wrapped around itself. There are no guides, and it is possible for
Entry  Thursday, December 12, 2024, 16:20, Aaron Tam, Hot Cell 1, Development, Extraction Electrode Banana Plug (Show and Tell) 6x
 December 12, 2024 - Chad Fisher, Albert Kong, Aaron Tam, Austin Hagen
Tests:
Loose piece connection and removal 
Entry  Wednesday, May 06, 2015, 14:19, Isaac Earle, 100KW Beam Dump, Development, EHDT Beam Pipe Section Installed IMG_4922.JPGIMG_4924.JPGIMG_4925.JPG
- On May 4th the EHDT beam pipe section was installed by Mike Vogel of Beamlines Group
- A new Helicoflex seal was used (provided by Vacuum Group)
- 4" RH Clamp was installed by Isaac Earle.  Clamp became stiff in early travel, was backed off, then fully tighetend down to stop-ring
Entry  Monday, June 15, 2015, 17:08, Isaac Earle, 100KW Beam Dump, Development, E-Dump Shielding Installation 
- The hoist rings were removed from the upper lead shield
- Two standard lock-blocks were installed over the E-Linac beam dump according to TSH0372
- 5/8" of shims were required on the north end of both blocks to make them level.  Aluminum shims were used (1/2" + 1/8")
Entry  Tuesday, September 10, 2024, 12:52, Adam Newsome, T-Hall Crane, Standard Operation, Drive not ready faults observed on power-up 
Upon powering on the crane today and attempting to use the main hoist, the following faults were present:
1. Main Hoist East Drum North Motor Drive Fault (700VFD)
2. Main Hoist West Drum South Motor Drive Fault (900VFD)
Entry  Friday, November 21, 2014, 13:37, Isaac Earle, 100KW Beam Dump, Development, Destructive Testing of 1" MDC Ceramic Breaks Ceramic_Water_Break_Test_#1.docxCeramic_Water_Break_Test_#2.docxTest_#1_Broken_Sample.JPGTest_#2_Broken_Sample.JPG
Testing was performed on the ceramic water breaks to be used on the beam dump water hose assemblies.  The ceramic breaks are a custom MDC product
with the following description:  3kV ceramic break, 1" OD tube 0.083" wall thickness, 2" length, 304SS tube stub each end, 250psi water
rating (see TRIUMF PO#  TR199315).
Entry  Wednesday, November 19, 2014, 13:49, Isaac Earle, 100KW Beam Dump, Development, Decision on Modifications to Lower Center Block (TSH0225) 
I received a call today from Jim Adamson at Kaltech regarding modifications to shielding block TSH0225.
They had finished removing 19mm from the bottom of the block, as well as removing 10mm of material from the side plates (TSH0246).  He was
wondering whether it was also necessary to remove material from the back plate (TSH0253) and weld the back plate to the 6" plate (TSH0252).  I
Entry  Friday, January 13, 2023, 13:57, Adam Newsome, T-Hall Crane, Repair, Crane light (west) not working 
It was observed today that the crane's west light was not functioning. 
Entry  Tuesday, March 21, 2023, 10:47, Adam Newsome, Hot Cell 1, Repair, Circuit breaker replacement - telemanipulators 
There was an issue with a 20 A circuit breaker used to control motor assist functions for the telemanipulators (specifically, the rightmost CB in the
panel for the right (East) manipulator set). This circuit breaker was moved to the panel for the left (West) manipulator set in the rightmost position,
and then subsequently replaced with a new one, which is functioning correctly. It is suspected that the former CB which was not working was calibrated
Entry  Thursday, September 16, 2021, 09:37, Adam Newsome, T-Hall Crane, Maintenance, Bridge Encoder Homing PXL_20210916_161245978.jpgPXL_20210916_161205277.jpg
The bridge motion was slowed due to encoder homing issue. It is likely that the problem which occurred yesterday caused an velocity fault (mismatch between
encoder speed and commanded speed), which unlatches the homing status for the bridge motion axis.
When the bridge was in the southmost position (bumper pressed against wall), the position readback was: 0.353 m, encoder count = 5164003.
Entry  Tuesday, June 02, 2015, 16:42, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Water Block RH Test & Installation BD_Water_Block_RH_Test_Procedure_-_June_2_2015.docx
Beam dump waterblocks #1 (BD Inlet) and #3 (Upper Pb Inlet) were removed as per the attached procedure
on June 1-2.  The following was noted:
- The RH pole tool (TRH1244) and water tool wrench (TRH1243) fit easily over all four water block
Entry  Monday, June 08, 2015, 15:15, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Vacuum Leak BD_Flanges_and_Clamp_Jaws_Dimension_Check_-_Keith_Ng_-_June_5_2015.pdf
- On Thurdsay June 4th the EHDT beamline section was vented by Vacuum Group so that they could install a new pump
- After pumping down again a leak was found at the BD front flange seal around the top of the seal
- The RH clamp and Helicoflex seal were removed and an o-ring seal was installed with a band clamp
Entry  Friday, June 12, 2015, 10:16, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Vac Seal Vent & Test 
- Vacuum has been pumping steadily on the EHDT section since June 8, reaching 3.2E-8 Torr at 8am today (June 12)
- Leak check performed this morning by Anthony Ip: no leaks
- Vacuum vented and re-pumped, leak check repeated: no leaks
Entry  Thursday, May 28, 2015, 16:08, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Vac Seal RH Test & Installation BD_Vac_Flange_RH_Test_Procedure_-_June_2_2015.docx
The following work was performed on May 27 & 28, 2015:
- The beam dump 10kW Remote Handling setup was arranged as shown in the attached procedure
- The EHDT split ring clamp was found to be installed too far downstream and the pole tool could not be installed properly;  the position
Entry  Monday, June 08, 2015, 15:23, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Seal Re-Install 
 On Monday June 8 the following work was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented
- Band clamp and o-ring seal removed
Entry  Friday, December 19, 2014, 14:05, Isaac Earle, 100KW Beam Dump, Development, Beam Dump & Lead Shielding Design Documentation Cooled_Lead_Shielding_Scanned_Design_Notes_(Isaac_Earle).pdf
 As there likely won't be an opportunity to properly document the design of the beam dump insert and cooled lead shielding in design notes, a list
of design reviews, released on Docushare is provided below.  These provide a reasonable overview of the design process for each item.  In addition
the attached PDF of scanned notes provides detailed information on the lead shielding design.  Further notes, ANSYS documents, meeting minutes, concept