40
|
Thursday, January 20, 2022, 13:38 |
Carla Babcock | | | Testing of spare FUG bias supply | Tomislav and John Chow tested the spare
bias supply located in the rack of the electrical
services room. This is a FUG HCN 1400 M-60000, |
|
|
41
|
Thursday, April 07, 2022, 12:00 |
Aaron Schmidt | Under Process | | Ar Glove box issue & LaC removal. | Thursday, April 07, 2022, 11:55:
It was noticed on Wednesday that
the glove box was not regulating pressure |
|
|
42
|
Thursday, April 07, 2022, 12:21 |
Aaron Schmidt | Fixed | | Ar glove box roughing pump. | Thursday, April 07, 2022, 12:00: While
preparing to remove LaC, the roughing pump
(1) stopped operating. It didn't appear to |
|
|
43
|
Tuesday, July 12, 2022, 11:08 |
Aaron Schmidt | | | Q2 - 2022 Ball Mill Calibration & Inspection | Fritsch
Pulverisette 5 Ball Mill status:
|
|
|
44
|
Friday, December 16, 2022, 07:36 |
Aaron Schmidt | | | Q4 - 2022 Ball Mill Calibration & Inspection | Fritsch Pulverisette
5 Ball Mill status: |
|
|
45
|
Thursday, February 02, 2023, 10:30 |
Aaron Schmidt | | | Eyewash & Shower Station OK | Thursday, February 02, 2023, 10:14:
Cold Lab Eyewash & shower station ran.
Ok. |
|
|
47
|
Tuesday, June 20, 2023, 15:11 |
Darwin Ortiz Rosales | Fixed | | Inspection ISAC 1 B1 L06 Glovebox | On Monday June 19th, the Glove box was
inspected. Gas lines, solenoids, pump,
argon usage, state of gloves and gas levels |
|
|
48
|
Friday, June 30, 2023, 12:21 |
Aaron Schmidt | | | Q2 - 2023 Ball Mill Calibration & Inspection | Fritsch |
|
|
49
|
Tuesday, August 01, 2023, 12:31 |
Darwin Ortiz Rosales | | | Evap1 and Evap2 Inspection and Maintenance | Evap1: Cleaned and checked seals.
Oil level could not be clearly determined,
but are consulting with pump group to check. |
|
|
50
|
Thursday, November 30, 2023, 10:03 |
Aaron Schmidt | Fixed | | Ar Glove box - Blower / solenoid fix | On November 10th / 11th a site wide
power outage occured. Once power was restored,
the Ar glove box had intermittent issues |
|
|
51
|
Tuesday, December 12, 2023, 13:12 |
Aaron Schmidt | | | Q4 - 2023 Ball Mill Calibration & Inspection | Fritsch |
|
|
52
|
Friday, January 19, 2024, 10:18 |
Darwin Ortiz Rosales | Fixed | | Inspection of Glovebox inside B1 L06 (hotlab) | Friday, January 19, 2024, 10:10
This is a belated entry. The
inspection was performed on December 19, |
|
|
53
|
Friday, January 19, 2024, 10:20 |
Darwin Ortiz Rosales | Fixed | | Glovebox regeneration (B1 L06, Hotlab) | Friday, January 19, 2024, 10:19
This is a belated entry. The
regeneration was performed successfully on |
|
|
54
|
Friday, February 09, 2024, 11:01 |
Aaron Schmidt | | | Laser cutter inspection | Friday, February 09, 2024, 11:01:
Epilog laser cutter operates. OK |
|
|
55
|
Tuesday, March 12, 2024, 15:21 |
Darwin Ortiz Rosales | Fixed | | Glovebox regeneration and O2 sensor replacement(B1 L06, Hotlab) | Tuesday, March 12, 2024, 15:21
Hotlab ISAC1 B1
Normal
0
|
|
|
56
|
Wednesday, March 27, 2024, 13:42 |
Keyur Chauhan | | | Actinide Mass Balance Calibration ISAC-I B1 Hot Lab | ISAC-1
B1 Hot Lab actinide mass balance calibration |
|
|
57
|
Monday, April 15, 2024, 10:52 |
Aaron Schmidt | Fixed | | Ar Glove box RP swapped. | Monday, April 15, 2024, 10:50: The
old IDP15 RP was not pumping the antechamber
down properly. An exchange IDP15 pump is |
|
|
58
|
Thursday, June 20, 2024, 13:33 |
Darwin Ortiz Rosales | Fixed | | Glovebox inspection ISAC1 B1 L06 | Thursday, June 20, 2024, 13:28
All lines, pump, blower, were |
|
|
59
|
Thursday, July 11, 2024, 13:40 |
Aaron Schmidt | | | Q2 - 2024 Ball Mill Calibration & Inspection | Fritsch Pulverisette
5 Ball Mill status: |
|
|
60
|
Thursday, August 01, 2024, 15:01 |
Darwin Ortiz Rosales | | | EVAP1 and EVAP2 Inspection and Maintenance | Thursday, August 01, 2024, 14:56
EVAP1: Checked seal and no
visible deterioration was observed. |
|