ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
156
|
Tuesday, September 23, 2014, 15:02 |
Laura Lambert | Empty | 40282-5 | TARGET BOAT | In progress | Sintering Ta target boat with TaC coating | Tuesday, September 23, 2014, 15:00
A new target boat [new design with no end caps] was sprayed with TaC coating and let dry.
The target boat is wrapped with 3-layers of Ta-heat shield.
The boat was installed in EVAP2, chamber is currently being pumped down.
|
160
|
Thursday, October 02, 2014, 11:52 |
Laura Lambert | Empty | 40282-5 | LP-SIS | In progress | Sintering TaC coating container for UCx#11 | Thursday, October 02, 2014, 11:51
Target container sprayed with TaC, currently drying in fume hood
Monday, October 06, 2014, 12:11
Target container & back block is wrapped with 3 layers of Ta-heat shield. The chamber has been pumped down over the weekend.
Pressure currently at 2.23e-7 Torr.
HS water valves open; no leaks detected.
TGHT will be ramped up to 580A at 0.2A/min
TBHT will be ramped up to 230A at 0.2A/min.
|
163
|
Wednesday, October 08, 2014, 11:51 |
Laura Lambert | Empty | 40282-5 | LP-SIS | Done | Sintering TaC coating container for UCx#11 (temp measured with OMEGA 2IR) |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, October 02, 2014, 11:51
Target container sprayed with TaC, currently drying in fume hood
Monday, October 06, 2014, 12:11
Target container & back block is wrapped with 3 layers of Ta-heat shield. The chamber has been pumped down over the weekend.
Pressure currently at 2.23e-7 Torr.
HS water valves open; no leaks detected.
TGHT will be ramped up to 580A at 0.2A/min
TBHT will be ramped up to 230A at 0.2A/min.
|
Monday, October 06, 2014, 12:16
Stepped up both TGHT/TBHT to 35A.
Tuesday, October 07, 2014, 12:54
TBHT reached to 230A/3.7V and TGHT is still ramping up, currently at 303A/4.5V. Temp measured with Omega-IR2 = 1165C with e'=0.85
Pressure @ 5.2e-7 Torr.
Increase ramping rate to 2A/min.
Tuesday, October 07, 2014, 16:21
TGHT is now at 580A and TGHT at 230A.
Temperature is measured with OMEGA-IR2, MIKRON, and analog pyrometer - All the measurements are agreed at 1700C (without the tantalum emissivity correction of 250C)
The OMEGA-IR2 slope has changed to 0.97 for the correction - The real temperature reading from the display is showing 1935C.
Now... attempting to low TBHT to see any temperature change.
Tuesday, October 07, 2014, 17:01
TGHT @ 580A.
TBHT = 180C, Temp = 1925C
TBHT = 130C, Temp = 1920C
Not much of change in the temperature on the target tube...
Tuesday, October 07, 2014, 17:07
Attempting to increase the temperature to 2000C
TGHT = 600A, Temp = 1955C
TGHT = 620A, Temp = 2000C
Target will continue heating at this temperature overnight... Will continue to monitor.
Tuesday, October 07, 2014, 20:59
After almost 4 hours of heating at 620A on TGHT, the temperature has dropped to 1980C.
Pressure is coming down to 1.17e-6 Torr.
Increased TGHT to 630A to maintain temp @ 2000C
|
Wednesday, October 08, 2014, 11:46
Temperature readout from omega-IR2C = 2054C
TGHT = 11.14V, 628.0A
TBHT = 2.01V, 129.8A
IGP1 = 8.2e-7Torr
Initiating auto-cool for TGHT @ 2A/min, TBHT @ 1A/min
Thursday, October 09, 2014, 16:00
vented in air and opened up this morning
target container looks good!
|
167
|
Thursday, October 23, 2014, 15:38 |
Laura Lambert | SiC | 39530-8 | HP-FEBIAD | In progress | Testing the new OMEGA-IR2C on SiC#31 target | Thursday, October 23, 2014, 15:34
*See elog #142 for target description*
one endcap still in place, one removed for OMEGA-IR2C beam to reach material [see pic]
no heat shields
currently being pumped down
Friday, October 24, 2014, 11:34
EVAP2 pumped down overnight.
IGP1 = 7e-7 Torr
HS water valves opened, no leaks detected.
TGHT will be ramped up to 1400C
TBHT will be ramped up to 230A
Friday, October 24, 2014, 14:32
TBHT reached 230A, TGHT reached 1400C
Stepped TGHT up manually to 1600C; TGHT = 693A, 10.6V [see pic]
Friday, October 24, 2014, 15:58
TGHT = 760A, 12.07V [local read back] = setpoint.
epics readback TGHT = 754.8A, 11.76V
OMEGA = 1700C
Friday, October 24, 2014, 16:26
OMEGA = 1800C
epics readback TGHT = 828.7A, 13.15V
Friday, October 24, 2014, 16:34
OMEGA = 1900C
epics readback TGHT = 899A, 14.53V
Friday, October 24, 2014, 16:46
OMEGA = 2000C
epics readback TGHT = 967A, 15.8V
MIKRON target spot on SiC = 1650C, e = 0.97
|
Attachment 1: 2014-10-23_15.12.56.jpg
|
|
Attachment 2: 2014-10-24.jpeg
|
|
170
|
Monday, November 10, 2014, 13:55 |
Laura Lambert | Empty | | LP-SIS | Done | Sintering TaC coating container for UCx#11 [2nd container] | Monday, November 10, 2014, 13:51
target container was sprayed with TaC on friday and sintered over the weekend.
vented and removed from evap2 this morning, looks good.
this container will be used as a round2 for UCx #11 since the last container broke as it was being assembled.
hopefully all the materials can be recovered and re-used/re-loaded into the new container...
|
171
|
Wednesday, November 19, 2014, 15:10 |
Laura Lambert | Empty | 39530-2 | LP-FEBIAD | Done | test#1. direct voltage and OMEGA temperature measurements | Wednesday, November 19, 2014, 15:10
currently pumping down
Wednesday, November 19, 2014, 15:28
container is wrapped with 3 x Ta-heat shield
leak check done
Starting voltage = -0.017mV
TGHT = 0A, 0V
TBHT = 0A, 0V
IGP1 = 1.7e-6 Torr
Wednesday, November 19, 2014, 16:33
Tapped TGHT up manually to 100A
DV [direct voltage] = 0.33V
TGHT = 109A
TBHT = 0A
IGP1 = 1.3e-6 Torr
Initiating auto-ramp of TGHT to 400A at 2A/min
Thursday, November 20, 2014, 09:49
DV = 3.47V
OMEGA = 1645C
TGHT = 401A, 6.49V
TBHT = 0
IGP1 = 4.5e-7Torr
TGHT finished auto-ramping ~19:00 last night
initiating manual tap up to 2000 celsius or 580A [whichever is higher] and recording activity
Friday, November 21, 2014, 12:50
TGHT was ramped up to 580A yesterday and left overnight.
In the picture attached one can see the TGHT current has remained constant at 578A [red = TGHT current, green = TGHT voltage]
The vacuum has slowly gone down as expected.
However, the DV, TGHT voltage and temperature have deviated. They have dipped up and down several times throughout the night. The first deviation was observed ~3.5hours after it reached its target of 580A.
DV reached 6.02V [when TGHT initially hit 580A] and increased to 6.27V after 3.5hrs and is currently sitting at 5.94V
OMEGA reached 2111C [when TGHT initially hit 580A] and increased to 2154C after 3.5 hrs and is currently sitting at 2094C
TGHT voltage reached 10.4V [when TGHT initially hit 580A] and increased to 10.6V after 3.5hrs and is currently sitting at 10.3V
Friday, November 21, 2014, 17:59
EVAP2 sat at max setting: TGHT = 580A and TBHT = 230A for ~4hours
Initiating auto-cool TGHT 2A/min, TBHT 1A/min
Monday, November 24, 2014, 14:28
Vented and opened this morning.
No notable changes on target container.
[See attachments for more detailed information of results]
|
Attachment 1: test#1_TGHT_[without_vacuum].JPG
|
|
Attachment 2: test#1_excel.JPG
|
|
Attachment 3: test#1_graph1.JPG
|
|
Attachment 4: test#1_graph2.JPG
|
|
172
|
Wednesday, November 26, 2014, 14:09 |
Laura Lambert | | | | Maintenance | OMEGA-IR dark patch and backing pump trip | Wednesday, November 26, 2014, 13:47
OMEGA-IR laser had a dark patch on it [see picture]
Cleaned window, still dark patch
When tested by itself, through air, not through window, patch still visible - cleaned lens of OMEGA-IR, still no change.
Conclusion: assuming laser used to be able to focus the OMEGA-IR to a specific area - so visual only, but the measurements itself will not be affected.
Wednesday, November 26, 2014, 13:53
Backing pump trips off every time roughing valve turned on through epics.
Requested further investigation...
Friday, November 28, 2014, 12:09
Backing Pump has been replaced, waiting on a reply from OMEGA re: dark patch on laser
Pancake monitor was also acting funny. Background was reading 100cpm and jumping up to as high as 400cpm by simply moving the probe piece.
The wire connecting the probe to the monitor was replaced and works fine now.
Tuesday, December 09, 2014, 15:55
Finally got a reply from the OMEGA people:
"That [ dark patch] would happen because of sharp bends in the fiber, or simply defective fiber cable.
As manufacturer we allow 2% of broken fibers, out of 870 in the bundle.
As far as measurements is concerned, if IR2 is used in dual colour mode,
the field of view can be obstructed as much as 50%,
without changing the readings accuracy. This laser issure should not affect readings."
-Quote from Brian Newport from OMEGA
|
Attachment 1: IR_focus.jpeg
|
|
173
|
Thursday, December 11, 2014, 10:20 |
Laura Lambert | | | | Maintenance | water supply shut off for lab closure over holidays | Thursday, December 11, 2014, 10:17
water supply and return valves closed for lab closure over the holidays.
all taps leading into evap2 have been closed.
evap2 was fully flushed leaving no water left inside the system.
|
177
|
Tuesday, February 03, 2015, 10:31 |
Laura Lambert | Empty | 41077-2 | LP-SIS | In progress | Coating/Sintering TaC on target container - For Graphite Insert |
John Wong wrote: |
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:28
HS water valves opened; no leaks detected.
IGP1 = 5.9e-7 Torr
Wednesday, February 04, 2015, 11:10
attempted to initiate manual ramp up of TGHT and TBHT yesterday, but not responding to EPICS
currently sitting under vacuum, waiting on fix...
Wednesday, February 04, 2015, 14:16
controls fixed.
initiated auto-ramp.
Thursday, February 05, 2015, 08:56
IGP1 = 4.1e-7 Torr
TGHT = 290A
TBHT = 225A
Increasing auto-ramp to 1.0A/min
Thursday, February 05, 2015, 13:49
IGP1 = 1.4e-6 Torr
TGHT = 569A
TBHT = 232A
Increasing auto-ramp to 2.0A/min
|
179
|
Tuesday, February 10, 2015, 13:19 |
Laura Lambert | Empty | 41077-2 | LP-SIS | Done | Coating/Sintering TaC on target container - For Graphite Insert |
John Wong wrote: |
Laura Lambert wrote: |
John Wong wrote: |
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:28
HS water valves opened; no leaks detected.
IGP1 = 5.9e-7 Torr
Wednesday, February 04, 2015, 11:10
attempted to initiate manual ramp up of TGHT and TBHT yesterday, but not responding to EPICS
currently sitting under vacuum, waiting on fix...
Wednesday, February 04, 2015, 14:16
controls fixed.
initiated auto-ramp.
Thursday, February 05, 2015, 08:56
IGP1 = 4.1e-7 Torr
TGHT = 290A
TBHT = 225A
Increasing auto-ramp to 1.0A/min
Thursday, February 05, 2015, 13:49
IGP1 = 1.4e-6 Torr
TGHT = 569A
TBHT = 232A
Increasing auto-ramp to 2.0A/min
|
Thursday, February 05, 2015, 18:02
Auto-cooling TGHT to 400A at 1A/min. Need to take voltage reading tomorrow.
|
Tuesday, February 10, 2015, 09:35
Vented and opened this morning.
Container fully sintered.
|
Attachment 1: empty_container_table.JPG
|
|
180
|
Tuesday, February 10, 2015, 14:01 |
Laura Lambert | Empty | 41077-2 | LP-SIS | Done | Conditioning graphite insert inside container - no heat shield | Tuesday, February 10, 2015, 14:00
Container loaded into EVAP2 at noon.
no heat shields.
Chamber currently being pumped down.
TGHT/ TBHT will be ramped up to 580A/ 230A, tapped up manually.
Tuesday, February 10, 2015, 14:39
HS water valves opened, no leaks detected.
Tapping up manually / recording data in excel
Wednesday, February 11, 2015, 11:24
Reached max set points yesterday early evening.
Tapped down manually this a.m.
Will vent and open this afternoon.
Wednesday, February 11, 2015, 15:54
Took out this afternoon.
container looks good.
graphite insert removed/ inspected - not much change, slightly lighter in colour.
[see attachments for graphs/ table]
|
Attachment 1: graphite_insert_table.JPG
|
|
Attachment 2: graphite_insert_no_hs_power_vs_temp.JPG
|
|
Attachment 3: graphite_insert_no_hs_resistance.JPG
|
|
181
|
Wednesday, February 11, 2015, 16:12 |
Laura Lambert | Empty | 41077-2 | LP-SIS | Done | Conditioning graphite insert inside container - with heat shield | Wednesday, February 11, 2015, 16:10
Container loaded into EVAP2.
3xTa heat shields.
Chamber currently being pumped down.
TGHT/ TBHT will be ramped up to 580A/ 230A or 1800C tapped up manually.
Thursday, February 12, 2015, 09:39
HS water valves opened, no leaks detected.
Tapping up manually.
Thursday, February 12, 2015, 12:07
OMEGA reached 1805C; TGHT = 415A, TBHT = 205A
Will continue to tap up manually to 2000C
Thursday, February 12, 2015, 15:19
Reached TGHT = 500A, TBHT = 230A, OMEGA = 2035C.
Sat for ~2hrs.
Tapping up a further 25A on the TGHT.
Thursday, February 12, 2015, 16:05
Tapped up manually to:
OMEGA = 2250C
DV = 5.65V
TGHT = 580A
TBHT = 230A
Friday, February 13, 2015, 10:05
Reached max setpoint last night.
Voltage starting to increase at contant TGHT @ 580A. Lower TGHT to 525A, temp at 2150C (time 6:30pm)
Initiating manual cool down.
Friday, February 13, 2015, 15:31
vented and opened up this afternoon.
everything looked good, container not broken! graphite insert looked good! the container was slightly bent, but nothing of significance.
however, the graphite insert bonded to the container so it was not taken out in one piece... |
Attachment 1: grp_with_HS_before_cooling.JPG
|
|
Attachment 2: grp_insert_with_HS_table.JPG
|
|
Attachment 3: resistance.JPG
|
|
Attachment 4: temp_vs_current.JPG
|
|
Attachment 5: temp_vs_power.JPG
|
|
182
|
Thursday, February 19, 2015, 15:21 |
Laura Lambert | Empty | 41177-2 | LP-SIS | Done | Sintering TaC coating container for UCx#12 | Thursday, February 19, 2015, 15:19
Target container coated with TaC, loaded in EVAP2.
No Ta heat shields.
Will pump down over the weekend.
Monday, February 23, 2015, 10:22
IGP1 = 1.75e-7 Torr
TGHT will be ramped up to 580A at 0.2A/min
TBHT will be ramped up to 230A at 0.2A/min
evap2 power supply not responding to epics controls...waiting on fix
Wednesday, February 25, 2015, 16:05
controls now fixed.
danceioc1 involving evap ioc will be updated tomorrow by controls.
once ioc update complete will ramp up.
Friday, February 27, 2015, 09:34
ioc update complete yesterday afternoon.
IGP1 = 1.1e-7
initiating ramp up...
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Monday, March 02, 2015, 09:01
IGP1 = 2.5e-7 Torr
TGHT = 578A
TBHT = 232A
OMEGA = 1750C
Increasing to 1800C
Monday, March 02, 2015, 10:42
Reached 1800C at 10:30
TGHT = 603A
TBHT = 232A
IGP1 = 2.8e-7 Torr
Monday, March 02, 2015, 14:26
Sat at max set point for 4hrs.
IGP1 = 2.7e-7 Torr.
Initiating auto-cool, TGHT @ 2A/min, TBHT @ 1A/min.
Tuesday, March 03, 2015, 09:17
vented and opened this a.m.
target container looks good, TaC coating fully sintered.
|
183
|
Monday, March 09, 2015, 16:50 |
Laura Lambert | Ta | 38817-5 | HP-SIS | In progress | Conditioning Ta target | Monday, March 09, 2015, 16:47
Target consists of 400 discs.
Total packed length 3.4cm
Total mass 45.8181g
Re foil inserted.
Chamber is currently being pumped down.
No Ta-heat shield wrapped.
One end-cap inserted on left (wrt ionizer into the page)
TGHT and TBHT will be ramped up to 820A/230A respectively at 2.0A/min.
Tuesday, March 10, 2015, 10:28
HS water valves opened, no leaks detected.
IGP1 = 4.5e-7 Torr.
Power supply not responding to epics...AGAIN. grrrr
Tuesday, March 10, 2015, 13:17
IOC was rebooted - back up and running again! yay!
IGP1 = 4.0e-7 Torr.
Tapped up manually to 35A, waited ~30min, vaccuum stable.
Initiating auto-ramp.
Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr.
Wednesday, March 11, 2015, 09:11
Target has been at max setpoints for ~14hrs.
OMEGA = 1472C
TGHT = 820A, 12.85V
TBHT = 230A, 3.696V
IGP1 = 5.5ee-7 Torr
Manually tapping up to obtain hotter internal temperature...
Wednesday, March 11, 2015, 11:33
Current conditions:
OMEGA = 1565C
TGHT = 900A, 14.3V
TBHT = 230A, 3.7V
IGP1 = 6.3e-7 Torr
Digital pyrometer readings:
Hottest point on left leg, WRT ionizer tube into page = 2400C
Internal temp of container = 1580C
Sat at this temperature ~45min.
Initiating auto-cool at TGHT 2.0A/min, TBHT 1.0A/min
[See attached photo for collected data]
Thursday, March 12, 2015, 13:12
vented and opened up this morning.
only reached a max internal temp of 1580C.
therefore added 3xTa heat shield and will re-condition at a higher temp.
currently pumping back down.
Thursday, March 12, 2015, 14:34
IGP1 = 7.0e-7 Torr
stepped up to 35A, waited ~30min, vacuum stable.
IGP1 = 6.1e-7 Torr
Initating ramp-up...
Friday, March 13, 2015, 07:47
IGP1 = 2.9e-7 Torr
reached max set points for TGHT = 600A, TBHT = 230A
Initiating manual tap-up.
Friday, March 13, 2015, 10:31
Reached 720A, 1800C at 0850
Will continue to heat for ~3hrs
[see attachment for collected data]
Friday, March 13, 2015, 12:00
Sat at max temperature, 1800C, for 3 hours.
Initiating auto-cool at 2.0A/min for TGHT and 1.0A/min for TBHT.
|
Attachment 1: first_ramp_up.JPG
|
|
Attachment 2: second_ramp_up_with_Ta_heat_shields.JPG
|
|
185
|
Thursday, April 09, 2015, 09:38 |
Laura Lambert | Empty | 38817-7 | HP-SIS | Done | Sintering TaC coating container for SiC#32 | Thursday, April 09, 2015, 09:33
Target container is coated with TaC and wrapped with 3-Ta heat shields, not incl center block.
TGHT and TBHT will be ramped up to 820A and 230A, respectively.
Chamber pumped down overnight.
IGP1 = 5.2e-7 Torr.
HS cooling water valves opened; no leaks detected.
TGHT max voltage = 18V, TBHT max voltage = 5V
Stepping TGHT and TBHT up to 35A...
Thursday, April 09, 2015, 10:07
Waited ~20min, vacuum stable.
IGP1 = 5.3e-7 Torr.
Good vac = 3e-5 Torr. Bad vac = 4e-5 Torr.
Auto-ramp initiated at 0.2A/min.
Monday, April 13, 2015, 09:06
Reached max setpoints sunday morning [see attached photo for striptool].
Internal temperature measured with OMEGA = 1965C
IGP1 = 4.4e-7 Torr,
Initiating auto cool for TGHT and TBHT at 2.0A/min and 1.0A/min respectively.
Tuesday, April 14, 2015, 14:12
Vented in air and opened up this morning.
Fully sintered.
|
Attachment 1: sintering_TaC_coating_for_container.JPG
|
|
186
|
Friday, April 17, 2015, 16:14 |
Laura Lambert | SiC | 38817-7 | HP-SIS | In progress | Sintering SiC#31 | Friday, April 17, 2015, 16:01
Total number of foils: 520 discs
Total mass of materials [incl graphite foils]: 60.2441g
Total length packed: 17.0cm
Container is wrapped with 3x Ta-heat shields.
No endcaps inserted to allow outgasing.
Currently being pumped down.
Monday, April 20, 2015, 11:08
Target container is coated with TaC and wrapped with 3-Ta heat shields, not incl center block.
TGHT and TBHT will be ramped up to 820A and 230A, respectively.
Chamber pumped down over the weekend.
IGP1 = 2.1e-7 Torr.
HS cooling water valves opened; no leaks detected.
TGHT max voltage = 18V, TBHT max voltage = 5V
....
attempted to start stepping up manually.
power supply not responding to epics controls for TBHT only...looking into problems now...
Monday, April 20, 2015, 16:06
Epics is working.
Power supply connections unplugged/plugged back in.
Everything working again.
Tapped up manually to 40A.
Waited ~1hr30 for vacuum to stabilize.
IGP1 = 1.8e-6 Torr.
Good vac = 3e-5 Torr. Bad vac = 4e-5 Torr.
TGHT and TBHT will be ramped up to 820A and 230A, respectively.
Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
Wednesday, April 22, 2015, 15:23
TGHT = 200A, 2.26V; TBHT = 117A, 1.58V
IGP1 = 9.8e-6 Torr.
Increasing auto-ramp to 0.4A/min and 0.2A/min for the TGHT and TBHT respectively.
|
188
|
Friday, May 01, 2015, 10:50 |
Laura Lambert | | 40282-4 | TARGET BOAT | In progress | Sintering four different ZrC samples | Friday, May 01, 2015, 10:27
Four different samples of ZrC are loaded into a target boat.
Sample A: ZrC + NO graphite / hand cut
Sample B: ZrC + NO graphite / laser cut
Sample C: ZrC + graphite / hand cut
Sample D: ZrC + graphite / laser cut
A picture showing the different samples is attached [one face-up/ one face-down sample of each side-by-side]
Each sample consists of ~20-25 discs, stacked together and wrapped in graphite sheet [see attachment for photo]
The target boat is wrapped with 3 x Ta heat shield.
EVAP1 pumped down overnight.
HS water valves were opened this morning, no leaks detected.
IGP1 = 5.5e-7 Torr.
Tapping up TGHT manually to 30A...
Friday, May 01, 2015, 10:54
Tapped up manually to 30A.
Over the course of 20min the vacuum climbed to IGP1 = 1.0 e-5 Torr.
Backed off TGHT to 20A to allow vacuum to stabilize.
Waited ~10min.
Vacuum dropped to IGP1 = 6.5e-6 Torr.
Tapped back-up manually to 30A.
Waited ~45min.
Vacuum stable, IGP1 = 1.2e-5 Torr.
Initiating auto-ramp at 0.1A/min for the TGHT with a max setpoint of 300A / 5.00V.
Good Vacuum = 3.00e-5 Torr. Bad vacuum = 4.00e-5 Torr.
Monday, May 04, 2015, 11:17
IGP1 = 2e-7 Torr.
TGHT = 274A, 4.75V
Ramp-up limited to 275A due to max voltage being set at 5.0V
Increased max voltage to 10V
Tapping up manually to 1800C and recording data.
|
Attachment 1: 1.jpg
|
|
Attachment 2: 2015-04-30_15.24.57.jpg
|
|
190
|
Wednesday, May 06, 2015, 13:59 |
Laura Lambert | | 40282-4 | TARGET BOAT | Done | Sintering two different ZrC samples | Wednesday, May 06, 2015, 13:54
Two different samples of ZrC are wrapped in graphite sheet and loaded into the target boat.
Sample #1 = ZrC
Sample #2 = ZrC+C
Both samples are hand punched with a 18mm die.
The target boat is wrapped with 3x Ta heat shield.
Pumped down this morning.
HS water valves opened, no leaks detected.
IGP1 = 1.5e-6 Torr.
Tapping up manually to 35A...
Waited ~50min for vacuum to stabilize.
IGP1 = 5.3e-6 Torr.
Initiating auto-ramp at 0.1A/min for the TGHT with a max setpoint of 275A/ 10V
Good vacuum = 3.00e-5 Torr. Bad vacuum = 4.00e-5 Torr.
Wednesday, May 06, 2015, 15:37
Increasing ramping rate to 0.2A/min
Thursday, May 07, 2015, 11:15
Stopping auto ramp.
TGHT = 273A.
Tapping up manually and recording data...
IGP1 = 6.6e-7 Torr.
Thursday, May 07, 2015, 14:21
Increased max voltage to 14V
Friday, May 08, 2015, 09:33
EVAP2 reached 2000C yesterday evening and remained at max setpoint overnight.
IGP1 = 3.8e-7 Torr
Initiated auto-cool this morning at 2.0A/min.
Friday, May 08, 2015, 11:32
IGP1 = 2.1e-7 Torr
TGHT = 221A, 3.21V
OMEGA = 1100C
Increasing auto-cool to 5.0A/min.
Friday, May 08, 2015, 15:53
Vented in air and opened up this afternoon.
See attachment for data results.
|
Attachment 1: evap2_data_from_two_samples_-_18mm_hand_punched.xlsx
|
191
|
Friday, May 08, 2015, 15:56 |
Laura Lambert | | 40282-4 | TARGET BOAT | Done | Sintering four different ZrC samples |
John Wong wrote: |
Laura Lambert wrote: |
Friday, May 01, 2015, 10:27
Four different samples of ZrC are loaded into a target boat.
Sample A: ZrC + NO graphite / hand cut
Sample B: ZrC + NO graphite / laser cut
Sample C: ZrC + graphite / hand cut
Sample D: ZrC + graphite / laser cut
A picture showing the different samples is attached [one face-up/ one face-down sample of each side-by-side]
Each sample consists of ~20-25 discs, stacked together and wrapped in graphite sheet [see attachment for photo]
The target boat is wrapped with 3 x Ta heat shield.
EVAP1 pumped down overnight.
HS water valves were opened this morning, no leaks detected.
IGP1 = 5.5e-7 Torr.
Tapping up TGHT manually to 30A...
Friday, May 01, 2015, 10:54
Tapped up manually to 30A.
Over the course of 20min the vacuum climbed to IGP1 = 1.0 e-5 Torr.
Backed off TGHT to 20A to allow vacuum to stabilize.
Waited ~10min.
Vacuum dropped to IGP1 = 6.5e-6 Torr.
Tapped back-up manually to 30A.
Waited ~45min.
Vacuum stable, IGP1 = 1.2e-5 Torr.
Initiating auto-ramp at 0.1A/min for the TGHT with a max setpoint of 300A / 5.00V.
Good Vacuum = 3.00e-5 Torr. Bad vacuum = 4.00e-5 Torr.
Monday, May 04, 2015, 11:17
IGP1 = 2e-7 Torr.
TGHT = 274A, 4.75V
Ramp-up limited to 275A due to max voltage being set at 5.0V
Increased max voltage to 10V
Tapping up manually to 1800C and recording data.
|
Monday, May 04, 2015, 17:24
Samples have been heated at 1800C for >2 hours.
Vaccum at 4.3e-7 Torr, TGHT 475A/9.1V. (Direct Vol = 5.3V).
Initiated cooling down process. Chamber will be vented tomorrow.
Tuesday, May 05, 2015, 10:22
TGHT reached to 0A. Chamber has already vented.
Samples will be taken out for examination.
|
Friday, May 08, 2015, 15:55
see attachment for data results.
|
Attachment 1: evap2_data_from_four_samples.xlsx
|
192
|
Wednesday, May 13, 2015, 16:01 |
Laura Lambert | | 40282-4 | TARGET BOAT | Done | Sintering three different ZrC samples | Wednesday, May 13, 2015, 15:21
Three different samples of ZrC are loaded into a target boat.
Sample A: ZrC + NO graphite
Sample B: ZrC + graphite [1:0.5 molar ratio]
Sample C: ZrC + graphite [1:1 molar ratio]
Each sample consists of 20 discs, stacked together and wrapped in graphite sheet
The target boat is wrapped with 3 x Ta heat shield.
EVAP2 pumping down overnight...
Thursday, May 14, 2015, 08:20
HS water valves opened up this a.m, no leaks detected.
IGP1 = 6.6e-7 Torr
Tapping up manually to 35A.
Good Vacuum = 3.00 e-5 Torr. Bad Vacuum = 4.00 e-5 Torr.
Thursday, May 14, 2015, 09:51
Tapped up manually to 30A.
After ~25min, vacuum gone up to IGP1 = 3.5e-5 Torr!
Backed off to 20A.
Waited ~10min. IGP1 = 1.75e-5 Torr.
Tapped back up to 25A.
Waited ~20min, IGP1 = 1.4e-5 Torr.
Tapped up to 30A.
Waited ~20min, IGP1 = 2.2e-5 Torr.
Tapped up to 35A
Waited ~50min, IGP1 = 2.5e-5 Torr.
Continuing manual tap-up...
Thursday, May 14, 2015, 13:27
IGP1 = 9e-6 Torr
Tapped up to 40A.
Waited ~45min, IGP1 = 1e-5 Torr
Initiating auto-ramp at 0.1A/min for the TGHT with a max setpoint of 275A/ 8.0V
Friday, May 15, 2015, 08:25
Max setpoints were changed to 400A/ 8.0V last night.
Reached 400A ~4.5hrs ago.
IGP1 = 4.9e-5 Torr
Initiating manual tap up and recording data.
Friday, May 15, 2015, 15:50
Samples remained at ~2000C for ~4 hours [see attachment for data]
IGP1 = 7.8e-7 Torr.
Initiating auto-cool at 1.0A/min.
Tuesday, May 19, 2015, 08:27
Vented in air and opened up this morning.
|
Attachment 1: evap2_data_from_three_samples_-_final_test_run.xlsx
|
|