Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 5 of 34  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Target Material Target Oven W.O#down Source Status Subject Text Attachments
  576   Wednesday, May 18, 2022, 09:59 Darwin Ortiz RosalesSiC44692-9HP-FEBIADDoneT-220516 Sintering SiC Wednesday, May 18, 2022, 09:46
Total number of foils:
  
  610   Tuesday, February 28, 2023, 07:21 Darwin Ortiz RosalesTa44692-7LP-FEBIADDoneTaC coating sinteringTuesday, February 28, 2023, 07:19
Ta LP-FEBIAD was coated
  
  612   Saturday, March 04, 2023, 08:34 Darwin Ortiz RosalesTiC44692-7LP-FEBIADDoneTiC230301 conditioningSaturday, March 04, 2023, 08:29
  
  624   Monday, April 24, 2023, 09:12 Darwin Ortiz RosalesTaC44692-5LP-FEBIADDoneTaC coating sinteringSunday, April 23, 2023, 07:23
The coated container was wrapped
in 3 Ta foil heatshields.
  
  625   Wednesday, April 26, 2023, 09:48 Darwin Ortiz RosalesTiC44692-5LP-FEBIADDoneTiC230425Wednesday, April 26, 2023, 09:32
LP FEBIAD loaded with 367 TiC discs
and 4 TiC removable discs for analyses
  
  626   Wednesday, April 26, 2023, 18:20 Carla BabcockTiC44692-5LP-FEBIADIn progressTiC230425


   
        
            
  
  627   Wednesday, April 26, 2023, 22:26 John WongTiC44692-5LP-FEBIADIn progressTiC230425


   
        
            
 Screenshot_2023-04-26_221720.jpg 
  628   Thursday, April 27, 2023, 06:30 Darwin Ortiz RosalesTiC44692-5LP-FEBIADDoneTiC230425


   
        
            
  
  629   Thursday, April 27, 2023, 21:48 Carla BabcockTiC44692-5LP-FEBIADIn progressTiC230425


   
        
            
 MicrosoftTeams-image_(36).png 
  630   Thursday, April 27, 2023, 22:18 John WongTiC44692-5LP-FEBIADIn progressTiC230425


   
        
            
 Screenshot_2023-04-27_204948.jpgScreenshot_2023-04-27_205012.jpgScreenshot_2023-04-27_220239.jpgScreenshot_2023-04-27_220323.jpgScreenshot_2023-04-28_010640.jpg 
  631   Friday, April 28, 2023, 09:39 Darwin Ortiz RosalesTiC44692-5LP-FEBIADDoneTiC230425


   
        
            
 MicrosoftTeams-image_(20).png 
  611   Wednesday, March 01, 2023, 21:49 Darwin Ortiz RosalesTa44692-3HP-SISDoneTaC coating sinteringWednesday, March 01, 2023, 21:46
Ta HP-SIS was coated
  
  613   Monday, March 06, 2023, 21:34 Darwin Ortiz RosalesSiC44692-3HP-SISDone230306SiC conditioningMonday, March 06, 2023, 21:29
Total number of foils:382
  
  615   Sunday, March 12, 2023, 08:06 Darwin Ortiz RosalesTa44692-2HP-SISDoneTaC coating sinteringSunday, March 12, 2023, 08:04
Ta HP-SIS was coated
  
  616   Monday, March 13, 2023, 22:31 Darwin Ortiz RosalesSiC44692-2HP-SISDoneSiC-230313Monday, March 13, 2023, 22:28
Total number of foils:380
  
  602   Thursday, November 17, 2022, 08:14 Darwin Ortiz RosalesTaC44692-12TARGET BOATDoneTaC coating sinteringThursday, November 17, 2022, 08:11
The coated container was wrapped
in four Ta foil heatshields.
  
  639   Tuesday, August 15, 2023, 12:03 Darwin Ortiz RosalesTaC44692-11TARGET BOATDoneTaC coating sinteringTuesday, August 15, 2023, 10:48
The coated container was wrapped
in 4 Ta foil heatshields.
  
  640   Tuesday, August 22, 2023, 09:35 Darwin Ortiz RosalesTaC44692-11TARGET BOATDoneTaC coating sintering (second coating on same tube)Tuesday, August 22, 2023, 09:29
The coated container was wrapped
in 4 Ta foil heatshields.
  
  654   Wednesday, February 07, 2024, 22:49 Darwin Ortiz RosalesTiC44692-11LP TUBEDone240206TiC conditioning
Wednesday, February 07, 2024, 22:36
Ta container tube TaC coated, wrapped
in 4 Ta foil heat-shields, and loaded with
  
  586   Wednesday, June 29, 2022, 10:12 Darwin Ortiz RosalesTaC44692-10HP-FEBIADDoneTaC coating sinteringWednesday, June 29, 2022, 10:07
Ta HP-FEBIAD was coated
  