Wednesday, January 14, 2015, 13:46, Anders Mjos, Empty, , , Maintenance, Pumping down for water leak test
|
Wednesday, January 14, 2015, 13:46: Roughing
Wednesday, January 14, 2015, 14:57: Starting turbo
Monday, January 19, 2015, 13
Water opened up to one circuit at at time. No response on the vacuum could be seen.
IGP1 at 1.7E-7 T
IGP2 at 3E-8 T
Tuesday, January 20, 2015, 13:11: Stopped turbo and roughing pump.
Wednesday, January 21, 2015, 15:46: Venting
Rick and Anders found CG1A to be reading too high a value. A borrowed gauge from the vacuum group confirmed this. A new gauge will be installed
Thursday, January 22, 2015, 14:06: Roughing
Thursday, January 22, 2015, 14:18: Venting
The reading is consistent between CG1A and CG1B, which simplifies pump down. |
Thursday, January 22, 2015, 14:21, Anders Mjos, Empty, , , Problems resolved, CG1A replaced
|
See previous e-log entry for details |
Monday, February 02, 2015, 16:33, John Wong, Empty, 41077-2, LP-SIS, In progress, Coating/Sintering TaC on target container - For Graphite Insert
|
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:31, Laura Lambert, Empty, 41077-2, LP-SIS, In progress, Coating/Sintering TaC on target container - For Graphite Insert
|
John Wong wrote: |
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:28
HS water valves opened; no leaks detected.
IGP1 = 5.9e-7 Torr
Wednesday, February 04, 2015, 11:10
attempted to initiate manual ramp up of TGHT and TBHT yesterday, but not responding to EPICS
currently sitting under vacuum, waiting on fix...
Wednesday, February 04, 2015, 14:16
controls fixed.
initiated auto-ramp.
Thursday, February 05, 2015, 08:56
IGP1 = 4.1e-7 Torr
TGHT = 290A
TBHT = 225A
Increasing auto-ramp to 1.0A/min
Thursday, February 05, 2015, 13:49
IGP1 = 1.4e-6 Torr
TGHT = 569A
TBHT = 232A
Increasing auto-ramp to 2.0A/min
|
Thursday, February 05, 2015, 18:03, John Wong, Empty, 41077-2, LP-SIS, In progress, Coating/Sintering TaC on target container - For Graphite Insert
|
Laura Lambert wrote: |
John Wong wrote: |
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:28
HS water valves opened; no leaks detected.
IGP1 = 5.9e-7 Torr
Wednesday, February 04, 2015, 11:10
attempted to initiate manual ramp up of TGHT and TBHT yesterday, but not responding to EPICS
currently sitting under vacuum, waiting on fix...
Wednesday, February 04, 2015, 14:16
controls fixed.
initiated auto-ramp.
Thursday, February 05, 2015, 08:56
IGP1 = 4.1e-7 Torr
TGHT = 290A
TBHT = 225A
Increasing auto-ramp to 1.0A/min
Thursday, February 05, 2015, 13:49
IGP1 = 1.4e-6 Torr
TGHT = 569A
TBHT = 232A
Increasing auto-ramp to 2.0A/min
|
Thursday, February 05, 2015, 18:02
Auto-cooling TGHT to 400A at 1A/min. Need to take voltage reading tomorrow.
|
Tuesday, February 10, 2015, 13:19, Laura Lambert, Empty, 41077-2, LP-SIS, Done, Coating/Sintering TaC on target container - For Graphite Insert
|
John Wong wrote: |
Laura Lambert wrote: |
John Wong wrote: |
Monday, February 02, 2015, 16:28
Container is coated with TaC. No Ta foil wrapped around.
Chamber is being pumped down.
TGHT/TBHT will be ramped up to 580A/230A at 0.2A/min.
|
Tuesday, February 03, 2015, 10:28
HS water valves opened; no leaks detected.
IGP1 = 5.9e-7 Torr
Wednesday, February 04, 2015, 11:10
attempted to initiate manual ramp up of TGHT and TBHT yesterday, but not responding to EPICS
currently sitting under vacuum, waiting on fix...
Wednesday, February 04, 2015, 14:16
controls fixed.
initiated auto-ramp.
Thursday, February 05, 2015, 08:56
IGP1 = 4.1e-7 Torr
TGHT = 290A
TBHT = 225A
Increasing auto-ramp to 1.0A/min
Thursday, February 05, 2015, 13:49
IGP1 = 1.4e-6 Torr
TGHT = 569A
TBHT = 232A
Increasing auto-ramp to 2.0A/min
|
Thursday, February 05, 2015, 18:02
Auto-cooling TGHT to 400A at 1A/min. Need to take voltage reading tomorrow.
|
Tuesday, February 10, 2015, 09:35
Vented and opened this morning.
Container fully sintered.
|
Tuesday, February 10, 2015, 14:01, Laura Lambert, Empty, 41077-2, LP-SIS, Done, Conditioning graphite insert inside container - no heat shield  
|
Tuesday, February 10, 2015, 14:00
Container loaded into EVAP2 at noon.
no heat shields.
Chamber currently being pumped down.
TGHT/ TBHT will be ramped up to 580A/ 230A, tapped up manually.
Tuesday, February 10, 2015, 14:39
HS water valves opened, no leaks detected.
Tapping up manually / recording data in excel
Wednesday, February 11, 2015, 11:24
Reached max set points yesterday early evening.
Tapped down manually this a.m.
Will vent and open this afternoon.
Wednesday, February 11, 2015, 15:54
Took out this afternoon.
container looks good.
graphite insert removed/ inspected - not much change, slightly lighter in colour.
[see attachments for graphs/ table]
|
Wednesday, February 11, 2015, 16:12, Laura Lambert, Empty, 41077-2, LP-SIS, Done, Conditioning graphite insert inside container - with heat shield    
|
Wednesday, February 11, 2015, 16:10
Container loaded into EVAP2.
3xTa heat shields.
Chamber currently being pumped down.
TGHT/ TBHT will be ramped up to 580A/ 230A or 1800C tapped up manually.
Thursday, February 12, 2015, 09:39
HS water valves opened, no leaks detected.
Tapping up manually.
Thursday, February 12, 2015, 12:07
OMEGA reached 1805C; TGHT = 415A, TBHT = 205A
Will continue to tap up manually to 2000C
Thursday, February 12, 2015, 15:19
Reached TGHT = 500A, TBHT = 230A, OMEGA = 2035C.
Sat for ~2hrs.
Tapping up a further 25A on the TGHT.
Thursday, February 12, 2015, 16:05
Tapped up manually to:
OMEGA = 2250C
DV = 5.65V
TGHT = 580A
TBHT = 230A
Friday, February 13, 2015, 10:05
Reached max setpoint last night.
Voltage starting to increase at contant TGHT @ 580A. Lower TGHT to 525A, temp at 2150C (time 6:30pm)
Initiating manual cool down.
Friday, February 13, 2015, 15:31
vented and opened up this afternoon.
everything looked good, container not broken! graphite insert looked good! the container was slightly bent, but nothing of significance.
however, the graphite insert bonded to the container so it was not taken out in one piece... |
Thursday, February 19, 2015, 15:21, Laura Lambert, Empty, 41177-2, LP-SIS, Done, Sintering TaC coating container for UCx#12
|
Thursday, February 19, 2015, 15:19
Target container coated with TaC, loaded in EVAP2.
No Ta heat shields.
Will pump down over the weekend.
Monday, February 23, 2015, 10:22
IGP1 = 1.75e-7 Torr
TGHT will be ramped up to 580A at 0.2A/min
TBHT will be ramped up to 230A at 0.2A/min
evap2 power supply not responding to epics controls...waiting on fix
Wednesday, February 25, 2015, 16:05
controls now fixed.
danceioc1 involving evap ioc will be updated tomorrow by controls.
once ioc update complete will ramp up.
Friday, February 27, 2015, 09:34
ioc update complete yesterday afternoon.
IGP1 = 1.1e-7
initiating ramp up...
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Monday, March 02, 2015, 09:01
IGP1 = 2.5e-7 Torr
TGHT = 578A
TBHT = 232A
OMEGA = 1750C
Increasing to 1800C
Monday, March 02, 2015, 10:42
Reached 1800C at 10:30
TGHT = 603A
TBHT = 232A
IGP1 = 2.8e-7 Torr
Monday, March 02, 2015, 14:26
Sat at max set point for 4hrs.
IGP1 = 2.7e-7 Torr.
Initiating auto-cool, TGHT @ 2A/min, TBHT @ 1A/min.
Tuesday, March 03, 2015, 09:17
vented and opened this a.m.
target container looks good, TaC coating fully sintered.
|
Thursday, April 09, 2015, 09:38, Laura Lambert, Empty, 38817-7, HP-SIS, Done, Sintering TaC coating container for SiC#32
|
Thursday, April 09, 2015, 09:33
Target container is coated with TaC and wrapped with 3-Ta heat shields, not incl center block.
TGHT and TBHT will be ramped up to 820A and 230A, respectively.
Chamber pumped down overnight.
IGP1 = 5.2e-7 Torr.
HS cooling water valves opened; no leaks detected.
TGHT max voltage = 18V, TBHT max voltage = 5V
Stepping TGHT and TBHT up to 35A...
Thursday, April 09, 2015, 10:07
Waited ~20min, vacuum stable.
IGP1 = 5.3e-7 Torr.
Good vac = 3e-5 Torr. Bad vac = 4e-5 Torr.
Auto-ramp initiated at 0.2A/min.
Monday, April 13, 2015, 09:06
Reached max setpoints sunday morning [see attached photo for striptool].
Internal temperature measured with OMEGA = 1965C
IGP1 = 4.4e-7 Torr,
Initiating auto cool for TGHT and TBHT at 2.0A/min and 1.0A/min respectively.
Tuesday, April 14, 2015, 14:12
Vented in air and opened up this morning.
Fully sintered.
|
Tuesday, May 19, 2015, 13:54, Laura Lambert, Empty, 41177-1, LP-SIS, Done, Sintering TaC coating container for ZrC
|
Tuesday, May 19, 2015, 13:33
Target container is coated with TaC. No Ta-heat shields are used.
TGHT will be ramped up to 580A at 0.2A/min.
TBHT will be ramped up to 230A at 0.1A/min.
Chamber is currently being pumped down
Tuesday, May 19, 2015, 15:04
Opened up HS water, no leaks detected.
Stepped up to 35A.
Waited ~35min, vacuum stable.
IGP1 = 1.7e-6 Torr.
Initiating auto-ramp.
Wednesday, May 20, 2015, 11:43
IGP1 = 3e-7 Torr.
TGHT = 282A, 3.8V
TBHT = 156A, 2.2V
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Thursday, May 21, 2015, 10:42
IGP1 = 2.9e-7
Direct voltage = 5.48V
OMEGA = 1703C.
Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT.
Friday, May 22, 2015, 11:41
Vented in air and opened up this morning.
TaC coating fully sintered, looks good! 
|
Friday, May 22, 2015, 11:44, Laura Lambert, Empty, , TARGET BOAT, In progress, Sintering TaC coating on Ta target boat
|
Friday, May 22, 2015, 11:43
A target boat was sprayed with TaC coating and let dry yesterday.
The target boat is wrapped with 3-layers of Ta-heat shield.
The boat was installed in EVAP2, chamber is currently being pumped down.
Friday, May 22, 2015, 14:22
HS water valves opened, no leaks detected.
IGP1 = 2.4e-6 Torr.
Tapping up manually...
Friday, May 22, 2015, 14:33
Tapped up to 20A.
Vacuum jumped up to 7e-6 Torr.
Backed off to 5A before vacuum started to drop again.
IGP1 = 5e-6 Torr.
Tapping up manually again...just more slowly...
Friday, May 22, 2015, 15:31
Tapped up to 12A, unable to tap up very fast due to volatile content in coating.
IGP1 = 3.6e-6 Torr.
Initiating auto-ramp at 0.1A/min with a max current of 580A.
Monday, May 25, 2015, 09:03
IGP1 = 3e-7 Torr.
TGHT = 397.5A, 6.43V
Increasing ramping rate to 1.0A/min.
|
Monday, May 25, 2015, 17:08, John Wong, Empty, 40282-5, TARGET BOAT, In progress, Sintering TaC coating on Ta target boat
|
Laura Lambert wrote: |
Friday, May 22, 2015, 11:43
A target boat was sprayed with TaC coating and let dry yesterday.
The target boat is wrapped with 3-layers of Ta-heat shield.
The boat was installed in EVAP2, chamber is currently being pumped down.
Friday, May 22, 2015, 14:22
HS water valves opened, no leaks detected.
IGP1 = 2.4e-6 Torr.
Tapping up manually...
Friday, May 22, 2015, 14:33
Tapped up to 20A.
Vacuum jumped up to 7e-6 Torr.
Backed off to 5A before vacuum started to drop again.
IGP1 = 5e-6 Torr.
Tapping up manually again...just more slowly...
Friday, May 22, 2015, 15:31
Tapped up to 12A, unable to tap up very fast due to volatile content in coating.
IGP1 = 3.6e-6 Torr.
Initiating auto-ramp at 0.1A/min with a max current of 580A.
Monday, May 25, 2015, 09:03
IGP1 = 3e-7 Torr.
TGHT = 397.5A, 6.43V
Increasing ramping rate to 1.0A/min.
|
Monday, May 25, 2015, 17:06
TGHT at been at 580A for over 4 hours. Cooling down in process at 1A/min.
|
Tuesday, May 26, 2015, 13:05, Laura Lambert, Empty, 40282-5, TARGET BOAT, Done, Sintering TaC coating on Ta target boat
|
John Wong wrote: |
Laura Lambert wrote: |
Friday, May 22, 2015, 11:43
A target boat was sprayed with TaC coating and let dry yesterday.
The target boat is wrapped with 3-layers of Ta-heat shield.
The boat was installed in EVAP2, chamber is currently being pumped down.
Friday, May 22, 2015, 14:22
HS water valves opened, no leaks detected.
IGP1 = 2.4e-6 Torr.
Tapping up manually...
Friday, May 22, 2015, 14:33
Tapped up to 20A.
Vacuum jumped up to 7e-6 Torr.
Backed off to 5A before vacuum started to drop again.
IGP1 = 5e-6 Torr.
Tapping up manually again...just more slowly...
Friday, May 22, 2015, 15:31
Tapped up to 12A, unable to tap up very fast due to volatile content in coating.
IGP1 = 3.6e-6 Torr.
Initiating auto-ramp at 0.1A/min with a max current of 580A.
Monday, May 25, 2015, 09:03
IGP1 = 3e-7 Torr.
TGHT = 397.5A, 6.43V
Increasing ramping rate to 1.0A/min.
|
Monday, May 25, 2015, 17:06
TGHT at been at 580A for over 4 hours. Cooling down in process at 1A/min.
|
Vented in air and opened up this morning.
Target boat looks good! fully sintered!  |
Thursday, June 04, 2015, 11:10, Laura Lambert, Empty, , LP-IG-LIS, In progress, Sintering TaC coating container for UCx
|
Thursday, June 04, 2015, 9:07
Container was sprayed with TaC and let dry.
Container has 3x Ta heat shields including center block.
Container was loaded into EVAP2 yesterday and pumped down overnight.
HS water valves were opened up this morning, no leaks detected.
IGP1 = 4.6e-7 Torr.
Tapped up manually to 40A.
Waited ~25min, Vacuum stable.
IGP1 = 5.0e-7 Torr.
Initiating auto-ramp.
TGHT will be ramped to reach 2000C
Friday, June 05, 2015, 10:01
IGP1 = 4.5e-7 Torr.
TGHT = 313A, 4.47V
OMEGA = 1444C
Increasing ramping rate to 1.0A/min
Friday, June 05, 2015, 11:31
IGP1 = 1.2e-6 Torr.
Increasing ramping rate to 2.0A/min
|
Friday, June 05, 2015, 12:19, John Wong, Empty, , LP-IG-LIS, In progress, Sintering TaC coating container for UCx
|
Laura Lambert wrote: |
Thursday, June 04, 2015, 9:07
Container was sprayed with TaC and let dry.
Container has 3x Ta heat shields including center block.
Container was loaded into EVAP2 yesterday and pumped down overnight.
HS water valves were opened up this morning, no leaks detected.
IGP1 = 4.6e-7 Torr.
Tapped up manually to 40A.
Waited ~25min, Vacuum stable.
IGP1 = 5.0e-7 Torr.
Initiating auto-ramp.
TGHT will be ramped to reach 2000C
Friday, June 05, 2015, 10:01
IGP1 = 4.5e-7 Torr.
TGHT = 313A, 4.47V
OMEGA = 1444C
Increasing ramping rate to 1.0A/min
Friday, June 05, 2015, 11:31
IGP1 = 1.2e-6 Torr.
Increasing ramping rate to 2.0A/min
|
Friday, June 05, 2015, 12:01
TGHT reached to 465A/7.56V, temp is stable at 2000C. Current vac at 1.2e-6 Torr and coming down
Cooling down process can be initiated after 4 hours.
|
Friday, June 05, 2015, 13:22, Laura Lambert, Empty, 40860-1, LP-IG-LIS, In progress, Sintering TaC coating container for UCx 
|
John Wong wrote: |
Laura Lambert wrote: |
Thursday, June 04, 2015, 9:07
Container was sprayed with TaC and let dry.
Container has 3x Ta heat shields including center block.
Container was loaded into EVAP2 yesterday and pumped down overnight.
HS water valves were opened up this morning, no leaks detected.
IGP1 = 4.6e-7 Torr.
Tapped up manually to 40A.
Waited ~25min, Vacuum stable.
IGP1 = 5.0e-7 Torr.
Initiating auto-ramp.
TGHT will be ramped to reach 2000C
Friday, June 05, 2015, 10:01
IGP1 = 4.5e-7 Torr.
TGHT = 313A, 4.47V
OMEGA = 1444C
Increasing ramping rate to 1.0A/min
Friday, June 05, 2015, 11:31
IGP1 = 1.2e-6 Torr.
Increasing ramping rate to 2.0A/min
|
Friday, June 05, 2015, 12:01
TGHT reached to 465A/7.56V, temp is stable at 2000C. Current vac at 1.2e-6 Torr and coming down
Cooling down process can be initiated after 4 hours.
|
Friday, June 05, 2015, 13:21
OMEGA = 1995C
Increasing TGHT to 470A to achieve desired max temperature of 2000C
Friday, June 05, 2015, 15:59
TGHT sat at max desired temperature of 2000C for ~4hrs.
TGHT = 470A, 7.7V
Initiating auto-cool at 1.0A/min.
Monday, June 08, 2015, 11:31
Vented in air and opened up this morning.
Target container mostly sintered, two tiny patches near both ends not fully sintered.
Will re-install and re-sinter next week as another container with priority needs to be sintered first.
Tuesday, June 09, 2015, 10:45
See attachements for 'not-fully-sintered' photos
|
Tuesday, June 09, 2015, 10:44, Laura Lambert, Empty, 41177-2, LP-SIS, In progress, Sintering TaC coating container for ZrC back-up
|
Tuesday, June 09, 2015, 9:16
Target container is coated with TaC. No Ta-heat shields are used.
TGHT will be ramped up to 580A at 0.2A/min.
TBHT will be ramped up to 230A at 01A/min.
Chamber is currently being pumped down.
Tuesday, June 09, 2015, 15:37
HS water valves were opened. no leaks detected.
Tapped up manually to 35A.
Once vacuum stabilized after ~45min, initiated auto-ramp.
Wednesday, June 10, 2015, 08:02
IGP1 = 5.3e-7 Torr.
TGHT = 250A and TBHT = 140A.
Increasing auto ramp to 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
|
Wednesday, June 10, 2015, 12:15, John Wong, Empty, 40860-1, LP-IG-LIS, In progress, Sintering TaC coating container for UCx
|
Laura Lambert wrote: |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, June 04, 2015, 9:07
Container was sprayed with TaC and let dry.
Container has 3x Ta heat shields including center block.
Container was loaded into EVAP2 yesterday and pumped down overnight.
HS water valves were opened up this morning, no leaks detected.
IGP1 = 4.6e-7 Torr.
Tapped up manually to 40A.
Waited ~25min, Vacuum stable.
IGP1 = 5.0e-7 Torr.
Initiating auto-ramp.
TGHT will be ramped to reach 2000C
Friday, June 05, 2015, 10:01
IGP1 = 4.5e-7 Torr.
TGHT = 313A, 4.47V
OMEGA = 1444C
Increasing ramping rate to 1.0A/min
Friday, June 05, 2015, 11:31
IGP1 = 1.2e-6 Torr.
Increasing ramping rate to 2.0A/min
|
Friday, June 05, 2015, 12:01
TGHT reached to 465A/7.56V, temp is stable at 2000C. Current vac at 1.2e-6 Torr and coming down
Cooling down process can be initiated after 4 hours.
|
Friday, June 05, 2015, 13:21
OMEGA = 1995C
Increasing TGHT to 470A to achieve desired max temperature of 2000C
Friday, June 05, 2015, 15:59
TGHT sat at max desired temperature of 2000C for ~4hrs.
TGHT = 470A, 7.7V
Initiating auto-cool at 1.0A/min.
Monday, June 08, 2015, 11:31
Vented in air and opened up this morning.
Target container mostly sintered, two tiny patches near both ends not fully sintered.
Will re-install and re-sinter next week as another container with priority needs to be sintered first.
Tuesday, June 09, 2015, 10:45
See attachements for 'not-fully-sintered' photos
|
Wednesday, June 10, 2015, 12:06
After inspecting the target container, the inner tube surface has "dark" patches, which may not be evenly coated or the coating layer was too think.
See link for photos: https://www.dropbox.com/sh/m94mjuuodwhz5jb/AADEBv_Kha_p_1An40eftWNHa?dl=0
Attempt to re-spray the container and re-sinter.
|
Wednesday, June 10, 2015, 16:35, John Wong, Empty, 41177-2, LP-SIS, In progress, Sintering TaC coating container for ZrC back-up
|
Laura Lambert wrote: |
Tuesday, June 09, 2015, 9:16
Target container is coated with TaC. No Ta-heat shields are used.
TGHT will be ramped up to 580A at 0.2A/min.
TBHT will be ramped up to 230A at 01A/min.
Chamber is currently being pumped down.
Tuesday, June 09, 2015, 15:37
HS water valves were opened. no leaks detected.
Tapped up manually to 35A.
Once vacuum stabilized after ~45min, initiated auto-ramp.
Wednesday, June 10, 2015, 08:02
IGP1 = 5.3e-7 Torr.
TGHT = 250A and TBHT = 140A.
Increasing auto ramp to 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
|
Wednesday, June 10, 2015, 16:32
TGHT/TBHT are at 580A/230A for almost 6 hours, temp at 1728C.
Vac at 8.5e-7 Torr.
Cooling down initiated at 1A/min.
Target container should be inspected once the chamber is vented.
|
|