  Evaporator_2, Page 19 of 35  Not logged in ELOG logo
ID Date Author Target Material Target Oven W.O#down Source Status Subject
  432   Thursday, March 07, 2019, 09:22 Darwin Ortiz RosalesEmpty40282-4TARGET BOATDoneTransfer tube TaC coating (Legnaro)

Thursday, March 07, 2019, 09:09

Transfer tube from Legnaro was coated with TaC.

The transfer tube was set in a tantalum boat and wrapped with 3 heat shields,

the legs of the transfer tube were let out of the shielding sheets.

Chamber pump down was started on Wednesday March 06, 2019.

Desired temperature TGHT = 1800 C, Omega slope set = 0.990.

IGP1= 4.48e-07 Torr

Will tap up TGHT manually to 40-50 A and monitor pressure.


 Thursday, March 07, 2019, 10:57

The TGHT current was left at 40 A for 50 min, the pressure achieved was 6.15e-7 Torr

The TGHT was rised to 45 A 11:00 am the pressure rised to 6.18e-7 Torr (11:10am)

The TGHT was rised to 50 A 11:10 am the pressure rised to 6.81e-7 Torr (11:32am)

auto ramp was set to 1 A/min to 300 A

Good vacuum 3e-5 Torr

Bad vaccum 5e-5 Torr

auto ramp was set to 1 A/min to 400 A

auto ramp was set to 1 A/min to 470 A

Final conditions TGHT = 485 A, 8.25V Temperature = 1800 C

The transfer tube stayed at 1800 C for 4 hours

auto ramp was set to -1 A/min to 0 A. 


Friday, March 08, 2019, 16:53 

EVAP2 was vented with air and the transfer tube was unloaded

  451   Wednesday, July 17, 2019, 11:13 Marla CervantesNb40282-4TARGET BOATDoneAnnealing of RRR-Nb test samples

 Wednesday, July 17, 2019, 10:57

Annealing of five RRR Nb samples following cold-working and resistance measurements.  Used to validate computational annealing model developed for SRF studies.  For more information contact Norman Muller, x6398.

Desired temperature 1025 C.

Five Nb samples wrapped with Nb foil were set on a tantalum boat (coated with TaC)

the tantalum boat was wrapped with two tantalum sheets.

The boat was installed in the EVAP2.

The initial vacuum was IGP1 = 1.26e-6 Torr.

Ramping rate 5 A/min to final current of 200 A.


Wednesday, July 17, 2019, 11:18 

At 155 A, the ramping rate was changed to 1 A/min 


Wednesday, July 17, 2019, 11:28 

The ramping was stopped at 167 A.


 Wednesday, July 17, 2019, 11:57

Conditions:

IGP1 = 1.65e-6 Torr


TGHT = 2.54 V, 174.46 A

Temperature ~ 950 C


Wednesday, July 17, 2019, 18:07

IGP1 = 1.16 e-6

TGHT = 3.18 V, 206.7 A

Temperature ~950 C

Cooling ramp 10 A/min 

 Vented with air


Suggestion for future annealing:

  Use tantalum boat without TaC coating.

  465   Monday, November 04, 2019, 14:25 Darwin Ortiz RosalesEndcaps40282-4TARGET BOATDone 

Monday, November 04, 2019, 14:19 

Each endcap is separated with a disc of graphite foil and rolled into packs one pack of 4 and one pack of 8 within a foil envelope in a target boat.

There are also 3 coated springs interspersed.

The boat is wrapped with 3-layers of Ta heatshields.

Chamber pumped down overnight.

OMEGA slope = 0.99

Will Tap TGHT up to 40 A then autoramp to 400A at 1A/min.

Final desired temperature on OMEGA (tap)= 1800C


 Tuesday, November 05, 2019, 11:30

IGP1 = 9.6e-7 Torr

Autoramp TGHT to 40A at 1A/min


Tuesday, November 05, 2019, 11:44

IGP1= 2.6e-06 Torr

TGHT = 40.8 A, 0.37V

Will leave at 40 A for 1 hour


 Tuesday, November 05, 2019, 12:39

 IGP1=2.5e-6 Torr

TGHT =40.0A, .33V

Start ramping TGHT to 400A at 0.1A/min


Wednesday, November 06, 2019, 09:32

IGP1=7.8e-7 Torr

TGHT = 168.4A, 2.38V

increase ramp speed to 1A/min


 Wednesday, November 06, 2019, 14:07

IGP1= 2.34e-6 Torr

TGHT=400.0 A, 6.98V

set TGHT autoramp to 460A @ 1A/min aiming for 1850C (see attached plot)

 


Wednesday, November 06, 2019, 15:18

OMEGA = 1776 C

TGHT = 460.0A, 8.52V

IGP1= 4.7e-6 Torr

Starting manual tap up to 1810C


Wednesday, November 06, 2019, 15:36

OMEGA=1810 C

TGHT = 468.8A, 8.74V

IGP1=4.14e-6


Wednesday, November 06, 2019, 19:04

OMEGA=1822 C (has been between 1817-1824 C over 3.5 hours )

TGHT=468.8A, 8.67V

IGP1=1.9498e-06 Torr

Start TGHT ramp down at -2A/min


Thursday, November 07, 2019, 09:55

THGT = 0A, 0V overnight

IGP1= 3.2 e-07 Torr

Proceeding with unloading.


End caps looked good for online use.

 

Attachment 1: Nov4CapCoating.PNG
Nov4CapCoating.PNG
  526   Monday, February 01, 2021, 13:57 Darwin Ortiz RosalesSiC40282-4TARGET BOATDoneSintering of SiC discs for SEM

Monday, February 01, 2021, 13:52  

Ta boat loaded with 20 Disc on either end capped with Ta springs to prevent overexpansion.   discs wrapped Graphite foil and boat wrapped in Ta heat-shields (3 layers).

Sample A on left side and sample B on right side.

Desired temperature= 1800C (expected TGHT 410 A).

good vacuum = 3.00 e-05 Torr

bad vacuum = 5.00 e-05 Torr

Evap2 left to pump down over night.


 Tuesday, February 02, 2021, 10:01

Pressure stable at IGP1= 7.8e-7 Torr

TGHT autoramp  set to 50 A @ 1/min


Tuesday, February 02, 2021, 13:45

IGP1=3.5e-6 Torr

TGHT =49.9 A, 0.56 V

Ramp at 1A/min to 100A


Wednesday, February 03, 2021, 08:25

IGP1= 5.5 e-07 Torr

TGHT = 100 A, , 1.2 V

Yesterday the camera failed to operate.  Cloud service discontinued.  The TS camera is offline but it is a different provider.  Will start ramping to 400A .

Ramp rate 2A/min


Wednesday, February 03, 2021, 15:55

ramped up to 520 A and 9.1V TGHT

Temperature average 1644 C but suspect actual temperature higher.

Held for 5 hours and started ramp down at -2A/min


Thursday, February 04, 2021, 9:35

IGP1= 2.99e-7 Torr

Begin pumpdown procedure and remove container

Note:  SiC evaporation on most discs.  The temperature was too high.  Need to repeat.

 

 

 

  118   Tuesday, February 18, 2014, 12:19 Laura LambertEmpty40282-3TARGET BOATDoneSintering Ta target boat with TaC coating

 Tuesday, February 18, 2014, 12:12

A new target boat was sprayed with TaC coating and let dry.
The target boat is NOT wrapped with Ta-heat shield.

Thermocouples have been attached to the target boat in order to monitor the internal temperature of the new target boat design. 

The boat was installed in Evap#2, chamber is currently being pumped down.


 Tuesday, February 18, 2014, 14:20

Chamber was pumped down this morning to 2.9e-6 Torr. HS cooling water valves were opened, no leaks detected.

TGHT was stepped up to 35A, voltage max set at 14V. TBHT currently at 0A.

Waited ~20min, current stabilized, vacuum started to drop, auto-ramp initiated at 0.2A/min and max setpoint to 700A.

Good vacuum: 3.00e-5 Torr; Bad vacuum: 4.00e-5 Torr.

Temperature reading on left: thermocouple touching edge of target boat; temperature reading on right: thermocouple floating in center of target boat.


 Wednesday, February 19, 2014, 09:11

TGHT has been slowly ramping up overnight at a rate of 0.2A/min

IGP1 = 3.9e-7 Torr, TGHT = 260A; stepping ramping rate up to 2.0A/min


 Wednesday, February 19, 2014, 15:25

IGP1 = 9.4e-7 Torr

Thermocouple T2 = 1267.8C

Internal temp measured with Mikron = 1600C

Increasing max setpoint to 720A due to previous not fully sintered new design of target boat.


 Thursday, February 20, 2014, 09:17

Thermocouple T2 = 1254.5C

Internal temp measured with Mikron = 1811C

IGP1 = 2.6e-7 Torr

Reached max setpoint yesterday evening.

Initiating auto-cooling at 2.0A/min.


 Friday, February 21, 2014, 10:47

Vented and opened chamber this morning.

Target boat not fully sintered. [see attached photos]

Close to a full sinter, and will re-sinter next week with endcaps, so will not re-sinter by itself.


 

Attachment 1: Photo_2-17-2014_3_54_11_PM.jpg
Photo_2-17-2014_3_54_11_PM.jpg
Attachment 2: IMG_20140221_102415969.jpg
IMG_20140221_102415969.jpg
Attachment 3: IMG_20140221_102337054.jpg
IMG_20140221_102337054.jpg
  119   Tuesday, February 25, 2014, 16:10 Laura Lambert 40282-3TARGET BOATDoneSintering TaC coated end caps

 Tuesday, February 25, 2014, 16:08

The target containers end-caps were coated with TaC spray and let dry.

The caps are inserted in the target boat vertically with no heat shield and no graphite foil. [see attached photo]

The chamber is currently being pumped down overnight.


 Wednesday, February 26, 2014, 09:54

Chamber was pumped down overnight to 4.2e-7 Torr.

HS cooling water valves opened; no leaks detected.

TGHT was stepped up to 35A, voltage max set at 14V. TBHT currently at 0A.

Waited ~20min, current stabilized, vacuum started to drop, auto-ramp initiated at 0.2A/min and max setpoint to 700A.

Will ramp up to 700A rather than the usual 580A due to last round of endcaps not fully sintering at 580A with new target boat design.

Good vacuum: 3.00e-5 Torr; Bad vacuum: 4.00e-5 Torr.


 Thursday, February 27, 2014, 09:38

TGHT has been slowly ramping up overnight at a rate of 0.2A/min.

IGP1 = 2.8e-7 Torr; TGHT = 311A, 4.3V

Stepping ramping rate up to 2.0A/min.


 Friday, February 28, 2014, 08:53

TGHT reached max setpoint of 700A yesterday evening.

Internal temp measured with Mikron = 1700C

IGP1 = 3e-7 Torr 

Power = 12.95V

Initiating auto-cooling at 2.0A/min.


 Monday, March 03, 2014, 11:46

Vented and opened chamber this morning.

End caps not fully sintered! 

See attached photo comparison of fully sintered [grey], partially sintered from this round [light green] and pre-sinter [dark green].

Will not bother re-sintering, as partial sinter is enough.


 

Attachment 1: feb25-2014
Attachment 2: march3-2014(4).jpg
march3-2014(4).jpg
  121   Friday, March 07, 2014, 11:46 Laura Lambert 40282-3TARGET BOATIn progressSintering TaC coated end caps

 Friday, March 07, 2014, 11:41

The target container end-caps were sintered previously, but did not fully complete the sintering process [See elog entry # 119 EVAP2]

The caps are inserted in the target boat wrapped in graphite foils with 3 x Ta-heat shields.

The chamber was pumped down overnight.

IGP1 = 2e-7 Torr

HS cooling water valves were opened; no leaks detected.

TGHT was stepped up to 35A, voltage max set at 9.05V. TBHT currently at 0A.


 Friday, March 07, 2014, 11:52

Waited ~20min, current stabilized, vacuum started to drop, auto-ramp initiated at 0.5A/min and max setpoint to 500A.

Will ramp to 500A due to last failed round of end caps breaking with 3-ta heat shields at 580A.

Good vacuum: 3.00e-5 Torr; Bad vacuum: 4.00e-5 Torr.


 Friday, March 07, 2014, 13:21

IGP1 = 8e-7 Torr.

TGHT = 72A

Vacuum stable; therefore, increasing ramping rate up to 1.0A/min


 Friday, March 07, 2014, 14:20

IGP1 = 9.8e-7 Torr

TGHT = 130A

Vacuum stable; therefore, increasing ramping rate up to 2.0A/min


 

  122   Friday, March 07, 2014, 22:25 John Wong 40282-3TARGET BOATProblemsSintering TaC coated end caps

Laura Lambert wrote:

 Friday, March 07, 2014, 11:41

The target container end-caps were sintered previously, but did not fully complete the sintering process [See elog entry # 119 EVAP2]

The caps are inserted in the target boat wrapped in graphite foils with 3 x Ta-heat shields.

The chamber was pumped down overnight.

IGP1 = 2e-7 Torr

HS cooling water valves were opened; no leaks detected.

TGHT was stepped up to 35A, voltage max set at 9.05V. TBHT currently at 0A.


 Friday, March 07, 2014, 11:52

Waited ~20min, current stabilized, vacuum started to drop, auto-ramp initiated at 0.5A/min and max setpoint to 500A.

Will ramp to 500A due to last failed round of end caps breaking with 3-ta heat shields at 580A.

Good vacuum: 3.00e-5 Torr; Bad vacuum: 4.00e-5 Torr.


 Friday, March 07, 2014, 13:21

IGP1 = 8e-7 Torr.

TGHT = 72A

Vacuum stable; therefore, increasing ramping rate up to 1.0A/min


 Friday, March 07, 2014, 14:20

IGP1 = 9.8e-7 Torr

TGHT = 130A

Vacuum stable; therefore, increasing ramping rate up to 2.0A/min


 

Friday, March 07, 2014, 22:22  

Target current was at 500A before it tripped off on the chiller.   Tried to reset the chiller but to no avail.  Don't know what is going on yet. 

The TGHT/TBHT cooling water is still on, and this should OK while the HOT target boat is cooling down at the moment. 

Will leave it for now and further investigate on Monday



 

  143   Wednesday, July 23, 2014, 15:07 John WongEmpty40282-3LP-SISIn progressSintering TaC coated target container

Wednesday, July 23, 2014, 15:07

Target container is coated with TaC.  No Ta-heat shields are used.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 0.2A/min.

Chamber is currently being pumped down


 Wednesday, July 23, 2014, 17:40

Vacuum came down to mid 10-6 Torr.

Stepped up TGHT and TBHT to 30A - IG1 @ 1.4e-5 Torr.

Initiated auto-ramping.


 Thursday, July 24, 2014, 17:19

TGHT and TBHT have reached to 100A, and vacuum is coming down to 1.4e-6 Torr.

Increase ramping rate, TGHT to 1A/min, TBHT 0.5A/min.


 Friday, July 25, 2014, 11:26

Target container temperature reaches ~1550C at 580A on TGHT and 230A TBHT, and it has been heated for ~10 hrs.

Auto-cooling initiated at 2A/min.


 

  144   Monday, July 28, 2014, 10:52 Laura LambertEmpty40282-3LP-SISDoneSintering TaC coated target container

John Wong wrote:

Wednesday, July 23, 2014, 15:07

Target container is coated with TaC.  No Ta-heat shields are used.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 0.2A/min.

Chamber is currently being pumped down


 Wednesday, July 23, 2014, 17:40

Vacuum came down to mid 10-6 Torr.

Stepped up TGHT and TBHT to 30A - IG1 @ 1.4e-5 Torr.

Initiated auto-ramping.


 Thursday, July 24, 2014, 17:19

TGHT and TBHT have reached to 100A, and vacuum is coming down to 1.4e-6 Torr.

Increase ramping rate, TGHT to 1A/min, TBHT 0.5A/min.


 Friday, July 25, 2014, 11:26

Target container temperature reaches ~1550C at 580A on TGHT and 230A TBHT, and it has been heated for ~10 hrs.

Auto-cooling initiated at 2A/min.


 

 Monday, July 28, 2014, 10:50

vented in air and opened this morning. successful run


 

  145   Monday, July 28, 2014, 15:06 Laura Lambert 40282-3LP-SISIn progressSintering ZrC# 6 target

 Monday, July 28, 2014, 14:41

Total number of foils: 445 discs

Total mass of materials [incl graphite foils]: 49.027 g

Total length packed: 11.2 cm

Container has no Ta heat shields.

Currently being pumped down.


 

  146   Tuesday, July 29, 2014, 11:23 John Wong 40282-3LP-SISIn progressSintering ZrC# 6 target

Laura Lambert wrote:

 Monday, July 28, 2014, 14:41

Total number of foils: 445 discs

Total mass of materials [incl graphite foils]: 49.027 g

Total length packed: 11.2 cm

Container has no Ta heat shields.

Currently being pumped down.


 

 Tuesday, July 29, 2014, 11:19

Chamber was pumped down overnight to ~5.5e-7 torr.

HS water valve opened; no leaks were detected.

Stepped up TGHT/TBHT to 40A. IG went up 8e-6 Torr and stabilized. 

Initiated auto-ramping TGHT @ 580A, TBHt @ 230A at 0.2A/min


 

  147   Friday, August 01, 2014, 11:47 Peter Kunz  40282-3LP-SISIn progressZrC #6 conditioning

The maximum current of 580A was reached at 9:15.

TGHT:RDCUR 578 A

TGHT:RDVOL 9.87 V

IGP1:RDVAC 3.8e-6

The temperature was measured with the Minolta 2-color pyrometer:

from the side - inside target container : ~1200 deg C

from the front trough hole in the heat shield : ~1800 deg C

 

  148   Friday, August 01, 2014, 13:27 Peter Kunz  40282-3LP-SISIn progressZrC #6 conditioning

Target was conditioned for 4 hours at 580A.

Initiating ramp-down sequence @ 2A/min

 

Attachment 1: zrc6_conditioning.png
zrc6_conditioning.png
  149   Tuesday, August 05, 2014, 12:01 Laura Lambert 40282-3LP-SISDoneZrC #6 conditioning

Peter Kunz wrote:

Target was conditioned for 4 hours at 580A.

Initiating ramp-down sequence @ 2A/min

 

 Tuesday, August 05, 2014, 12:00

target vented in air and taken out this morning


 

  155   Thursday, September 11, 2014, 14:23 Laura Lambert 40282-3TARGET BOATFailedSintering TaC coated end caps

 Thursday, September 11, 2014, 13:14

The target container end caps were coated with TaC spray and let dry.

The caps are inserted in the target boat wrapped in graphite foil with 3 x Ta-heat shields.

The chamber is currently pumping down.


 Friday, September 12, 2014, 14:17

Chamber was pumped down overnight.

HS cooling water valves opened, no leaks detected.

IGP1 = 7.2e-7 Torr.

TGHT stepped up to 35A, TBHT at 0A.

Waited ~30min, current stabilized, vacuum started to drop, auto-ramp initiated at 0.2A/min.

Will ramp TGHT to 580A with a max 10V.

Good vacuum: 3.00e-5 Torr; Bad vacuum: 4.00e-5 Torr.


 Monday, September 15, 2014, 11:31

TGHT stopped at 500A due to not high enough voltage max.

Increased max voltage to 12V


 Monday, September 15, 2014, 14:17

IGP1 = 6.3e-7 Torr

Increasing ramping rate to 1.0A/min


 Tuesday, September 16, 2014, 09:04

TGHT reached 577A and finished auto-ramping, then proceeded to drop down to 560A overnight.

Increased max voltage to 13.05A and TGHT to 580A.


 Tuesday, September 16, 2014, 13:52

TGHT reached 580A and sat there for ~5hrs.

IGP1 = 6.1e-7 Torr.

Initiating auto-cool at 2.0A/min.


 Wednesday, September 17, 2014, 13:03

Vented in air.

Opened up....looked 'deceivingly' ok.

then i took a layer of Ta off....grrrr  

the 1st layer of Ta was holding the boat together. as soon as that layer was taken off the target boat broke.

see attached photos.


 

Attachment 1: IMG_20140917_142605683.jpg
IMG_20140917_142605683.jpg
Attachment 2: IMG_20140917_143120141.jpg
IMG_20140917_143120141.jpg
Attachment 3: IMG_20140917_143343399_HDR.jpg
IMG_20140917_143343399_HDR.jpg
Attachment 4: Capture.JPG
Capture.JPG
Attachment 5: Capture2.JPG
Capture2.JPG
  293   Wednesday, May 04, 2016, 13:45 Laura Lambert 40282-3TARGET BOATIn progressConditioning Nb samples for Tobias

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

Attachment 1: Nb_samples_in_boat_(2).jpg
Nb_samples_in_boat_(2).jpg
  294   Monday, May 09, 2016, 18:19 John Wong 40282-3TARGET BOATIn progressConditioning Nb samples for Tobias

Laura Lambert wrote:

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

 Monday, May 09, 2016, 18:18

TGHT at 341A/5.34V for over 4 hours.  Vac stables at 1.78e-7 Torr.

Cooling down at 2A/min


 

  295   Tuesday, May 10, 2016, 11:57 Laura Lambert 40282-3TARGET BOATDoneConditioning Nb samples for Tobias

John Wong wrote:

Laura Lambert wrote:

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

 Monday, May 09, 2016, 18:18

TGHT at 341A/5.34V for over 4 hours.  Vac stables at 1.78e-7 Torr.

Cooling down at 2A/min


 

 Tuesday, May 10, 2016, 08:45

Vented in air and opened up this morning.

Samples look good!


 

  339   Tuesday, November 22, 2016, 15:58 Laura LambertNb40282-3TARGET BOATDoneConditioning Nb samples for Doug

Tuesday, November 22, 2016, 15:53

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Niobium samples are placed in slots, holding in place, to avoid warping.

Smaller samples closest to MIKRON IR reading [left side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 today.

Pumping down now...


 Wednesday, November 23, 2016, 11:45

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 6.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to max setpoint of 250A.

Will tap up manually to final desired temperature of 1400C.


 Wednesday, November 23, 2016, 13:17

IGP1 = 5.9e-7

TGHT = 66A, 0.51V

Vacuum stable.

Increasing ramping rate to 1.0A/min


 Thursday, November 24, 2016, 08:46

IGP1 = 3.9e-7 Torr

TGHT = 250A, 3.41V      *NOTE: the current set reads 243.8A but the readout is 250A

OMEGA = 1013C

MIKRON has no reading yet

Tapping up manually to 1400C


 Thursday, November 24, 2016, 15:42

Samples have remained at ~1400C for 5hrs.

IGP1 = 5.8e-7 Torr

TGHT = 420A, 6.5V

OMEGA = 1410C

MIKRON = 1420C

Initiating auto-cool at 2.0A/min


 Friday, November 25, 2016, 11:39

Vented in air and opened up this morning.

Samples look good!


 

Attachment 1: samples.jpg
samples.jpg
Attachment 2: evap2.jpg
evap2.jpg
Attachment 3: heating_up.xlsx
Attachment 4: visual_of_MIKRON_pointing_at_samples.JPG
visual_of_MIKRON_pointing_at_samples.JPG
ELOG V2.9.2-2455