ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
Text |
|
|
269
|
Tuesday, March 30, 2021, 16:04 |
Marla Cervantes | UO2/C | P2N-02 | | Done | P2N-3 carbothermal reduction | Green
target material characteristics (elog |
|
|
270
|
Thursday, April 15, 2021, 15:01 |
Marla Cervantes | | | | | IGP1 patch | Thursday, March 31, 2021, 14:42
EVAP1's TGHT has |
|
|
271
|
Saturday, June 05, 2021, 09:14 |
Marla Cervantes | UC2 | | TARGET BOAT | In progress | UCx#33 Conditioning | Saturday, June 05, 2021, 08:57
Target #33 was installed in |
|
|
274
|
Wednesday, September 15, 2021, 07:19 |
Marla Cervantes | UC2 | | TARGET BOAT | Done | Conditioning 2sc samples | Wednesday, September 14, 2021, 21:14
Boat is wrapped with 2 layers |
|
|
44
|
Monday, November 14, 2011, 11:56 |
Peter Kunz | UC2 | 38634-10 | LP-SIS | Done | UCx03: Conditioning up to 175A | Evaporator was cleaned Nov 11 from after
target was conditioned up to 175A. There
was significant condensation of oily fluid |
|
|
58
|
Monday, September 03, 2012, 02:56 |
Peter Kunz | UC2 | 39165-5 | LP-SIS | In progress | Conditioning UCx05 | Organic/volatile burnoff complete at TGHT
= 190A. Rampdown initiated. |
|
|
59
|
Tuesday, September 04, 2012, 17:26 |
Peter Kunz | UC2 | 39165-5 | LP-SIS | In progress | Conditioning UCx05 | Organic gunk cleaned out. Beginning 2nd phase
of conditioning. |
|
|
60
|
Friday, September 07, 2012, 17:21 |
Peter Kunz | UC2 | 39165-5 | LP-SIS | In progress | Conditioning UCx05 | Target 6h at 520A. IEVAP:IG1 8.4e-6 Torr.
Cool down sequence initiated. |
|
|
61
|
Monday, September 10, 2012, 11:00 |
Peter Kunz | UC2 | 39165-5 | LP-SIS | In progress | Conditioning UCx05 | Plot of conditioning run: IEVAP:IG1, TGHT |
|
|
70
|
Tuesday, July 02, 2013, 11:13 |
Peter Kunz | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) |
1. stage - burning off organics complete
2. stage - carbonization began 1-8 |
|