  291   Tuesday, April 09, 2024, 14:43 Darwin Ortiz RosalesUO2 LP TUBEIn progressUCx240408 reductionTuesday, April 09, 2024, 14:42
Cartridge #16 loaded with 213 plus
3 analysi discs
  
  290   Wednesday, October 11, 2023, 10:06 Darwin Ortiz RosalesUO2/C LP TUBEDoneTUCx-231005 reduction & conditioningWednesday, October 11, 2023, 9:36
Cartridge #10 loaded with 213 plus
3 analysi discs
  
  289   Wednesday, March 22, 2023, 22:29 Darwin Ortiz RosalesUO2/C LP TUBEDone230316 ReductionWednesday, March 22, 2023, 22:29
Cartridge #9 loaded with 213 plus
3 analysi discs
  
  288   Thursday, January 19, 2023, 10:02 Darwin Ortiz RosalesUO2/C LP TUBEDoneC230105 ReductionThursday, January 19, 2023, 09:57
Cartridge #8 loaded with 198 discs
To be reduced inside a Ta container
  
  287   Monday, December 19, 2022, 10:45 Darwin Ortiz RosalesUO2/C LP TUBEDoneC-221207 ReductionMonday, December 19, 2022, 10:38
Cartridge with 175 discs (including
5 analysis discs) loaded into a graphite
  
  286   Monday, November 28, 2022, 05:59 Darwin Ortiz RosalesUO2/C LP-SISDoneC221125experimentMonday, November 28, 2022, 05:58
Left weekend to pump down
current IGPI= 7.23e-7 Torr
 Data_summary.png 
  285   Wednesday, October 19, 2022, 12:28 Darwin Ortiz RosalesUC240253-5LP TUBEDoneC-220510 further conditioningWednesday, October 19, 2022, 10:27
Cartridge-220510Cx was installed
  
  284   Friday, October 07, 2022, 08:14 Darwin Ortiz RosalesUO2/C LP-SISDoneC-220928UCx conditioning experimentsFriday, October 07, 2022, 07:55
Cartridge-220928UCx was installed
 Cap_1_221011.pngCap_2.pngcap3.png 
  283   Tuesday, June 07, 2022, 07:09 Darwin Ortiz RosalesUO2/CTarget Boat DoneUO2 reduction ID C220510-1Tuesday, June 07, 2022, 07:05
A loaded graphite cartridge
  
  282   Friday, June 03, 2022, 06:21 Darwin Ortiz RosalesUO2/C42218-4LP-IG-LISDoneUCx#39 reduction
Friday, June 03, 2022, 06:24
  
  281   Wednesday, June 01, 2022, 08:42 Darwin Ortiz RosalesUO2/CTarget Boat DoneUO2 reduction Provisional ID C211209-1 Wednesday, June 01, 2022, 08:39
A loaded graphite cartridge
  
  280   Wednesday, May 04, 2022, 09:47 Luca EgoritiUC2 P2N-SISDoneP2N carbothermal reduction P2NC220408 Wednesday, May 04, 2022, 09:42
Yesterday, a second graphite cartridge
was installed in EVAP1, it consists of the
  
  279   Wednesday, April 13, 2022, 10:55 Luca EgoritiUC2 P2N-SISDoneP2N carbothermal reduction P2Ncartridge-220323Wednesday, April 13, 2022, 10:50
P2NC-220323
Preparing the P2N-UCx for online
  
  278   Wednesday, November 24, 2021, 10:38 Luca EgoritiTa  In progressIPF release testsWednesday, November 24, 2021, 10:38
A first, short "FullTa1"
target was loaded into the evap1. It consists
  
  277   Friday, November 05, 2021, 13:38 Luca EgoritiTa LP-SISIn progressFull target release test 2 Friday, November 05, 2021, 13:23
Full target loaded with ~500
 Ta-ReleaseTest-2_low-current.JPG 
  276   Friday, September 24, 2021, 15:40 Luca EgoritiTa LP-SISIn progressFull target release test 1 Friday, September 24, 2021, 15:38
Full target loaded with ~500 non-active
foils plus 4 active foils.  
  
  275   Thursday, September 23, 2021, 07:03 Darwin Ortiz RosalesUO2/C TARGET BOATDoneUCx#35 C reduction Thursday, September 23, 2021, 06:55
A loaded graphite cartridge
  
  274   Wednesday, September 15, 2021, 07:19 Marla CervantesUC2 TARGET BOATDoneConditioning 2sc samplesWednesday, September 14, 2021, 21:14
Boat is wrapped with 2 layers
  
  273   Wednesday, July 07, 2021, 12:40 Darwin Ortiz RosalesUO2/C TARGET BOATDoneUCx Provisional ID= 200229 conditioning Wednesday, July 07, 2021, 14:39
Target Provisional ID = 200929
  
  272   Wednesday, June 30, 2021, 13:35 Darwin Ortiz RosalesUO2/C TARGET BOATDoneUCx#34 conditioningTarget
#34 was installed in the EVAP1 and pumped
down (Tuesday June 29, 2021).
  