373
|
Thu Dec 2 10:02:46 2010 |
Damien Gallop | | | 12C2+ for Commissioning | Accelerator development continues. Save:
101201_2157.snaiosvault. Today's agenda:
emittance scans. Attached: overnight beam |
14x |
|
372
|
Wed Dec 1 08:51:54 2010 |
Damien Gallop | | | 12C2+ for Commissioning | Continuing from Supernanogan. Source touch-up
last evening. |
|
|
371
|
Tue Nov 30 08:47:47 2010 |
Damien Gallop | | | 12C2+ for Commissioning | Commissioning and development
continue. |
|
|
370
|
Mon Nov 29 08:55:35 2010 |
Damien Gallop | | | 12C2+ for Commissioning | Supernanogan is online. MCIS:TP3 is off.
It should be on. It is required for best
production of higher charge states. |
|
|
369
|
Thu Nov 25 11:50:14 2010 |
Damien Gallop | | | 12C2+ for Commissioning | Some start-up teething pains last night.
Decision: Go with the Supernanogan for now.
~20enA on FC6. Save: 101125_1148.snapiosdragon. |
|
|
368
|
Wed Nov 24 17:08:41 2010 |
Damien Gallop | | | 12C2+ for SEBT Commissioning | Source switchover began at ~15:00. |
|
|
367
|
Wed Nov 24 14:02:14 2010 |
Damien Gallop | | | 85Rb for TITAN | Last day of 85Rb delivery. Save: 101124_1400_snapiostitan.
Next up: 12C2+ for SEBT commissioning. We
took a few minutes earlier |
|
|
366
|
Tue Nov 23 10:31:27 2010 |
Damien Gallop | | | 85Rb for TITAN | We are back to running a Rb beam using
the MWS. The run started last Thursday, November
18th. The previous Rb run ended on Monday, |
|
|
365
|
Wed Nov 10 09:18:31 2010 |
Damien Gallop | | | 12C2+ for DRAGON | 12C2+ beam established yesterday from the
Supernanogan. Tuning to DRAGON began last
evening and is continuing presently. |
|
|
364
|
Tue Nov 9 08:42:38 2010 |
Damien Gallop | | | 12C2+ for DRAGON | A good 12C2+ beam was established yesterday
from the Supernanogan source, driven by background
pressure only; no source gas actively injected. |
|
|
363
|
Mon Nov 8 09:37:03 2010 |
Damien Gallop | | | 12C2+ for DRAGON | The 85/87Rb run from the MWS ended last
evening as scheduled. The Supernanogan source
was brought online (~21:30 Sunday?) and a |
|
|
362
|
Fri Nov 5 09:23:53 2010 |
Damien Gallop | | | 85Rb for Polarizer | Beam was used yesterday. Mostly idle overnight.
Looks like a plasma mode change happened
at around 19:00 yesterday. It happens. Or |
|
|
361
|
Thu Nov 4 09:18:15 2010 |
Damien Gallop | | | 85Rb for Polarizer | Source ran nicely overnight. ICR team set
up a tune into the Polarizer line. Experiment
setup is scheduled to start tomorrow morning. |
|
|
360
|
Wed Nov 3 09:22:38 2010 |
Damien Gallop | | | 85Rb for Polarizer | Yesterday we handed over a 85Rb beam to
ICR. It will be used for a LEBT run using
the Polarizer line. Beam stayed on FC6 overnight. |
|
|
359
|
Tue Nov 2 09:25:30 2010 |
Damien Gallop | | | MWS Development | 85Rb on FC6 overnight. After restarting
the source yesterday following development,
the beam intensity came back, but it's slightly |
|
|
358
|
Mon Nov 1 09:30:15 2010 |
Damien Gallop | | | MWS Development | The source stayed up steadily over the
weekend, with 85Rb on FC6. Not a lot of current,
but pretty good for a first pass. More development |
|
|
357
|
Fri Oct 29 09:41:20 2010 |
Damien Gallop | | | MWS Development | MWS source switchover yesterday was successful.
Leakchecking went well. A small leak on the
intermediate section sealed with a snug on |
6x |
|
356
|
Thu Oct 28 17:51:49 2010 |
Damien Gallop | | | MWS switchover for scheduled 85/87Rb beams | A controls issue with IOS:BIAS was found
yesterday. Controls people resolved it today.
MWS source was switched over and prepared |
|
|
355
|
Thu Oct 28 17:51:49 2010 |
Damien Gallop | | | MWS switchover for scheduled 85/87Rb beams | A controls issue with IOS:BIAS was found
yesterday. Controls people resolved it today.
MWS source was switched over and prepared |
|
|
354
|
Wed Oct 27 09:21:59 2010 |
Damien Gallop | | | 26Mg6+ for TIGRESS EOB | The experiment ran overnight, smoothly,
by the looks of it. Beam is on FC6 now, so
they're likely done. EOB studies on Mg beam |
16x |