  243   Tue Apr 13 10:20:27 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningAccelerator commissioning has resumed for
the day. Beam was nice and stable overnight.
See attached Stripchart.
 Picture_3.png 
  244   Wed Apr 14 17:28:32 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningBeam reserved for continuing accelerator
development, but there are some ISAC-I RF
phase troubles. However, maintenance was
  
  245   Thu Apr 15 09:39:11 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningYesterday's RF troubles in ISAC-I are reportedly
solved. Beam development is expected to resume
this morning.
  
  246   Fri Apr 16 09:26:01 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningBeam development through accelerators continues
today. Beam was rock-stable overnight.
 grab.Ft9922.png 
  247   Mon Apr 19 10:11:17 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningDevelopment on Friday; idle over the weekend.
Stripchart attached.
Meanwhile, there was a power bump
 Picture_1.pnggrab.a19570.png 
  250   Wed Apr 21 15:30:09 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningBeam up as of last evening. Controls performed
some network upgrades today, which impacted
beam operations. One glitch on our side:
 Picture_8.png 
  251   Thu Apr 22 14:57:25 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningAccelerator development continued this
morning. Beam from source was reported to
be "good". ICR showed me their
  
  252   Fri Apr 23 10:18:32 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningMarco and experimenters are busy at it,
tuning the DTL. Regarding the source, he
is "happy as always!" Well, that
 Picture_4.png 
  309   Thu Jul 8 09:38:36 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningBeam idle overnight. Source conditioned
and changed a bit. Slight tweaking required
to bring it back to stable.
 Picture_5.png 
  310   Fri Jul 9 10:00:03 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningSource drifted overnight. Operators made
a slight correction to silence an alarm.
I have tweaked this up. Shown below are before
 8x 
  311   Mon Jul 12 10:55:14 2010 Damien Gallop  16O1+ at 32.64keV for accelerator commissioningBeam used sporadically over the weekend.
Note temperature response in beam. A power
bump occurred at about 10:00, knocking out
 Picture_1.png 
  253   Mon Apr 26 10:58:46 2010 Damien Gallop  16O1+ at 32.64keV to SEBT2Our first experiment of the year started
right around midnight last night, after extensive
tuning. As I understand it, S1151
 Picture_1.png 
  254   Tue Apr 27 09:04:13 2010 Damien Gallop  16O1+ at 32.64keV to SEBT2Nominal beam operation to SEBT2 overnight.
A chart of beam over the last few days is
attached. There is a step change in the separator
 Picture_1.pngPicture_3.pnggrab.NQ9764.png 
  255   Wed Apr 28 10:08:05 2010 Damien Gallop  16O1+ at 32.64keV to SEBT2Beam delivery continued nicely through
the night.
Yesterday Controls repaired and reinstalled
 Picture_4.png 
  256   Thu Apr 29 09:11:27 2010 Damien Gallop  16O1+ at 32.64keV to SEBT2Another quiet night of beam to S1151.  Picture_5.png 
  257   Fri Apr 30 12:58:21 2010 Damien Gallop  16O1+ at 32.64keV to SEBT2Delivery to S1151 went quietly overnight
for their last few hours. The run ended at
~08:30 as scheduled. Marco and ICR did some
 grab.s30283.pnggrab.Y30291.pnggrab.z30299.png 
  308   Wed Jul 7 15:21:36 2010 Damien Gallop  16O1+ for SCC CommissioningA 16O1+ beam from the MWS is being used
for SCC development and commissioning by
agreement. Some sideshows getting there.
  
  96   Thu Jul 16 17:05:29 2009 Damien Gallop  16O1+ surveyA/q = 16 Field = 1873.4G FC6 = 204enA  grab.o17385.pnggrab.G17390.pnggrab.B17394.png 
  37   Tue Jun 30 10:56:26 2009 Damien GallopRoutineGeneral16O2+ emittance scansThe first emittance scan sort of got interrupted;
it auto-restarted just before the previous
scan had finished. I thought the resulting
 6x 
  38   Tue Jun 30 17:16:25 2009 Damien GallopRoutineGeneral16O2+ emittance scans with slits openFirst, with upstream slits opened, then
with both open. Original slit setting was
1mm. Finally, restore slits to 1mm and see
 6x 