  461   Wed Nov 2 10:16:49 2011 Damien Gallop  OLIS ShutdownMCIS pumpdown continues well. IOS optics
coming along. DB3 installed last night and
IOS is under vacuum very early. DB1/2 optics
 Picture_21.png 
  462   Thu Nov 3 09:50:05 2011 Damien Gallop  OLIS ShutdownMCIS pumped well overnight. Source development
imminent.
Later... possible IOS intervention.
 Picture_21.png 
  463   Fri Nov 4 09:41:32 2011 Damien Gallop  OLIS ShutdownMCIS continues to pump well. IOS DB assembly
planned for today.
Later... DB assembly complete and
 Picture_22.png 
  464   Mon Nov 7 09:58:17 2011 Damien Gallop  OLIS ShutdownIOS pumped well over the weekend. Present
pressure is 1.5e-7. MCIS pumps off
for setup.
 Picture_2.pngPicture_1.png 
  465   Tue Nov 8 10:02:54 2011 Damien Gallop  OLIS ShutdownSupernanogan is online with 36Ar+7 on FC6
overnight. Looks good. Note: The source gas
arrangement (enriched 36Ar) utilizes double
 Picture_3.pngPicture_4.pngPicture_5.pngPicture_7.pngPicture_6.png 
  466   Wed Nov 9 11:40:35 2011 Damien Gallop  OLIS ShutdownSupernanogan 36Ar+7 source development
in progress. RF frequency scans are the agenda
for today.
 Picture_8.pngPicture_9.png 
  467   Thu Nov 10 09:57:57 2011 Damien Gallop  OLIS ShutdownSupernanogan on overnight with 36Ar+7 on
FC6. Nice.
Today is the last day of scheduled
 Picture_3.png 
  468   Wed May 23 17:11:57 2012 Keerthi Jayamanna  Changed beam to 12C++ beamRemoved titanium from the back plate and
clean the source.
But left the PE titanium insert since
  
  469   Sun Dec 2 22:32:19 2012 Keerthi JayamannaRoutineGeneralStill cannot write anything other than Subject    
  470   Sun Dec 2 22:34:09 2012 Keerthi Jayamanna  Just finished 136Xe+25. ISAC reached 1GeV yesterday using OLIS Xe beam    
  471   Sun Dec 2 23:36:13 2012 Keerthi JayamannaRoutineGeneral16O+2 is ready for tuning.MCIS finished xenon development. MCIS is off
and isolation valve is shut.
A new oxygen gas line is installed to microwave
  
  472   Fri Dec 14 17:30:47 2012 Keerthi Jayamanna  18OH2 and 40Ar+2 delivaryDuring the last week we delivered 18O+2
from microwave ion source to Ritu.
Over the week end changed to 40Ar+2.
  
  473   Mon Dec 17 14:08:52 2012 Keerthi Jayamanna  IRIS beam delivary is completedIRIS beam delivery is completed with extra
3 days of beam providing to them.
18O2 and 40Ar+2 were delivered with
  
  474   Mon Dec 17 14:10:22 2012 Keerthi Jayamanna  Gas flow controller faultControls group may need some assistance
from OLIS group in order to trouble shoot
the problem.
  
  475   Wed Jan 22 10:34:58 2014 Raymond Dubé  IN-line 100K for IOS:YCB1A removedLast January 17th 2014 we removed an in-line
resistor (100K 10W) from IOS:YCB1A because
we do not think that it is needed.
  
  476   Thu Jan 23 12:56:14 2014 Raymond Dubé  New & updated drawings for S.S.I updated
an old drawing ISK4478D (MS & MCIS Optics)
and created 2 new ones: ISK4583D (Electrical
 ISK4478D-rev5.pdfISK4585D-rev2.pdfISK4583D-rev5.pdf 
  477   Fri Jan 24 09:15:10 2014 Raymond Dubé  New ISK4586D for OLIS with 3 Ion SourceI created
a new drawing: ISK4586D that shows the Optics
for OLIS with 3 Ion Source.
 ISK4586D-rev1.pdf 
  478   Wed Jan 29 12:27:57 2014 Raymond Dubé  OLIS Skimmers BOP & LabelsI updated
2 drawings that show the OLIS skimmers.
A. 
 isk4363d-rev4.pdfisk4365d-rev2.pdf 
  479   Fri May 16 08:44:27 2014 Raymond DubéRoutineGeneralOLIS work next weekAttached
is the scheduled work for OLIS next week.
 OLIS-Work-05.pdf 
  480   Wed Aug 13 15:00:27 2014 Raymond DubéRoutineGeneralOLIS Surface Source broken Ionizer CoilWe spent
most of the day looking at OLIS to find out
why the "Ionizer Coil" keeps breaking
 ISK4386D-rev5.pdfISK4583D-rev7.pdfISK4584D-rev1.pdfPE-R5-FAN_ON.jpg 