193
|
Thu Nov 26 06:20:21 2009 |
Keerthi Jayamanna | | | Supernanogan Development | Swiched off all the pumps and ion gauge
for oven installation.
|
|
192
|
Tue Nov 24 13:55:55 2009 |
Damien Gallop | | | OLIS development for CUSP source - installation cont'd | Keerthi found and fixed a couple more vacuum
leaks last night. Present vacuum at IOS:IG1
= 4.4e-7 Torr. Electrical and water services |
|
191
|
Mon Nov 23 10:32:34 2009 |
Damien Gallop | | | OLIS development for CUSP source - installation cont'd | 4He2+ "alpha" CUSP source under
vacuum: IOS:IG1=7.3e-7 Torr. Electrical installations
today. |
|
190
|
Fri Nov 20 17:26:57 2009 |
Damien Gallop | | | OLIS development for CUSP source - installation | Today we installed the CUSP "alpha"
source on the MWS port at OLIS. It is vacuum-tight.
Looking good. Also we installed remaining |
|
189
|
Thu Nov 19 11:14:19 2009 |
Damien Gallop | | | OLIS development for CUSP source | Pumps were switched off last night. IOS
was vented to Ar and swiped clean this morning.
MCIS ready for disembarking from F-cage. |
|
188
|
Wed Nov 18 23:46:14 2009 |
Keerthi Jayamanna | | | OLIS development started | All turbos in the OLIS and MCIS are off.
No controls for the MCIS. Pumps switched
of by pulling the CG cable. |
|
187
|
Tue Nov 17 09:18:37 2009 |
Damien Gallop | | | 21Ne4+ to DRAGON for charge distribution studies | After their EOB with 17O3+ yesterday, DRAGON
switched to 21Ne4+ running for charge distribution
studies. Keerthi changed over the source |
   |
186
|
Mon Nov 16 10:00:41 2009 |
Damien Gallop | | | 17O3+ beam to DRAGON end of run this morning | DRAGON declared EOB at around 08:00 today.
Source and beam were switched to 21Ne4+ for
calibration studies. |
|
185
|
Fri Nov 13 10:26:07 2009 |
Damien Gallop | | | 17O3+ beam to DRAGON continuing | Beam and energy changes continued over
the weekend. The ICR reports that things
are going swimmingly, and that the users |
 |
184
|
Tue Nov 10 09:36:39 2009 |
Damien Gallop | | | 17O3+ beam to DRAGON continuing | Beam ran well overnight. Last evening Vacuum
Group diagnosed and repaired a catastrophic
leak in the ILT cross region. You can see |
|
183
|
Mon Nov 9 09:30:10 2009 |
Damien Gallop | | | 17O3+ beam to DRAGON | Beam delivery continued through the weekend.
As noted on Saturday, current dropped precipitously
due to source gas pressure. We have 2.3e-6eµA |
|
182
|
Sat Nov 7 12:21:35 2009 |
Keerthi Jayamanna | | | 17O hand valve status | 17O+3 at FC6 became 550nA.
17O hand valve found to be closed.
Probable cause may be the cold weather. |
|
181
|
Fri Nov 6 11:17:54 2009 |
Damien Gallop | | | 17O3+ setup to DRAGON | As noted, we handed over the beam to our
users yesterday by noon. Setup to DRAGON
is continuing. The report this morning that |
|
180
|
Thu Nov 5 09:45:03 2009 |
Damien Gallop | | | MCIS online with 17O3+ on FC6 overnight | Beam was quiet overnight. Keerthi touched
up the tune this morning, and it is quieter
yet and a little more of it too. |
|
179
|
Wed Nov 4 09:46:07 2009 |
Damien Gallop | | | MCIS online with 17O3+ on FC6 for development | Beam stayed up overnight nicely. Development
today. RF scans in progress now.
Later... scanning done for the moment. |
9x |
178
|
Tue Nov 3 09:25:31 2009 |
Damien Gallop | | | MCIS online with 17O3+ on FC6 overnight | We completed 33S operation last night,
and roughed in a setup for 17O. We had 17O3+
on FC6 overnight; chart attached. It grew |
|
177
|
Mon Nov 2 17:42:54 2009 |
Damien Gallop | | | MCIS online with 17O3+ on FC6 | As noted earlier, we have opened the OLIS
cage and set up the source gases for 17O
operation. It will take a while for the SO2 |
|
176
|
Mon Nov 2 09:32:40 2009 |
Damien Gallop | | | MCIS on with 33S5+ on FC6 over the weekend | Beam came up nicely on Friday, and
stayed up quuietly over the weekend. Note
the absence of periodic spikes in the separator |
   |
175
|
Fri Oct 30 09:44:49 2009 |
Damien Gallop | | | MCIS on with 33S5+ on FC6 overnight | Controls finished with IOSIOC work yesterday.
ICR had restored most optics. I restarted
the source last evening. As you can see below, |
   |
174
|
Thu Oct 29 09:42:23 2009 |
Damien Gallop | | | IOSIOC work in progress | Yesterday there was an IOSIOC reboot for
a purpose. It was an opportunity to demonstrate
to Controls that IOSIOC reboots materially |
|